Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long10 marks

A run-of-river hydropower scheme is proposed on a Himalayan stream. The catchment yields the following mean monthly discharges (in m³/s):

MonthJFMAMJJlAuSOND
Q181412112045809570402822

The gross head available at the site is H=120 mH = 120\ \text{m} and the overall plant efficiency is η=0.82\eta = 0.82.

(a) Construct the flow-duration curve (on a monthly basis) and determine the discharge available for at least 8 months of the year (≈ 67 % dependability).

(b) Estimate the firm (continuous) power corresponding to this dependable discharge.

(c) Estimate the average annual energy (in GWh) the plant could generate if it could use the full mean monthly flows up to a turbine rated capacity equal to the design discharge of Qd=45 m3/sQ_d = 45\ \text{m}^3/\text{s} (spill the excess).

(d) Comment on why run-of-river plants in Nepal exhibit large seasonal energy variation.

(a) Flow-duration curve and 8-month dependable discharge

Rank the 12 monthly discharges in descending order and assign exceedance percentage P=mN+1×100P = \dfrac{m}{N+1}\times100 where N=12N=12:

Rank mQ (m³/s)P = m/13 ×100 (%)
1957.7
28015.4
37023.1
44530.8
54038.5
62846.2
72253.8
82061.5
91869.2
101476.9
111284.6
121192.3

The flow that is equalled or exceeded for at least 8 of the 12 months is the 8th-ranked value, i.e. the discharge available 8 months/year:

Q8=20 m3/s(61.5% exceedance8/12=67%)Q_{8} = 20\ \text{m}^3/\text{s} \quad (\approx 61.5\% \text{ exceedance} \approx 8/12 = 67\%)

(b) Firm power

P=ρgQHηP = \rho\, g\, Q\, H\, \eta P=1000×9.81×20×120×0.82P = 1000 \times 9.81 \times 20 \times 120 \times 0.82 P=9.81×20=196.2; ×120=23,544; ×0.82=19,306.08 kWP = 9.81\times20 = 196.2;\ \times120 = 23{,}544;\ \times0.82 = 19{,}306.08\ \text{kW} Pfirm19.31 MW\boxed{P_{firm} \approx 19.31\ \text{MW}}

(c) Average annual energy (turbine capped at Qd=45Q_d = 45 m³/s)

Usable monthly discharge Qu=min(Qmonth,45)Q_u = \min(Q_{month}, 45):

MonthQQ_u (≤45)
J1818
F1414
M1212
A1111
M2020
J4545
Jl8045
Au9545
S7045
O4040
N2828
D2222

Sum of usable discharges =18+14+12+11+20+45+45+45+45+40+28+22=345 m3/s= 18+14+12+11+20+45+45+45+45+40+28+22 = 345\ \text{m}^3/\text{s}.

Mean usable discharge Qˉu=345/12=28.75 m3/s\bar Q_u = 345/12 = 28.75\ \text{m}^3/\text{s}.

Average power:

Pˉ=ρgQˉuHη=1000×9.81×28.75×120×0.82\bar P = \rho g \bar Q_u H \eta = 1000\times9.81\times28.75\times120\times0.82 =9.81×28.75=282.0375; ×120=33,844.5; ×0.82=27,752.49 kW27.75 MW= 9.81\times28.75 = 282.0375;\ \times120 = 33{,}844.5;\ \times0.82 = 27{,}752.49\ \text{kW} \approx 27.75\ \text{MW}

Annual energy (8760 h/yr):

E=Pˉ×8760=27,752.49 kW×8760 h=243,11×103 kWhE = \bar P \times 8760 = 27{,}752.49\ \text{kW} \times 8760\ \text{h} = 243{,}11\times10^{3}\ \text{kWh} E=2.4311×108 kWh=243.1 GWhE = 2.4311\times10^{8}\ \text{kWh} = 243.1\ \text{GWh} E243 GWh/year\boxed{E \approx 243\ \text{GWh/year}}

(d) Nepal's rivers are snow- and monsoon-fed: roughly 80 % of annual flow occurs in the wet months (Jun–Sep). In the dry season flows drop to a small fraction of the peak (here 11 vs 95 m³/s, a ~9:1 ratio). A run-of-river plant has negligible storage, so generation tracks the natural hydrograph — full output during monsoon and only firm (low) output in winter. This is why RoR projects sell large secondary (wet-season) energy but provide modest firm power, and why peaking-reserve / storage projects are needed for dry-season security.

hydropower-potentialflow-duration-curvefirm-power
2long9 marks

A settling basin is to be designed for a run-of-river plant carrying a design discharge of Q=12 m3/sQ = 12\ \text{m}^3/\text{s}. The basin must trap all suspended particles with diameter 0.30 mm\ge 0.30\ \text{mm} (specific gravity 2.65). The kinematic viscosity of water is ν=1.0×106 m2/s\nu = 1.0\times10^{-6}\ \text{m}^2/\text{s}. Adopt a basin mean flow-through velocity of V=0.25 m/sV = 0.25\ \text{m/s} and a water depth of D=3.5 mD = 3.5\ \text{m}.

(a) Compute the fall (settling) velocity ww of the design particle. Use Stokes' law and check its validity with the particle Reynolds number; if invalid, use an appropriate transition-range value.

(b) Determine the required basin length and width for ideal (non-turbulent) settling.

(c) Apply a turbulence correction factor and comment.

(a) Fall velocity of a 0.30 mm particle

Stokes' law (laminar, valid for Rep<1Re_p < 1):

w=g(s1)d218νw = \frac{g\,(s-1)\,d^2}{18\,\nu}

with g=9.81g = 9.81, s=2.65s = 2.65, d=0.30×103 md = 0.30\times10^{-3}\ \text{m}, ν=1.0×106\nu = 1.0\times10^{-6}:

w=9.81(1.65)(0.30×103)218×1.0×106=9.81×1.65×9.0×1081.8×105w = \frac{9.81\,(1.65)\,(0.30\times10^{-3})^2}{18\times1.0\times10^{-6}} = \frac{9.81\times1.65\times9.0\times10^{-8}}{1.8\times10^{-5}} =1.4568×1061.8×105=0.0809 m/s= \frac{1.4568\times10^{-6}}{1.8\times10^{-5}} = 0.0809\ \text{m/s}

Check particle Reynolds number:

Rep=wdν=0.0809×0.30×1031.0×106=24.3Re_p = \frac{w\,d}{\nu} = \frac{0.0809\times0.30\times10^{-3}}{1.0\times10^{-6}} = 24.3

Since Rep=24.31Re_p = 24.3 \gg 1, Stokes' law is not valid (we are in the transition range). Use a transition-range estimate. A commonly adopted design value for a 0.30 mm sand grain (the empirical settling chart / Sudry / Scobey curves) is:

w0.035 m/s\boxed{w \approx 0.035\ \text{m/s}}

(Stokes badly over-predicts because form drag is neglected. Equivalently the transition drag relation CD18.5Rep0.6C_D \approx 18.5\,Re_p^{-0.6} gives ww on the order of 0.03–0.04 m/s for this grain size.)

(b) Basin dimensions (ideal settling)

Water must travel down depth DD in the same time it travels along length LL:

Dw=LV    L=VDw\frac{D}{w} = \frac{L}{V} \;\Rightarrow\; L = \frac{V\,D}{w} L=0.25×3.50.035=0.8750.035=25.0 mL = \frac{0.25\times3.5}{0.035} = \frac{0.875}{0.035} = 25.0\ \text{m}

Required flow cross-section (continuity Q=VA=VBDQ = V\,A = V\,B\,D):

B=QVD=120.25×3.5=120.875=13.7 mB = \frac{Q}{V\,D} = \frac{12}{0.25\times3.5} = \frac{12}{0.875} = 13.7\ \text{m} L25 m,B13.7 m,D=3.5 m\boxed{L \approx 25\ \text{m}, \quad B \approx 13.7\ \text{m}, \quad D = 3.5\ \text{m}}

(c) Turbulence correction

Real flow is turbulent, so an effective (reduced) fall velocity w=wΔww' = w - \Delta w is used. A simple Camp/Vetter correction multiplies length by a factor λ\lambda (typically 1.2–1.5). Taking λ=1.4\lambda = 1.4:

Ldesign=1.4×25.0=35 mL_{design} = 1.4 \times 25.0 = 35\ \text{m}

Thus provide L35 mL \approx 35\ \text{m}, B13.7 mB \approx 13.7\ \text{m} (often split into 2–3 parallel chambers ≈ 5 m wide each for hydraulic stability and flushing). The basin should include a transition zone, a sloped flushing channel, and a periodic/continuous flushing arrangement, because Himalayan rivers carry very high sediment loads, especially abrasive quartz, that would otherwise erode the turbine runners.

settling-basinsedimentintake
3long8 marks

A simple cylindrical surge tank is provided at the downstream end of a low-pressure headrace tunnel of a hydropower plant. The headrace tunnel has length L=800 mL = 800\ \text{m}, cross-sectional area At=9.0 m2A_t = 9.0\ \text{m}^2, and the surge tank cross-sectional area is As=40 m2A_s = 40\ \text{m}^2. The steady design discharge is Q=18 m3/sQ = 18\ \text{m}^3/\text{s}.

Neglecting tunnel friction (frictionless analysis), for a sudden complete load rejection (full flow stopped at the tank):

(a) Derive / state the expression for the maximum upsurge above the static reservoir level and compute it.

(b) Compute the period of the mass oscillation.

(c) Briefly explain the function of a surge tank and one situation where a restricted-orifice tank is preferred.

(a) Maximum upsurge (frictionless)

Tunnel velocity at design flow:

V0=QAt=189.0=2.0 m/sV_0 = \frac{Q}{A_t} = \frac{18}{9.0} = 2.0\ \text{m/s}

For a simple surge tank with no friction, energy conservation between the kinetic energy of the tunnel water column and the potential energy of the raised water in the tank gives the maximum surge amplitude:

Zmax=V0LAtgAsZ_{max} = V_0\sqrt{\frac{L\,A_t}{g\,A_s}} LAtgAs=800×9.09.81×40=7200392.4=18.349 s2\frac{L\,A_t}{g\,A_s} = \frac{800\times9.0}{9.81\times40} = \frac{7200}{392.4} = 18.349\ \text{s}^2 18.349=4.283 s\sqrt{18.349} = 4.283\ \text{s} Zmax=2.0×4.283=8.57 mZ_{max} = 2.0\times4.283 = 8.57\ \text{m} Zmax8.57 m above static level\boxed{Z_{max} \approx 8.57\ \text{m above static level}}

(b) Period of mass oscillation

The undamped (frictionless) mass oscillation is simple harmonic with period:

T=2πLAsgAtT = 2\pi\sqrt{\frac{L\,A_s}{g\,A_t}} LAsgAt=800×409.81×9.0=3200088.29=362.44 s2\frac{L\,A_s}{g\,A_t} = \frac{800\times40}{9.81\times9.0} = \frac{32000}{88.29} = 362.44\ \text{s}^2 362.44=19.038 s\sqrt{362.44} = 19.038\ \text{s} T=2π×19.038=119.6 sT = 2\pi\times19.038 = 119.6\ \text{s} T120 s  (2.0 min)\boxed{T \approx 120\ \text{s} \;(\approx 2.0\ \text{min})}

(c) Function and choice

A surge tank is a free water surface installed between the headrace tunnel and the penstock. Its functions are: (i) to protect the long pressure tunnel from water-hammer by reflecting the pressure waves (it converts a sudden flow change into a slow mass oscillation), (ii) to provide a ready supply / storage of water to the turbine during load demand increases, and (iii) to improve speed regulation.

A restricted-orifice (throttled) surge tank is preferred where it is desirable to introduce additional damping and to develop a retarding head quickly: the orifice creates a head loss that damps oscillations faster and reduces the tank size and surge amplitude, useful for plants with frequent load changes or where a tall simple tank would be uneconomic.

surge-tankwater-hammerheadrace
4long8 marks

A steel penstock conveys water to a powerhouse. Penstock length L=450 mL = 450\ \text{m}, design discharge Q=18 m3/sQ = 18\ \text{m}^3/\text{s}, net head H=250 mH = 250\ \text{m}. The pressure wave (celerity) in the penstock is a=1000 m/sa = 1000\ \text{m/s}.

(a) For an economic flow velocity of about 4.0 m/s4.0\ \text{m/s}, determine the penstock diameter (round to a sensible value).

(b) Using the diameter from (a), find the flow velocity and the water-hammer pressure rise for an instantaneous (sudden) gate closure (Joukowsky). Express it as a head and as a percentage of the net head.

(c) Compute the critical (pipe-period) closure time Tc=2L/aT_c = 2L/a and state the criterion that distinguishes sudden from gradual closure.

(a) Penstock diameter

From continuity Q=VA=Vπ4D2Q = V\,A = V\,\dfrac{\pi}{4}D^2, with target V4.0V \approx 4.0 m/s:

D=4QπV=4×18π×4.0=7212.566=5.730=2.394 mD = \sqrt{\frac{4Q}{\pi V}} = \sqrt{\frac{4\times18}{\pi\times4.0}} = \sqrt{\frac{72}{12.566}} = \sqrt{5.730} = 2.394\ \text{m}

Adopt a standard diameter D=2.4 m\boxed{D = 2.4\ \text{m}}.

(b) Actual velocity and Joukowsky pressure rise

Area A=π4(2.4)2=0.7854×5.76=4.5239 m2A = \dfrac{\pi}{4}(2.4)^2 = 0.7854\times5.76 = 4.5239\ \text{m}^2.

V=QA=184.5239=3.979 m/sV = \frac{Q}{A} = \frac{18}{4.5239} = 3.979\ \text{m/s}

Joukowsky (instantaneous closure) pressure rise:

Δp=ρaVΔH=aVg\Delta p = \rho\,a\,V \quad\Rightarrow\quad \Delta H = \frac{a\,V}{g} ΔH=1000×3.9799.81=39799.81=405.6 m\Delta H = \frac{1000\times3.979}{9.81} = \frac{3979}{9.81} = 405.6\ \text{m}

As a pressure: Δp=ρaV=1000×1000×3.979=3.979×106 Pa=3.98 MPa39.8 bar\Delta p = \rho a V = 1000\times1000\times3.979 = 3.979\times10^{6}\ \text{Pa} = 3.98\ \text{MPa} \approx 39.8\ \text{bar}.

As a percentage of net head:

ΔHH=405.6250=1.62=162%\frac{\Delta H}{H} = \frac{405.6}{250} = 1.62 = 162\% ΔH406 m  (162% of net head)\boxed{\Delta H \approx 406\ \text{m} \;(\approx 162\% \text{ of net head})}

This very large surge (the total transient head reaches 250+406=656250 + 406 = 656 m) shows why instantaneous closure must never be allowed; gate closure is slowed and/or a surge tank/relief valve provided.

(c) Critical closure time and criterion

Tc=2La=2×4501000=0.90 sT_c = \frac{2L}{a} = \frac{2\times450}{1000} = 0.90\ \text{s}

Criterion:

  • If the gate closing time TcloseTc=2L/aT_{close} \le T_c = 2L/a, the closure is sudden (rapid); the full Joukowsky head aVg\dfrac{aV}{g} develops and the pipe must be designed for it.
  • If Tclose>2L/aT_{close} > 2L/a, the closure is gradual (slow); the pressure rise is smaller and may be estimated by formulae such as Allievi's, since the returning negative wave partially relieves the pressure before closure completes.
penstockwater-hammereconomic-diameter
5long9 marks

A hydropower plant has a net head H=250 mH = 250\ \text{m} and a design discharge Q=18 m3/sQ = 18\ \text{m}^3/\text{s}. The plant is to use two identical units. The generator is to run at a synchronous speed corresponding to a 50 Hz50\ \text{Hz} system. Take turbine efficiency η=0.90\eta = 0.90.

(a) Compute the power per unit and the total plant capacity.

(b) Recommend a suitable turbine type for this head and justify using the specific-speed concept. Choose a number of generator poles and the resulting synchronous speed.

(c) Compute the dimensionless / metric specific speed NsN_s (in terms of power) for one unit at your chosen speed and confirm it lies in the recommended range for the selected turbine.

(a) Power

Total hydraulic-to-shaft power available:

Ptotal=ρgQHη=1000×9.81×18×250×0.90P_{total} = \rho g Q H \eta = 1000\times9.81\times18\times250\times0.90 =9.81×18=176.58; ×250=44,145; ×0.90=39,730.5 kW39.73 MW= 9.81\times18 = 176.58;\ \times250 = 44{,}145;\ \times0.90 = 39{,}730.5\ \text{kW} \approx 39.73\ \text{MW}

With two identical units, power per unit:

Punit=39,730.52=19,865 kW19.87 MWP_{unit} = \frac{39{,}730.5}{2} = 19{,}865\ \text{kW} \approx 19.87\ \text{MW} Punit19.87 MW,Ptotal39.73 MW\boxed{P_{unit}\approx19.87\ \text{MW},\quad P_{total}\approx39.73\ \text{MW}}

(b) Turbine selection and synchronous speed

A net head of 250 m is a high head. Reaction turbines (Francis) are typically used up to ~300–350 m, and Pelton impulse turbines for very high heads (>250–300 m). At 250 m both are candidates; for a high-head, moderate-discharge site with abrasive Himalayan sediment, a Pelton turbine (or a high-head Francis) is appropriate. We select a Pelton turbine because sediment-laden water at high head favours the more easily maintained/replaceable impulse runner and buckets.

Synchronous speed: N=120fpN = \dfrac{120 f}{p} with f=50f = 50 Hz. Choosing p=12p = 12 poles:

N=120×5012=500 rpmN = \frac{120\times50}{12} = 500\ \text{rpm}

(c) Specific speed (power-based, metric)

Ns=NPH5/4(P in kW, H in m, N in rpm)N_s = \frac{N\sqrt{P}}{H^{5/4}}\qquad (P\text{ in kW},\ H\text{ in m},\ N\text{ in rpm})

For one unit, P=19,865P = 19{,}865 kW:

P=19865=140.9\sqrt{P} = \sqrt{19865} = 140.9 H5/4=2501.25:ln250=5.5215, ×1.25=6.9019, e6.9019=994.0H^{5/4} = 250^{1.25}: \ln 250 = 5.5215,\ \times1.25 = 6.9019,\ e^{6.9019} = 994.0 Ns=500×140.9994.0=70,450994.0=70.9N_s = \frac{500\times140.9}{994.0} = \frac{70{,}450}{994.0} = 70.9 Ns71 (metric, single-jet basis)\boxed{N_s \approx 71\ \text{(metric, single-jet basis)}}

For a single-jet Pelton the recommended NsN_s range is roughly 10–35; Ns71N_s \approx 71 is too high for one jet, which means a multi-jet Pelton is implied. Using a Pelton with nn jets, the per-jet specific speed is Ns,jet=Ns/nN_{s,jet}=N_s/\sqrt{n}. With n=4n = 4 jets:

Ns,jet=714=35.5N_{s,jet} = \frac{71}{\sqrt{4}} = 35.5

which falls at the upper edge of the Pelton range, confirming a 4-jet vertical Pelton unit at 500 rpm is feasible. (Alternatively, Ns71N_s\approx71 lies squarely in the medium-head Francis range of about 60–150, so a Francis turbine at 250 m is equally defensible — either selection is accepted if justified.)

turbine-selectionspecific-speedpowerhouse
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short5 marks

Classify hydropower plants on the basis of (i) head, (ii) the way water is used/operated, and (iii) capacity. Give the typical head/capacity ranges and one Nepali example for two of your categories.

(i) Classification by head

  • Low head: H<30 mH < 30\ \text{m} — usually large discharge, Kaplan/propeller turbines.
  • Medium head: 30 mH250 m30\ \text{m} \le H \le 250\ \text{m} — Francis turbines typical.
  • High head: H>250 mH > 250\ \text{m} — Pelton (impulse) turbines, small discharge. (Different texts use slightly different cut-offs, e.g. low <15 m, high >70/300 m.)

(ii) Classification by way of operation / water use

  • Run-of-river (RoR): no/negligible storage; generation follows river flow (e.g. Marsyangdi, Kaligandaki-A in Nepal are large RoR/peaking-RoR plants).
  • Storage (reservoir) plants: a dam stores wet-season flow for dry-season/peak use (e.g. Kulekhani — Nepal's only major reservoir plant).
  • Pumped-storage plants: pump water to an upper reservoir during off-peak, generate during peak.
  • Peaking RoR (PRoR): small pondage to meet daily peak.

(iii) Classification by capacity (Nepal convention)

  • Micro: up to 100 kW.
  • Mini: 100 kW – 1 MW.
  • Small: 1 – 25 MW (sometimes up to 10 MW in older definitions).
  • Medium: 25 – 300 MW.
  • Large: > 300 MW (e.g. Upper Tamakoshi, 456 MW).

Nepali examples: Kulekhani I (storage, high head ~550 m, 60 MW); Upper Tamakoshi (RoR/peaking, 456 MW); micro-hydro schemes (<100 kW) widely used for rural electrification in hill districts.

plant-typesclassification
7short4 marks

Differentiate between a forebay and a surge tank, and state the conditions under which each is provided. What is the purpose of a forebay's spillway and the freeboard provided to it?

Forebay vs surge tank

FeatureForebaySurge tank
Located onA free-flow (open-channel) headrace system, at the end of the canal before the penstockA pressure (tunnel/pipe) headrace system, between tunnel and penstock
Flow upstreamOpen-channel (atmospheric)Pressurised conduit
Primary roleActs as a small balancing reservoir, distributes/regulates water to the penstock, removes residual sediment and trashControls water-hammer in the long pressure tunnel and supplies water for load changes
Pressure wavesNot the main concernMain design concern

When provided:

  • A forebay is provided when the headrace is an open canal (low-pressure, run-of-river hill schemes).
  • A surge tank is provided when the headrace is a long pressure tunnel/pipe so that water-hammer must be controlled and a free surface created close to the turbine.

Forebay spillway and freeboard:

  • The spillway safely discharges the excess water that arrives when the turbine load is suddenly reduced/rejected (the canal keeps bringing flow but the penstock takes less), preventing overtopping and protecting the structure.
  • The freeboard is the vertical margin between the normal/maximum water level and the top of the forebay walls; it accommodates surges, wave action and the temporary rise on load rejection so the forebay does not overflow uncontrollably.
forebayheadracecanal
8short5 marks

A Francis turbine has a critical Thoma cavitation coefficient σc=0.12\sigma_c = 0.12. The net head is H=80 mH = 80\ \text{m}, atmospheric pressure head Ha=10.3 mH_a = 10.3\ \text{m} and vapour pressure head Hv=0.24 mH_v = 0.24\ \text{m} (water). Determine the maximum permissible suction (draft) height HsH_s above the tailwater for cavitation-free operation, and explain the role of the draft tube.

Maximum suction height

Thoma's cavitation coefficient:

σ=HaHvHsH\sigma = \frac{H_a - H_v - H_s}{H}

For cavitation-free operation σσc\sigma \ge \sigma_c, so the limiting (maximum) suction head is when σ=σc\sigma = \sigma_c:

Hs=(HaHv)σcHH_s = (H_a - H_v) - \sigma_c\,H Hs=(10.30.24)0.12×80H_s = (10.3 - 0.24) - 0.12\times80 Hs=10.069.60=0.46 mH_s = 10.06 - 9.60 = 0.46\ \text{m} Hs,max0.46 m above tailwater\boxed{H_{s,max} \approx 0.46\ \text{m above tailwater}}

The value is small and positive, so the runner may be set only about 0.46 m above the tailwater. In practice, to provide a margin against cavitation it is safer to set the runner at or slightly below tailwater level (negative HsH_s), which increases σ\sigma and the safety margin.

Role of the draft tube

The draft tube is a gradually diverging conduit connecting the runner exit to the tailrace. Its functions are:

  1. Recovers kinetic energy of the water leaving the runner by converting velocity head into pressure head (its diverging shape decelerates the flow), thereby increasing the effective head/efficiency.
  2. Recovers the suction (draft) head HsH_s, allowing the turbine to be installed above tailwater level while still using the full head down to tailrace.
  3. By creating sub-atmospheric pressure at the runner outlet it must be designed so that the pressure does not fall to the vapour pressure — hence the cavitation (Thoma) limit above governs the permissible setting.
turbinecavitationdraft-tube
9short5 marks

A hydropower project has an installed capacity of 20 MW20\ \text{MW} and generates an annual energy of 110 GWh110\ \text{GWh}. The total capital (investment) cost is NRs. 4.04.0 billion. Annual operation & maintenance cost is 2.5%2.5\% of capital cost. The capital recovery factor (CRF) for the assumed interest rate and life is 0.100.10. The energy is sold at NRs. 8.08.0 per kWh.

(a) Compute the plant capacity factor. (b) Compute the annual cost (CRF-based annualised capital + O&M) and hence the unit generation cost (NRs./kWh). (c) Compute the benefit–cost ratio and comment.

(a) Plant capacity factor

Maximum possible annual energy at full capacity:

Emax=20,000 kW×8760 h=1.752×108 kWh=175.2 GWhE_{max} = 20{,}000\ \text{kW}\times8760\ \text{h} = 1.752\times10^{8}\ \text{kWh} = 175.2\ \text{GWh}

Capacity factor:

CF=110175.2=0.628CF = \frac{110}{175.2} = 0.628 CF62.8%\boxed{CF \approx 62.8\%}

(b) Annual cost and unit cost

Annualised capital cost =CRF×capital=0.10×4.0×109=0.40×109=NRs. 400 million= \text{CRF}\times\text{capital} = 0.10\times4.0\times10^{9} = 0.40\times10^{9} = \text{NRs. }400\ \text{million}.

Annual O&M =2.5%×4.0×109=0.025×4.0×109=0.10×109=NRs. 100 million= 2.5\%\times4.0\times10^{9} = 0.025\times4.0\times10^{9} = 0.10\times10^{9} = \text{NRs. }100\ \text{million}.

Total annual cost:

Cannual=400+100=NRs. 500 million=5.0×108 NRs.C_{annual} = 400 + 100 = \text{NRs. }500\ \text{million} = 5.0\times10^{8}\ \text{NRs.}

Unit generation cost:

c=CannualE=5.0×108110×106 kWh=4.545 NRs./kWhc = \frac{C_{annual}}{E} = \frac{5.0\times10^{8}}{110\times10^{6}\ \text{kWh}} = 4.545\ \text{NRs./kWh} cNRs. 4.55 per kWh\boxed{c \approx \text{NRs. }4.55\ \text{per kWh}}

(c) Benefit–cost ratio

Annual revenue (benefit):

B=8.0 NRs./kWh×110×106 kWh=8.8×108=NRs. 880 millionB = 8.0\ \text{NRs./kWh}\times110\times10^{6}\ \text{kWh} = 8.8\times10^{8} = \text{NRs. }880\ \text{million}

Benefit–cost ratio:

B/C=880500=1.76B/C = \frac{880}{500} = 1.76 B/C1.76\boxed{B/C \approx 1.76}

Comment: Since B/C=1.76>1B/C = 1.76 > 1 (equivalently the selling price NRs. 8.0/kWh comfortably exceeds the generation cost NRs. 4.55/kWh), the project is economically viable. The healthy margin gives room for financing risk, hydrological uncertainty and tariff fluctuation.

economicscost-analysisbenefit-cost
10short5 marks

Describe the main types of intakes used in hydropower schemes and list the essential requirements of a good intake. For a trash rack inclined at 70°70° to the horizontal with bars 12 mm thick at 60 mm clear spacing, compute the percentage of gross area blocked by the bars (clogging neglected).

Types of intakes

  • Run-of-river / side (lateral) intake: water drawn from the side of a river or weir pool; common for RoR hill schemes in Nepal.
  • Frontal / canal intake: flow taken frontally into a canal.
  • Reservoir (dam) intake: intake tower or sluice located in the dam/reservoir, often with multiple levels for varying drawdown.
  • Tyrolean / bottom (drop / trench) intake: a bottom rack across the stream bed, suited to steep, sediment- and boulder-laden mountain streams (widely used in Nepal).
  • Shaft / tower intake: vertical shaft intake for deep reservoirs.

Essential requirements of a good intake

  1. Admit the required design discharge with minimum head loss.
  2. Exclude floating debris (trash rack) and bed load / coarse sediment.
  3. Provide control (gates/stoplogs) to regulate or stop flow for maintenance.
  4. Be located to avoid sediment deposition and air entrainment (adequate submergence to prevent vortices).
  5. Be structurally stable and accessible for cleaning/flushing.

Trash-rack area blocked by bars

Consider one bar pitch (one bar + one clear opening) on the rack plane:

pitch=bar thickness+clear spacing=12+60=72 mm\text{pitch} = \text{bar thickness} + \text{clear spacing} = 12 + 60 = 72\ \text{mm}

Fraction of plane occupied by bar metal:

1272=0.1667=16.7%\frac{12}{72} = 0.1667 = 16.7\% ≈ 16.7% of the gross rack area is blocked by bars\boxed{\text{≈ }16.7\%\text{ of the gross rack area is blocked by bars}}

so the net (effective) open area is about 83.3 % of the gross rack area (before any debris clogging). The 70°70° inclination means the rack's gross area normal-to-flow is larger than the flow cross-section by a factor 1/sin70°1.0641/\sin70° \approx 1.064, which is why inclined racks are used — they ease raking and reduce approach-velocity head loss.

intaketrash-rackdesign
11short7 marks

Write short notes on the status and challenges of hydropower development in Nepal. Include: (a) the commonly quoted theoretical, technical and economically-feasible potentials; (b) why most plants are run-of-river; (c) three major technical/financial challenges; and (d) two recent landmark projects.

(a) Hydropower potential of Nepal

  • Theoretical potential: about 83,000 MW (≈ 83 GW), based on the classic study of the runoff and head of Nepal's ~6,000 rivers and rivulets.
  • Technically feasible potential: about 42,000 MW (≈ 42 GW).
  • Economically feasible potential: commonly quoted as about 42,000 MW as well in older studies, with conservative figures around ~43,000 MW technically and a large fraction economically attractive; the installed capacity today is only a small fraction of this (a few thousand MW), so Nepal has developed only a small percentage of its feasible potential.

(b) Why most plants are run-of-river (RoR)

  • Lower capital cost and shorter construction time than storage dams.
  • Less land submergence, fewer resettlement and environmental issues.
  • Suitable steep topography gives high head with small structures.
  • Storage (reservoir) projects need large dams, big investment and complex environmental/social clearances, so very few exist (Kulekhani being the notable exception). The downside is poor dry-season firm power and large seasonal energy variation.

(c) Major challenges

  1. Seasonal flow / dry-season deficit: RoR-dominated system produces surplus in monsoon and shortfall in winter, forcing imports; need for storage and reservoir projects.
  2. High sediment load and geological/seismic risk: abrasive Himalayan sediment erodes turbines; landslides, GLOFs and earthquakes threaten structures and access roads.
  3. Financing, transmission and market constraints: large capital needs, limited domestic capital market, evacuation (transmission line) bottlenecks, and need for cross-border power trade (e.g. export to India/Bangladesh) and reliable PPAs. (Other valid points: difficult terrain/access, governance and licensing delays, environmental flow requirements.)

(d) Recent landmark projects

  • Upper Tamakoshi (456 MW): the country's largest plant (RoR/peaking), a flagship domestically funded project.
  • Kulekhani (I & II, ~92 MW total): Nepal's only major reservoir/storage scheme, providing valuable peaking and dry-season energy. (Also acceptable: Kaligandaki-A 144 MW, Middle Marsyangdi 70 MW, Tanahu/Budhi Gandaki storage projects under development.)
hydropower-nepalpolicypotential

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper 2080?
The full BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2080 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Hydropower Engineering (IOE, CE 755) 2080 paper come with solutions?
Yes. Every question on this Hydropower Engineering (IOE, CE 755) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2080 paper?
The BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2080 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Hydropower Engineering (IOE, CE 755) past paper free?
Yes — reading and attempting this Hydropower Engineering (IOE, CE 755) past paper on Kekkei is completely free.