Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long12 marks

A run-of-river hydropower scheme on a Himalayan tributary has the following firm flow-duration data at the intake. The gross head available is Hg=185 mH_g = 185\ \text{m} and the total head loss through the waterway up to the turbine inlet is 6%6\% of the gross head.

Flow QQ (m3^3/s)Duration (% of time)
12.00 - 30
9.030 - 70
5.070 - 100

Take the combined turbine-generator efficiency η=0.84\eta = 0.84, water density ρ=1000 kg/m3\rho = 1000\ \text{kg/m}^3 and g=9.81 m/s2g = 9.81\ \text{m/s}^2.

(a) Compute the net head and the installed (peak) power if the plant is sized for the Q=12.0 m3/sQ = 12.0\ \text{m}^3/\text{s} flow. (4)

(b) Estimate the mean annual energy generated (GWh) using the step flow-duration curve. (5)

(c) Determine the annual plant capacity (load) factor and comment on what it tells you about a run-of-river plant. (3)

(a) Net head and installed power

Head loss hL=0.06×185=11.1 mh_L = 0.06 \times 185 = 11.1\ \text{m}.

Net head:

Hn=HghL=18511.1=173.9 mH_n = H_g - h_L = 185 - 11.1 = 173.9\ \text{m}

Installed power at Q=12.0 m3/sQ = 12.0\ \text{m}^3/\text{s}:

P=ρgQHnη=1000×9.81×12.0×173.9×0.84P = \rho\, g\, Q\, H_n\, \eta = 1000 \times 9.81 \times 12.0 \times 173.9 \times 0.84 P=1000×9.81×12.0=117720;×173.9=20,471,508;×0.84=17,196,067 WP = 1000 \times 9.81 \times 12.0 = 117720;\quad \times 173.9 = 20{,}471{,}508;\quad \times 0.84 = 17{,}196{,}067\ \text{W}

Installed power 17.20 MW\approx 17.20\ \text{MW}.

(b) Mean annual energy

Power at each flow block (same HnH_n, η\eta, factor k=ρgHnη=9.81×173.9×0.84×1000=1,433,006 W per (m3/s)k = \rho g H_n \eta = 9.81\times173.9\times0.84\times1000 = 1{,}433{,}006\ \text{W per (m}^3/\text{s})):

BlockQQFraction of yearP=kQP=kQ (MW)Hours = fraction×8760\times8760Energy (GWh)
112.00.3017.196262845.19
29.00.4012.897350445.19
35.00.307.165262818.83

Block energies:

  • Block 1: 17.196 MW×2628 h=45,191 MWh=45.19 GWh17.196\ \text{MW} \times 2628\ \text{h} = 45{,}191\ \text{MWh} = 45.19\ \text{GWh}
  • Block 2: 12.897 MW×3504 h=45,191 MWh=45.19 GWh12.897\ \text{MW} \times 3504\ \text{h} = 45{,}191\ \text{MWh} = 45.19\ \text{GWh}
  • Block 3: 7.165 MW×2628 h=18,830 MWh=18.83 GWh7.165\ \text{MW} \times 2628\ \text{h} = 18{,}830\ \text{MWh} = 18.83\ \text{GWh}

Total annual energy:

E=45.19+45.19+18.83=109.21 GWhE = 45.19 + 45.19 + 18.83 = 109.21\ \text{GWh}

Mean annual energy 109.2 GWh\approx 109.2\ \text{GWh}.

(c) Plant (capacity) factor

Maximum possible energy at installed capacity:

Emax=17.196 MW×8760 h=150,637 MWh=150.64 GWhE_{max} = 17.196\ \text{MW} \times 8760\ \text{h} = 150{,}637\ \text{MWh} = 150.64\ \text{GWh} Capacity factor=109.21150.64=0.725\text{Capacity factor} = \frac{109.21}{150.64} = 0.725

Plant capacity factor 0.73\approx 0.73 (72.5%).

Comment: A capacity factor of about 73% is high and typical of a run-of-river (RoR) plant on a river with a relatively steady flow regime. RoR plants have little or no storage, so they cannot shift generation to peak hours; they generate whenever water is available and therefore tend to run at high capacity factors but offer limited peaking/firm-power flexibility compared with reservoir (storage) plants.

hydropower-potentialpower-energyload-factor
2long10 marks

(a) With a neat sketch, explain the functions and the three principal zones (inlet, settling, outlet) of a continuous-flow settling (de-sanding) basin in a Himalayan hydropower scheme, and state why sediment exclusion is critical for the turbines. (4)

(b) Design the plan dimensions of a settling basin to remove all particles of diameter d0.20 mmd \geq 0.20\ \text{mm} from a design discharge of Q=9.0 m3/sQ = 9.0\ \text{m}^3/\text{s}. The fall (settling) velocity for 0.20 mm0.20\ \text{mm} sand is w=0.021 m/sw = 0.021\ \text{m/s}. Adopt a basin flow-through (horizontal) velocity of v=0.30 m/sv = 0.30\ \text{m/s} and a water depth of D=3.0 mD = 3.0\ \text{m}. Compute the required surface area, basin width and the ideal settling length (ignore turbulence). (6)

(a) Settling basin functions and zones

A settling basin reduces the flow velocity so that suspended sediment settles out before water enters the headrace/penstock. Hard quartz sand carried by Himalayan rivers abrades turbine runners, guide vanes and seals; removing particles above a chosen size (commonly 0.2 mm0.2\ \text{mm} for medium-head Pelton/Francis units) protects the plant and reduces maintenance.

   inlet transition      settling (working) zone        outlet
  (flow expands,        (low velocity, particles        (weir / sill,
   velocity drops)       settle to hopper)               clear water out)
  ====\                                                   /====
       \____________________________________________   __/
        :  :   . .  .   .  .  .   .  .  .  .  . . .  : :  -> headrace
        :  :__________ sediment collects in hopper __: :
        flushing gate / sluice at bottom for periodic flushing

Three zones:

  • Inlet (transition) zone: gradually expands the cross-section so velocity drops uniformly without jets or eddies that would re-suspend sediment.
  • Settling (working) zone: long, wide, shallow-velocity region where particles fall to a collection hopper; flushing sluices remove deposits.
  • Outlet zone: an overflow weir / sill that draws clear surface water into the headrace while leaving deposited sediment behind.

(b) Plan dimensions

Ideal settling theory: a particle entering at the surface must reach the bottom before leaving the basin. The governing relation is the surface-loading (overflow-rate) criterion:

QAsurface=wAsurface=Qw\frac{Q}{A_{surface}} = w \quad\Rightarrow\quad A_{surface} = \frac{Q}{w}

Required surface area:

Asurface=9.00.021=428.6 m2A_{surface} = \frac{9.0}{0.021} = 428.6\ \text{m}^2

Basin width from continuity (cross-section =B×D= B \times D carries QQ at velocity vv):

B=QvD=9.00.30×3.0=9.00.90=10.0 mB = \frac{Q}{v\,D} = \frac{9.0}{0.30 \times 3.0} = \frac{9.0}{0.90} = 10.0\ \text{m}

Settling length from surface area:

L=AsurfaceB=428.610.0=42.9 mL = \frac{A_{surface}}{B} = \frac{428.6}{10.0} = 42.9\ \text{m}

Cross-check by the fall-time / horizontal-travel method: time to settle t=D/w=3.0/0.021=142.9 st = D/w = 3.0/0.021 = 142.9\ \text{s}; horizontal travel L=vt=0.30×142.9=42.9 mL = v\,t = 0.30 \times 142.9 = 42.9\ \text{m} (consistent).

Required surface area 429 m2\approx 429\ \text{m}^2, width B=10.0 mB = 10.0\ \text{m}, ideal length L42.9 mL \approx 42.9\ \text{m}. In practice a turbulence/safety factor of about 1.2-1.5 is applied, giving an adopted length of roughly 5252-64 m64\ \text{m}.

settling-basinintakesediment
3long12 marks

A steel penstock of length L=520 mL = 520\ \text{m} conveys Q=9.0 m3/sQ = 9.0\ \text{m}^3/\text{s} under a static head of H=173.9 mH = 173.9\ \text{m} to a single turbine. The pressure-wave celerity in the pipe is a=1100 m/sa = 1100\ \text{m/s} and the valve effective closure time is T=4.0 sT = 4.0\ \text{s}.

(a) Determine whether the closure is rapid or slow, and compute the water-hammer pressure rise: use the Joukowsky equation for rapid closure or the Michaud (Allievi slow-closure) formula as appropriate. Assume a pipe diameter d=2.0 md = 2.0\ \text{m}. (6)

(b) State the surge (max) head the penstock must be designed for, and compute the required wall thickness using the thin-cylinder formula with allowable hoop stress σallow=120 MPa\sigma_{allow} = 120\ \text{MPa} and a joint efficiency of 0.900.90. Take g=9.81 m/s2g = 9.81\ \text{m/s}^2, ρ=1000 kg/m3\rho = 1000\ \text{kg/m}^3. (6)

(a) Rapid vs slow closure and pressure rise

Critical (round-trip) time of the pressure wave:

Tc=2La=2×5201100=10401100=0.945 sT_c = \frac{2L}{a} = \frac{2 \times 520}{1100} = \frac{1040}{1100} = 0.945\ \text{s}

Since the closure time T=4.0 s>Tc=0.945 sT = 4.0\ \text{s} > T_c = 0.945\ \text{s}, the closure is slow. Use the Michaud (slow-closure) formula.

Flow velocity:

A=π4d2=π4(2.0)2=3.1416 m2,V=QA=9.03.1416=2.865 m/sA = \frac{\pi}{4}d^2 = \frac{\pi}{4}(2.0)^2 = 3.1416\ \text{m}^2,\qquad V = \frac{Q}{A} = \frac{9.0}{3.1416} = 2.865\ \text{m/s}

Michaud head rise:

ΔH=2LVgT=2×520×2.8659.81×4.0=2979.639.24=75.9 m\Delta H = \frac{2 L V}{g\,T} = \frac{2 \times 520 \times 2.865}{9.81 \times 4.0} = \frac{2979.6}{39.24} = 75.9\ \text{m}

Water-hammer (surge) head rise ΔH75.9 m\Delta H \approx 75.9\ \text{m}. (For comparison, full Joukowsky rapid closure would give aV/g=1100×2.865/9.81=321.3 maV/g = 1100\times2.865/9.81 = 321.3\ \text{m}, which the slow closure avoids.)

(b) Design surge head and wall thickness

Maximum head the penstock must withstand:

Hmax=H+ΔH=173.9+75.9=249.8 mH_{max} = H + \Delta H = 173.9 + 75.9 = 249.8\ \text{m}

Internal pressure:

p=ρgHmax=1000×9.81×249.8=2,450,538 Pa=2.451 MPap = \rho g H_{max} = 1000 \times 9.81 \times 249.8 = 2{,}450{,}538\ \text{Pa} = 2.451\ \text{MPa}

Thin-cylinder hoop stress with joint efficiency ηj\eta_j:

σ=pd2tηj    t=pd2σallowηj\sigma = \frac{p\,d}{2\,t\,\eta_j} \;\Rightarrow\; t = \frac{p\,d}{2\,\sigma_{allow}\,\eta_j} t=2.451×106×2.02×120×106×0.90=4.902×1062.16×108=0.02269 mt = \frac{2.451\times10^6 \times 2.0}{2 \times 120\times10^6 \times 0.90} = \frac{4.902\times10^6}{2.16\times10^8} = 0.02269\ \text{m} t=22.7 mmt = 22.7\ \text{mm}

Adding a corrosion allowance of about 1.5 mm1.5\ \text{mm} gives an adopted plate thickness of roughly 24 mm24\ \text{mm}.

Design surge head Hmax249.8 mH_{max} \approx 249.8\ \text{m}; required wall thickness t22.7 mmt \approx 22.7\ \text{mm} (adopt 24 mm\approx 24\ \text{mm}).

penstockwater-hammereconomic-diameter
4long10 marks

A hydropower plant develops a turbine output of P=16,000 kWP = 16{,}000\ \text{kW} under a net head of H=173.9 mH = 173.9\ \text{m} and runs at a synchronous speed N=600 rpmN = 600\ \text{rpm}.

(a) Compute the specific speed NsN_s (in metric units, Ns=NPH5/4N_s = \dfrac{N\sqrt{P}}{H^{5/4}} with PP in kW) and select the appropriate turbine type, justifying the choice against the usual head and NsN_s ranges. (5)

(b) For the same head, explain with reasoning how the choice of turbine would change if the discharge were very large (low head, high flow), and sketch (in text) the typical operating ranges of Pelton, Francis and Kaplan turbines on a head-vs-specific-speed basis. (5)

(a) Specific speed and turbine selection

Ns=NPH5/4=60016000173.91.25N_s = \frac{N\sqrt{P}}{H^{5/4}} = \frac{600\sqrt{16000}}{173.9^{1.25}}

Numerator: 16000=126.49\sqrt{16000} = 126.49, so 600×126.49=75,895600 \times 126.49 = 75{,}895.

Denominator: 173.91.25173.9^{1.25}. ln173.9=5.1585\ln 173.9 = 5.1585; ×1.25=6.4481\times 1.25 = 6.4481; e6.4481=631.9e^{6.4481} = 631.9.

Ns=75,895631.9=120.1N_s = \frac{75{,}895}{631.9} = 120.1

Specific speed Ns120N_s \approx 120 (metric, kW).

Selection: With H=173.9 mH = 173.9\ \text{m} (medium-high head) and Ns120N_s \approx 120, the operating point falls squarely in the Francis turbine range. Typical metric specific-speed bands are: Pelton 10\approx 10-3535 (single jet) up to 70\sim 70 (multi-jet), Francis 60\approx 60-400400, Kaplan/propeller 300\approx 300-10001000. A head near 175 m175\ \text{m} with Ns120N_s \approx 120 is well suited to a Francis runner, which gives good efficiency over this medium-head, moderate-flow regime.

(b) Effect of large discharge / low head, and operating ranges

If the discharge were very large at low head, the same power could only be developed with much higher flow per unit head, which pushes the specific speed up. High NsN_s (above ~300) and low head (below ~50 m) call for an axial-flow Kaplan (or propeller) turbine, whose adjustable blades pass large flows efficiently. Conversely, very high head with small flow lowers NsN_s and favours an impulse Pelton wheel.

Text sketch of operating ranges:

  Head (m)
  ^
 1500 | Pelton (high head, low Ns ~10-70)
      |  \
  500 |   \____ Francis (medium head, Ns ~60-400)
      |        \
  150 |         \______
      |                \___ Kaplan/Propeller (low head, high Ns ~300-1000)
   10 |                      \___________________
      +-------------------------------------------> Specific speed Ns

General rule: as head decreases and flow increases, specific speed rises and the preferred turbine shifts Pelton -> Francis -> Kaplan.

turbinesspecific-speedturbine-selection
5long8 marks

(a) Differentiate between a forebay and a surge tank, stating where each is used in a hydropower waterway and the hydraulic purpose of each. (3)

(b) A simple cylindrical surge tank of cross-sectional area As=60 m2A_s = 60\ \text{m}^2 is provided at the downstream end of a headrace tunnel of length L=2400 mL = 2400\ \text{m} and cross-sectional area At=9.0 m2A_t = 9.0\ \text{m}^2. The steady tunnel velocity before load rejection is V0=1.0 m/sV_0 = 1.0\ \text{m/s}. Neglecting friction, compute the maximum surge amplitude above the reservoir level and the period of oscillation. Take g=9.81 m/s2g = 9.81\ \text{m/s}^2. (5)

(a) Forebay vs surge tank

  • A forebay is an enlarged open basin at the end of a (low-pressure, free-surface) headrace canal, just upstream of the penstock intake. It acts as a small balancing reservoir that supplies water for short-duration demand fluctuations and traps any remaining sediment/trash before the penstock. It is used in canal (open-channel) conveyance schemes.
  • A surge tank is a vertical shaft/chamber on a long pressurized headrace tunnel, placed as close as practicable to the powerhouse. Its purpose is to absorb water-hammer/pressure transients and supply or store water during load changes, protecting the tunnel and reducing penstock surge. It is used in tunnel (pressurized) conveyance schemes.

(b) Surge amplitude and period (frictionless simple surge tank)

For a frictionless simple surge tank, the maximum surge amplitude is:

Zmax=V0LAtgAsZ_{max} = V_0\sqrt{\frac{L\,A_t}{g\,A_s}}

Substituting:

LAtgAs=2400×9.09.81×60=21600588.6=36.70 s2\frac{L\,A_t}{g\,A_s} = \frac{2400 \times 9.0}{9.81 \times 60} = \frac{21600}{588.6} = 36.70\ \text{s}^2 36.70=6.058 s\sqrt{36.70} = 6.058\ \text{s} Zmax=1.0×6.058=6.06 mZ_{max} = 1.0 \times 6.058 = 6.06\ \text{m}

Maximum surge amplitude Zmax6.06 mZ_{max} \approx 6.06\ \text{m} above reservoir level.

Period of (undamped) oscillation:

T=2πLAsgAt=2π2400×609.81×9.0T = 2\pi\sqrt{\frac{L\,A_s}{g\,A_t}} = 2\pi\sqrt{\frac{2400 \times 60}{9.81 \times 9.0}} 2400×609.81×9.0=14400088.29=1631.0 s2,1631.0=40.39 s\frac{2400 \times 60}{9.81 \times 9.0} = \frac{144000}{88.29} = 1631.0\ \text{s}^2,\quad \sqrt{1631.0} = 40.39\ \text{s} T=2π×40.39=253.8 sT = 2\pi \times 40.39 = 253.8\ \text{s}

Period T253.8 sT \approx 253.8\ \text{s} (about 4.24.2 minutes).

surge-tankforebayheadrace
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short4 marks

Classify hydropower plants on the basis of (i) head and (ii) operation/storage, giving the typical head ranges and one example application for each category.

(i) Classification by head:

  • Low head: H<30 mH < 30\ \text{m} — e.g. run-of-river barrage plants on large lowland rivers (Kaplan units).
  • Medium head: 30 mH300 m30\ \text{m} \leq H \leq 300\ \text{m} — e.g. Francis-turbine plants on hill rivers.
  • High head: H>300 mH > 300\ \text{m} — e.g. Pelton-turbine plants fed by long penstocks in steep terrain.

(Exact band limits vary slightly between texts; the medium band is sometimes quoted as 25-250 m.)

(ii) Classification by operation / storage:

  • Run-of-river (RoR): little/no storage; generates with available flow (e.g. most Nepali medium-head plants).
  • Storage (reservoir) plant: a reservoir stores seasonal flow to provide firm/peaking power (e.g. a multi-purpose dam scheme).
  • Pumped-storage plant: pumps water to an upper reservoir during off-peak hours and generates during peak demand, acting as energy storage.

Summary: head governs turbine choice; storage governs how flexibly the plant can meet demand.

plant-typesclassification
7short4 marks

List the major structural and electro-mechanical components housed in a surface powerhouse of a hydropower plant, and briefly state the function of any three of them.

Major components of a surface powerhouse:

Structural / civil:

  • Substructure (draft-tube and turbine foundations, scroll-case block)
  • Intermediate structure (generator floor, control gallery)
  • Superstructure (machine hall, service bay, crane gantry, roof)

Electro-mechanical:

  • Turbines and governors
  • Generators (alternators) with excitation systems
  • Main inlet valves / butterfly or spherical valves
  • Step-up transformers and switchgear/busbars
  • Overhead travelling (EOT) crane
  • Cooling, dewatering, drainage and auxiliary systems
  • Control room / SCADA and protection equipment

Functions of three components:

  1. Turbine: converts the hydraulic energy (head and flow) of water into mechanical shaft power.
  2. Generator: converts the turbine's mechanical rotation into electrical energy.
  3. Main inlet valve: isolates the turbine from the penstock for maintenance and provides emergency shut-off, protecting the unit.
  4. EOT crane: lifts and positions heavy runners, rotors and valves during erection and maintenance.
powerhouselayout
8short5 marks

A trapezoidal unlined-then-lined headrace canal is to carry Q=9.0 m3/sQ = 9.0\ \text{m}^3/\text{s}. The canal is concrete-lined with Manning's n=0.015n = 0.015, bed slope S=0.0005S = 0.0005, bed width b=3.0 mb = 3.0\ \text{m} and side slopes 1:11:1 (H:V). For a flow depth y=1.5 my = 1.5\ \text{m}, compute the discharge using Manning's equation and check whether the depth is adequate. Take the flow as uniform.

Geometry of a trapezoidal section (side slope m=1m = 1, so each side adds mym\,y horizontally):

Area:

A=(b+my)y=(3.0+1×1.5)×1.5=4.5×1.5=6.75 m2A = (b + m y)\,y = (3.0 + 1\times1.5)\times1.5 = 4.5 \times 1.5 = 6.75\ \text{m}^2

Wetted perimeter:

P=b+2y1+m2=3.0+2(1.5)2=3.0+3.0×1.4142=3.0+4.2426=7.243 mP = b + 2y\sqrt{1+m^2} = 3.0 + 2(1.5)\sqrt{2} = 3.0 + 3.0\times1.4142 = 3.0 + 4.2426 = 7.243\ \text{m}

Hydraulic radius:

R=AP=6.757.243=0.9320 mR = \frac{A}{P} = \frac{6.75}{7.243} = 0.9320\ \text{m}

Manning's equation:

Q=1nAR2/3S1/2Q = \frac{1}{n} A R^{2/3} S^{1/2}

R2/3R^{2/3}: ln0.9320=0.07041\ln 0.9320 = -0.07041; ×23=0.04694\times \tfrac{2}{3} = -0.04694; e0.04694=0.9542e^{-0.04694} = 0.9542.

S1/2=0.0005=0.022361S^{1/2} = \sqrt{0.0005} = 0.022361.

Q=10.015×6.75×0.9542×0.022361Q = \frac{1}{0.015}\times 6.75 \times 0.9542 \times 0.022361 =66.667×6.75×0.9542×0.022361= 66.667 \times 6.75 \times 0.9542 \times 0.022361 66.667×6.75=450.0;×0.9542=429.4;×0.022361=9.60 m3/s66.667 \times 6.75 = 450.0;\quad \times 0.9542 = 429.4;\quad \times 0.022361 = 9.60\ \text{m}^3/\text{s}

Computed capacity Q9.60 m3/s>9.0 m3/sQ \approx 9.60\ \text{m}^3/\text{s} > 9.0\ \text{m}^3/\text{s} design discharge.

The section at y=1.5 my = 1.5\ \text{m} carries about 9.6 m3/s9.6\ \text{m}^3/\text{s}, which exceeds the required 9.0 m3/s9.0\ \text{m}^3/\text{s} by roughly 7%7\%, so the depth is adequate and provides a small margin (a freeboard of 0.30.3-0.5 m0.5\ \text{m} should still be added above the water surface).

headraceopen-channelmanning
9short5 marks

A 17.2 MW17.2\ \text{MW} run-of-river plant has a total installed capital cost of NRs 5.16 billion\text{NRs } 5.16\ \text{billion} and generates 109.2 GWh109.2\ \text{GWh} per year. Annual operation and maintenance (O&M) cost is 2.0%2.0\% of the capital cost. The capital is recovered over 2525 years at an annual interest rate of 10%10\%.

(a) Compute the capital recovery factor (CRF) and the annual capital (debt-service) charge. (3)

(b) Compute the levelised generation cost in NRs/kWh\text{NRs/kWh}. (2)

(a) Capital recovery factor and annual capital charge

Capital recovery factor:

CRF=i(1+i)n(1+i)n1,i=0.10, n=25CRF = \frac{i(1+i)^n}{(1+i)^n - 1},\quad i = 0.10,\ n = 25

Compute (1.10)25(1.10)^{25}: ln1.10=0.0953102\ln 1.10 = 0.0953102; ×25=2.382755\times 25 = 2.382755; e2.382755=10.8347e^{2.382755} = 10.8347.

CRF=0.10×10.834710.83471=1.083479.8347=0.11017CRF = \frac{0.10 \times 10.8347}{10.8347 - 1} = \frac{1.08347}{9.8347} = 0.11017

CRF0.1102CRF \approx 0.1102.

Annual capital (debt-service) charge:

=CRF×capital=0.11017×5.16×109=5.685×108 NRs/yr= CRF \times \text{capital} = 0.11017 \times 5.16\times10^9 = 5.685\times10^8\ \text{NRs/yr}

Annual capital charge NRs 568.5 million/yr\approx \text{NRs } 568.5\ \text{million/yr}.

(b) Levelised generation cost

Annual O&M cost:

=0.02×5.16×109=1.032×108 NRs/yr=NRs 103.2 million/yr= 0.02 \times 5.16\times10^9 = 1.032\times10^8\ \text{NRs/yr} = \text{NRs } 103.2\ \text{million/yr}

Total annual cost:

=568.5+103.2=671.7 million NRs/yr=6.717×108 NRs/yr= 568.5 + 103.2 = 671.7\ \text{million NRs/yr} = 6.717\times10^8\ \text{NRs/yr}

Annual energy:

109.2 GWh=109.2×106 kWh109.2\ \text{GWh} = 109.2\times10^6\ \text{kWh}

Levelised cost:

=6.717×108109.2×106=6.151 NRs/kWh= \frac{6.717\times10^8}{109.2\times10^6} = 6.151\ \text{NRs/kWh}

Levelised generation cost NRs 6.15 per kWh\approx \text{NRs } 6.15\ \text{per kWh}.

economicscost-energy
10short5 marks

A single-jet Pelton wheel operates under a net head of H=320 mH = 320\ \text{m}. The nozzle velocity coefficient is Cv=0.98C_v = 0.98 and the jet diameter is d=100 mmd = 100\ \text{mm}. Compute (a) the jet velocity, (b) the jet discharge, and (c) the theoretical hydraulic power of the jet. Take g=9.81 m/s2g = 9.81\ \text{m/s}^2, ρ=1000 kg/m3\rho = 1000\ \text{kg/m}^3.

(a) Jet velocity

V=Cv2gH=0.982×9.81×320V = C_v\sqrt{2 g H} = 0.98\sqrt{2 \times 9.81 \times 320} 2×9.81×320=6278.4;6278.4=79.24 m/s2\times9.81\times320 = 6278.4;\quad \sqrt{6278.4} = 79.24\ \text{m/s} V=0.98×79.24=77.66 m/sV = 0.98 \times 79.24 = 77.66\ \text{m/s}

Jet velocity V77.7 m/sV \approx 77.7\ \text{m/s}.

(b) Jet discharge Jet area:

a=π4d2=π4(0.100)2=7.854×103 m2a = \frac{\pi}{4}d^2 = \frac{\pi}{4}(0.100)^2 = 7.854\times10^{-3}\ \text{m}^2 Q=aV=7.854×103×77.66=0.6100 m3/sQ = a V = 7.854\times10^{-3} \times 77.66 = 0.6100\ \text{m}^3/\text{s}

Jet discharge Q0.610 m3/sQ \approx 0.610\ \text{m}^3/\text{s}.

(c) Theoretical jet (kinetic) power

P=12ρQV2=0.5×1000×0.6100×(77.66)2P = \tfrac{1}{2}\rho Q V^2 = 0.5 \times 1000 \times 0.6100 \times (77.66)^2 (77.66)2=6031.1;0.5×1000×0.6100=305.0;×6031.1=1,839,500 W(77.66)^2 = 6031.1;\quad 0.5\times1000\times0.6100 = 305.0;\quad \times 6031.1 = 1{,}839{,}500\ \text{W}

Theoretical jet power P1.84 MWP \approx 1.84\ \text{MW}.

(Equivalently P=ρgQH×Cv2=1000×9.81×0.610×320×0.9604=1.84 MWP = \rho g Q H \times C_v^2 = 1000\times9.81\times0.610\times320\times0.9604 = 1.84\ \text{MW}, confirming the result.)

turbinespeltonjet-power
11short5 marks

Write short notes on hydropower development in Nepal, covering (a) the theoretical, technical and economically-feasible potential figures commonly cited, and (b) any three major challenges to harnessing this potential.

(a) Hydropower potential of Nepal (commonly cited figures)

  • Theoretical potential: about 83,000 MW83{,}000\ \text{MW} (roughly 83 GW83\ \text{GW}), based on the gross runoff of the country's major river systems (Koshi, Gandaki, Karnali, Mahakali and southern rivers).
  • Technically feasible potential: about 42,000 MW42{,}000\ \text{MW} (~42 GW42\ \text{GW}).
  • Economically feasible potential: about 42,000 MW42{,}000\ \text{MW} is often quoted as technically feasible, with the economically feasible portion commonly cited at roughly the same order; many references state about 42 GW42\ \text{GW} technically and a large fraction of that economically exploitable under current conditions.

Most developed and planned plants in Nepal are run-of-river (medium head, Francis or Pelton), with only a few storage schemes, leading to a marked seasonal generation deficit in the dry months.

(b) Three major challenges

  1. Seasonal flow variability: monsoon-dominated hydrology gives high wet-season flows and very low dry-season flows; with mostly RoR plants and little storage, the country faces winter energy deficits and surplus in the wet season.
  2. Difficult terrain, geology and sediment: steep, fragile Himalayan terrain, landslides, glacial-lake outburst flood (GLOF) risk and very high sediment loads raise construction cost and cause turbine abrasion.
  3. Financing, transmission and market constraints: high up-front capital cost, limited domestic financing, weak/insufficient transmission and cross-border evacuation infrastructure, and the need for power-trade agreements (e.g. export to India/Bangladesh) to absorb wet-season surplus.

(Other valid challenges: geopolitical/transboundary water issues, right-of-way and resettlement, and institutional/regulatory delays.)

hydropower-in-nepalpolicypotential

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper 2079?
The full BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2079 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Hydropower Engineering (IOE, CE 755) 2079 paper come with solutions?
Yes. Every question on this Hydropower Engineering (IOE, CE 755) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2079 paper?
The BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2079 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Hydropower Engineering (IOE, CE 755) past paper free?
Yes — reading and attempting this Hydropower Engineering (IOE, CE 755) past paper on Kekkei is completely free.