BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) Question Paper 2079 Nepal
This is the official BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper for 2079, as set in the regular annual examination. It carries 80 full marks and a time allowance of 180 minutes, across 11 questions. On Kekkei you can attempt this Hydropower Engineering (IOE, CE 755) past paper online with a timer, get instant AI feedback and step-by-step solutions, and track the topics where you lose marks — completely free. Whether you are revising for your BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) exam or solving previous years' question papers, this 2079 paper is a great way to practise under real exam conditions.
Section A: Long Answer Questions
Attempt all questions.
A run-of-river hydropower scheme on a Himalayan tributary has the following firm flow-duration data at the intake. The gross head available is and the total head loss through the waterway up to the turbine inlet is of the gross head.
| Flow (m/s) | Duration (% of time) |
|---|---|
| 12.0 | 0 - 30 |
| 9.0 | 30 - 70 |
| 5.0 | 70 - 100 |
Take the combined turbine-generator efficiency , water density and .
(a) Compute the net head and the installed (peak) power if the plant is sized for the flow. (4)
(b) Estimate the mean annual energy generated (GWh) using the step flow-duration curve. (5)
(c) Determine the annual plant capacity (load) factor and comment on what it tells you about a run-of-river plant. (3)
(a) Net head and installed power
Head loss .
Net head:
Installed power at :
Installed power .
(b) Mean annual energy
Power at each flow block (same , , factor ):
| Block | Fraction of year | (MW) | Hours = fraction | Energy (GWh) | |
|---|---|---|---|---|---|
| 1 | 12.0 | 0.30 | 17.196 | 2628 | 45.19 |
| 2 | 9.0 | 0.40 | 12.897 | 3504 | 45.19 |
| 3 | 5.0 | 0.30 | 7.165 | 2628 | 18.83 |
Block energies:
- Block 1:
- Block 2:
- Block 3:
Total annual energy:
Mean annual energy .
(c) Plant (capacity) factor
Maximum possible energy at installed capacity:
Plant capacity factor (72.5%).
Comment: A capacity factor of about 73% is high and typical of a run-of-river (RoR) plant on a river with a relatively steady flow regime. RoR plants have little or no storage, so they cannot shift generation to peak hours; they generate whenever water is available and therefore tend to run at high capacity factors but offer limited peaking/firm-power flexibility compared with reservoir (storage) plants.
(a) With a neat sketch, explain the functions and the three principal zones (inlet, settling, outlet) of a continuous-flow settling (de-sanding) basin in a Himalayan hydropower scheme, and state why sediment exclusion is critical for the turbines. (4)
(b) Design the plan dimensions of a settling basin to remove all particles of diameter from a design discharge of . The fall (settling) velocity for sand is . Adopt a basin flow-through (horizontal) velocity of and a water depth of . Compute the required surface area, basin width and the ideal settling length (ignore turbulence). (6)
(a) Settling basin functions and zones
A settling basin reduces the flow velocity so that suspended sediment settles out before water enters the headrace/penstock. Hard quartz sand carried by Himalayan rivers abrades turbine runners, guide vanes and seals; removing particles above a chosen size (commonly for medium-head Pelton/Francis units) protects the plant and reduces maintenance.
inlet transition settling (working) zone outlet
(flow expands, (low velocity, particles (weir / sill,
velocity drops) settle to hopper) clear water out)
====\ /====
\____________________________________________ __/
: : . . . . . . . . . . . . . : : -> headrace
: :__________ sediment collects in hopper __: :
flushing gate / sluice at bottom for periodic flushing
Three zones:
- Inlet (transition) zone: gradually expands the cross-section so velocity drops uniformly without jets or eddies that would re-suspend sediment.
- Settling (working) zone: long, wide, shallow-velocity region where particles fall to a collection hopper; flushing sluices remove deposits.
- Outlet zone: an overflow weir / sill that draws clear surface water into the headrace while leaving deposited sediment behind.
(b) Plan dimensions
Ideal settling theory: a particle entering at the surface must reach the bottom before leaving the basin. The governing relation is the surface-loading (overflow-rate) criterion:
Required surface area:
Basin width from continuity (cross-section carries at velocity ):
Settling length from surface area:
Cross-check by the fall-time / horizontal-travel method: time to settle ; horizontal travel (consistent).
Required surface area , width , ideal length . In practice a turbulence/safety factor of about 1.2-1.5 is applied, giving an adopted length of roughly -.
A steel penstock of length conveys under a static head of to a single turbine. The pressure-wave celerity in the pipe is and the valve effective closure time is .
(a) Determine whether the closure is rapid or slow, and compute the water-hammer pressure rise: use the Joukowsky equation for rapid closure or the Michaud (Allievi slow-closure) formula as appropriate. Assume a pipe diameter . (6)
(b) State the surge (max) head the penstock must be designed for, and compute the required wall thickness using the thin-cylinder formula with allowable hoop stress and a joint efficiency of . Take , . (6)
(a) Rapid vs slow closure and pressure rise
Critical (round-trip) time of the pressure wave:
Since the closure time , the closure is slow. Use the Michaud (slow-closure) formula.
Flow velocity:
Michaud head rise:
Water-hammer (surge) head rise . (For comparison, full Joukowsky rapid closure would give , which the slow closure avoids.)
(b) Design surge head and wall thickness
Maximum head the penstock must withstand:
Internal pressure:
Thin-cylinder hoop stress with joint efficiency :
Adding a corrosion allowance of about gives an adopted plate thickness of roughly .
Design surge head ; required wall thickness (adopt ).
A hydropower plant develops a turbine output of under a net head of and runs at a synchronous speed .
(a) Compute the specific speed (in metric units, with in kW) and select the appropriate turbine type, justifying the choice against the usual head and ranges. (5)
(b) For the same head, explain with reasoning how the choice of turbine would change if the discharge were very large (low head, high flow), and sketch (in text) the typical operating ranges of Pelton, Francis and Kaplan turbines on a head-vs-specific-speed basis. (5)
(a) Specific speed and turbine selection
Numerator: , so .
Denominator: . ; ; .
Specific speed (metric, kW).
Selection: With (medium-high head) and , the operating point falls squarely in the Francis turbine range. Typical metric specific-speed bands are: Pelton - (single jet) up to (multi-jet), Francis -, Kaplan/propeller -. A head near with is well suited to a Francis runner, which gives good efficiency over this medium-head, moderate-flow regime.
(b) Effect of large discharge / low head, and operating ranges
If the discharge were very large at low head, the same power could only be developed with much higher flow per unit head, which pushes the specific speed up. High (above ~300) and low head (below ~50 m) call for an axial-flow Kaplan (or propeller) turbine, whose adjustable blades pass large flows efficiently. Conversely, very high head with small flow lowers and favours an impulse Pelton wheel.
Text sketch of operating ranges:
Head (m)
^
1500 | Pelton (high head, low Ns ~10-70)
| \
500 | \____ Francis (medium head, Ns ~60-400)
| \
150 | \______
| \___ Kaplan/Propeller (low head, high Ns ~300-1000)
10 | \___________________
+-------------------------------------------> Specific speed Ns
General rule: as head decreases and flow increases, specific speed rises and the preferred turbine shifts Pelton -> Francis -> Kaplan.
(a) Differentiate between a forebay and a surge tank, stating where each is used in a hydropower waterway and the hydraulic purpose of each. (3)
(b) A simple cylindrical surge tank of cross-sectional area is provided at the downstream end of a headrace tunnel of length and cross-sectional area . The steady tunnel velocity before load rejection is . Neglecting friction, compute the maximum surge amplitude above the reservoir level and the period of oscillation. Take . (5)
(a) Forebay vs surge tank
- A forebay is an enlarged open basin at the end of a (low-pressure, free-surface) headrace canal, just upstream of the penstock intake. It acts as a small balancing reservoir that supplies water for short-duration demand fluctuations and traps any remaining sediment/trash before the penstock. It is used in canal (open-channel) conveyance schemes.
- A surge tank is a vertical shaft/chamber on a long pressurized headrace tunnel, placed as close as practicable to the powerhouse. Its purpose is to absorb water-hammer/pressure transients and supply or store water during load changes, protecting the tunnel and reducing penstock surge. It is used in tunnel (pressurized) conveyance schemes.
(b) Surge amplitude and period (frictionless simple surge tank)
For a frictionless simple surge tank, the maximum surge amplitude is:
Substituting:
Maximum surge amplitude above reservoir level.
Period of (undamped) oscillation:
Period (about minutes).
Section B: Short Answer Questions
Attempt all questions.
Classify hydropower plants on the basis of (i) head and (ii) operation/storage, giving the typical head ranges and one example application for each category.
(i) Classification by head:
- Low head: — e.g. run-of-river barrage plants on large lowland rivers (Kaplan units).
- Medium head: — e.g. Francis-turbine plants on hill rivers.
- High head: — e.g. Pelton-turbine plants fed by long penstocks in steep terrain.
(Exact band limits vary slightly between texts; the medium band is sometimes quoted as 25-250 m.)
(ii) Classification by operation / storage:
- Run-of-river (RoR): little/no storage; generates with available flow (e.g. most Nepali medium-head plants).
- Storage (reservoir) plant: a reservoir stores seasonal flow to provide firm/peaking power (e.g. a multi-purpose dam scheme).
- Pumped-storage plant: pumps water to an upper reservoir during off-peak hours and generates during peak demand, acting as energy storage.
Summary: head governs turbine choice; storage governs how flexibly the plant can meet demand.
List the major structural and electro-mechanical components housed in a surface powerhouse of a hydropower plant, and briefly state the function of any three of them.
Major components of a surface powerhouse:
Structural / civil:
- Substructure (draft-tube and turbine foundations, scroll-case block)
- Intermediate structure (generator floor, control gallery)
- Superstructure (machine hall, service bay, crane gantry, roof)
Electro-mechanical:
- Turbines and governors
- Generators (alternators) with excitation systems
- Main inlet valves / butterfly or spherical valves
- Step-up transformers and switchgear/busbars
- Overhead travelling (EOT) crane
- Cooling, dewatering, drainage and auxiliary systems
- Control room / SCADA and protection equipment
Functions of three components:
- Turbine: converts the hydraulic energy (head and flow) of water into mechanical shaft power.
- Generator: converts the turbine's mechanical rotation into electrical energy.
- Main inlet valve: isolates the turbine from the penstock for maintenance and provides emergency shut-off, protecting the unit.
- EOT crane: lifts and positions heavy runners, rotors and valves during erection and maintenance.
A trapezoidal unlined-then-lined headrace canal is to carry . The canal is concrete-lined with Manning's , bed slope , bed width and side slopes (H:V). For a flow depth , compute the discharge using Manning's equation and check whether the depth is adequate. Take the flow as uniform.
Geometry of a trapezoidal section (side slope , so each side adds horizontally):
Area:
Wetted perimeter:
Hydraulic radius:
Manning's equation:
: ; ; .
.
Computed capacity design discharge.
The section at carries about , which exceeds the required by roughly , so the depth is adequate and provides a small margin (a freeboard of - should still be added above the water surface).
A run-of-river plant has a total installed capital cost of and generates per year. Annual operation and maintenance (O&M) cost is of the capital cost. The capital is recovered over years at an annual interest rate of .
(a) Compute the capital recovery factor (CRF) and the annual capital (debt-service) charge. (3)
(b) Compute the levelised generation cost in . (2)
(a) Capital recovery factor and annual capital charge
Capital recovery factor:
Compute : ; ; .
.
Annual capital (debt-service) charge:
Annual capital charge .
(b) Levelised generation cost
Annual O&M cost:
Total annual cost:
Annual energy:
Levelised cost:
Levelised generation cost .
A single-jet Pelton wheel operates under a net head of . The nozzle velocity coefficient is and the jet diameter is . Compute (a) the jet velocity, (b) the jet discharge, and (c) the theoretical hydraulic power of the jet. Take , .
(a) Jet velocity
Jet velocity .
(b) Jet discharge Jet area:
Jet discharge .
(c) Theoretical jet (kinetic) power
Theoretical jet power .
(Equivalently , confirming the result.)
Write short notes on hydropower development in Nepal, covering (a) the theoretical, technical and economically-feasible potential figures commonly cited, and (b) any three major challenges to harnessing this potential.
(a) Hydropower potential of Nepal (commonly cited figures)
- Theoretical potential: about (roughly ), based on the gross runoff of the country's major river systems (Koshi, Gandaki, Karnali, Mahakali and southern rivers).
- Technically feasible potential: about (~).
- Economically feasible potential: about is often quoted as technically feasible, with the economically feasible portion commonly cited at roughly the same order; many references state about technically and a large fraction of that economically exploitable under current conditions.
Most developed and planned plants in Nepal are run-of-river (medium head, Francis or Pelton), with only a few storage schemes, leading to a marked seasonal generation deficit in the dry months.
(b) Three major challenges
- Seasonal flow variability: monsoon-dominated hydrology gives high wet-season flows and very low dry-season flows; with mostly RoR plants and little storage, the country faces winter energy deficits and surplus in the wet season.
- Difficult terrain, geology and sediment: steep, fragile Himalayan terrain, landslides, glacial-lake outburst flood (GLOF) risk and very high sediment loads raise construction cost and cause turbine abrasion.
- Financing, transmission and market constraints: high up-front capital cost, limited domestic financing, weak/insufficient transmission and cross-border evacuation infrastructure, and the need for power-trade agreements (e.g. export to India/Bangladesh) to absorb wet-season surplus.
(Other valid challenges: geopolitical/transboundary water issues, right-of-way and resettlement, and institutional/regulatory delays.)
Frequently asked questions
- Where can I find the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper 2079?
- The full BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2079 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
- Does the Hydropower Engineering (IOE, CE 755) 2079 paper come with solutions?
- Yes. Every question on this Hydropower Engineering (IOE, CE 755) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
- How many marks is the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2079 paper?
- The BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2079 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
- Is practising this Hydropower Engineering (IOE, CE 755) past paper free?
- Yes — reading and attempting this Hydropower Engineering (IOE, CE 755) past paper on Kekkei is completely free.