BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) Question Paper 2078 Nepal
This is the official BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper for 2078, as set in the regular annual examination. It carries 80 full marks and a time allowance of 180 minutes, across 11 questions. On Kekkei you can attempt this Hydropower Engineering (IOE, CE 755) past paper online with a timer, get instant AI feedback and step-by-step solutions, and track the topics where you lose marks — completely free. Whether you are revising for your BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) exam or solving previous years' question papers, this 2078 paper is a great way to practise under real exam conditions.
Section A: Long Answer Questions
Attempt all questions.
A run-of-river (RoR) hydropower scheme is proposed on a Himalayan river. The daily average discharge data have been processed into the following flow-duration curve (FDC):
| % time discharge equalled or exceeded | 10 | 20 | 30 | 40 | 50 | 60 | 70 | 80 | 90 | 100 |
|---|---|---|---|---|---|---|---|---|---|---|
| Discharge (m³/s) | 46 | 38 | 31 | 26 | 22 | 19 | 16 | 13 | 10 | 7 |
The gross head available is m. The plant is designed to use the discharge available 40 % of the time as its design discharge (any excess is spilled). Take overall plant efficiency and kN/m³.
(a) Define gross head, net head and firm power. (3)
(b) Estimate the installed (design) capacity of the plant. (3)
(c) Using the FDC, estimate the mean annual energy generated (GWh/year), accounting for the fact that the turbine cannot pass more than the design discharge and assuming a minimum technical flow of m³/s below which the plant shuts down. (4)
(a) Definitions
- Gross head (): the vertical difference in water-surface elevation between the intake/forebay and the tailrace, measured under static (no-flow) conditions.
- Net head (): the head actually available to the turbine after deducting all hydraulic losses (trashrack, intake, headrace, penstock friction and bend losses): .
- Firm power: the power that can be guaranteed for (almost) the entire period, i.e. the power corresponding to the dependable minimum flow (often the 95–100 % exceedance discharge).
(b) Installed (design) capacity
Design discharge = discharge available 40 % of the time .
Installed capacity ≈ 19.87 MW (≈ 19.9 MW).
(c) Mean annual energy
The turbine passes and shuts off when . Compute power at each exceedance level using with kW per (m³/s).
| % time | (kW) | ||
|---|---|---|---|
| 10 | 46 | 26 | 19,869 |
| 20 | 38 | 26 | 19,869 |
| 30 | 31 | 26 | 19,869 |
| 40 | 26 | 26 | 19,869 |
| 50 | 22 | 22 | 16,812 |
| 60 | 19 | 19 | 14,519 |
| 70 | 16 | 16 | 12,227 |
| 80 | 13 | 13 | 9,934 |
| 90 | 10 | 10 | 7,642 |
| 100 | 7 | 7 | 5,349 |
Use the average-of-ordinates (mid-point of each 10 % band) to get mean power. Average successive pairs and weight each band by 10 % (0.1):
- 0–10: avg of (P at 10) only edge → use trapezoidal between listed points. Pair averages (kW): (19869+19869)/2=19869; 19869; 19869; (19869+16812)/2=18341; (16812+14519)/2=15666; (14519+12227)/2=13373; (12227+9934)/2=11081; (9934+7642)/2=8788; (7642+5349)/2=6496.
These 9 band-averages cover the 10 %→100 % range (each band = 10 % = 0.1). Add half-band contributions at the two ends (assume P constant beyond 10 % at 19,869 kW for the 0–10 band, and equal to 5,349 kW for the 100 % tail which is the shutdown limit).
Mean power:
Sum inside: kW; including the leading 0–10 band (19,869):
Simpler trapezoidal over the 10 listed ordinates (9 intervals of 0.1 each):
Interior sum kW. End terms kW.
This covers 90 % of the year (10 %→100 % exceedance). For the top 10 % (0–10 %) the plant is capped at 19,869 kW. Add that band: contribution to the year-average kW, while the 13.34 MW above already represents the 0.9 fraction:
Annual energy (8760 h):
Mean annual energy ≈ 122.5 GWh/year, giving a plant (capacity) factor .
A settling basin is to be designed for a RoR plant carrying a design discharge of . The basin must trap all suspended particles of diameter mm (quartz, ). The fall (settling) velocity for this size in still water is m/s. Adopt a basin through-flow velocity m/s and water temperature 15 °C ().
(a) Explain why settling basins are essential for high-head plants and list four design requirements. (3)
(b) Determine the width, depth and length of a single ideal (Sokolov) settling chamber. (4)
(c) Apply a turbulence correction using Camp's approach so that the design (corrected) settling velocity is , and find the corrected length. Comment on the result. (3)
(a) Need for settling basins (high-head plants)
High-head plants use Pelton/Francis turbines running at high velocities; sediment (especially hard quartz mm) acts as an abrasive and rapidly erodes nozzles, needles, runner buckets and guide vanes, reducing efficiency and life. A settling basin reduces water velocity so suspended particles settle out before entering the headrace/penstock.
Four design requirements:
- Trap the target particle size (e.g. – mm) with the required efficiency.
- Low enough through-flow velocity to allow settling (non-scouring of deposited silt).
- Smooth inlet/transition to avoid turbulence and short-circuiting; uniform flow distribution.
- Provision for flushing/removal of trapped sediment (continuous or intermittent), and adequate freeboard.
(b) Basin dimensions (ideal theory)
Cross-sectional area required for the through-flow velocity:
Choose a practical depth-to-width relationship. Adopt depth m (typical for medium plants). Then
Ideal length: a particle entering at the surface must reach the floor (fall depth ) before it is carried out:
Ideal basin: m, m, m. (Surface-loading check: m/s ✓.)
(c) Turbulence (Camp) correction
Corrected fall velocity:
Corrected length:
Comment: The turbulence correction increases the required length almost 8-fold (48 m → ≈ 388 m), which is impractical for a single chamber. The very large factor shows that the empirical constant 0.04 makes the corrected settling velocity nearly collapse; in practice a milder turbulence factor (e.g. with –) or multiple narrower parallel chambers with lower velocity ( m/s) are adopted to keep length reasonable while still trapping 0.25 mm particles.
A steel penstock of length m, internal diameter m and wall thickness mm carries water at velocity m/s under a static head of m. Take GPa, GPa, , .
(a) Compute the pressure wave (celerity) in the penstock. (3)
(b) For instantaneous (sudden) complete closure, find the water-hammer head rise (Joukowsky) and the total maximum head. (3)
(c) If the valve is closed uniformly in s, classify the closure (rapid/slow) and estimate the head rise using the appropriate formula. State the role of a surge tank here. (4)
(a) Wave celerity
Numerator: m/s.
Denominator factor: .
m/s.
(b) Sudden closure (Joukowsky)
Total maximum head at valve:
m; m.
(c) Closure classification for s
Critical (reflection) time:
Since , this is a slow closure. Use Michaud/Allievi slow-closure formula:
Total head m — a large reduction compared with sudden closure (578 m → 237 m).
Role of surge tank: A surge tank placed near the powerhouse end of a long low-pressure conduit converts the conduit into a short penstock; it reflects/absorbs the pressure surge (mass oscillation) so that the rapid water-hammer pressure is confined to the short penstock below the tank, protecting the long headrace tunnel and reducing the effective in the water-hammer equation.
A hydropower station is to generate MW at a net head of m with a generator running at rpm (synchronous, 12-pole, 50 Hz).
(a) Compute the specific speed (metric, in terms of power) and recommend a suitable turbine type with justification. (3)
(b) The selected Pelton wheel uses a single jet. For jet velocity coefficient and a speed ratio (bucket/jet) , find the jet velocity, runner (pitch) diameter and number of jets needed if a single jet diameter must not exceed of the wheel diameter. (4)
(c) Sketch (describe) and explain the working of the Pelton turbine governing system (spear/deflector). (3)
(a) Specific speed and turbine type
Metric power specific speed (per unit, single runner):
(metric, kW). For a single jet this falls in the Pelton range (– for multi-jet up to ~70). Combined with the high head (310 m), a Pelton turbine is recommended (impulse turbine; suits high head, moderate discharge).
(b) Pelton jet and runner sizing
Discharge required (assume ):
Jet velocity:
Bucket (peripheral) speed:
Runner pitch diameter from :
m.
Total jet area: .
Max allowed single-jet diameter m; single-jet area .
Number of jets:
Since a single Pelton wheel is limited to ~6 jets, two wheels (6 jets each) on one shaft would be adopted; revised per runner then drops accordingly. (Acceptable answer: 12 jets total satisfying .)
(c) Pelton governing
penstock
|
[ spear/needle ] --> moves in/out of nozzle (controls jet area)
|| jet
VV
===O=== runner (buckets)
deflector plate (swings into jet on sudden load drop)
When load on the generator falls, the governor (oil servomotor driven by a centrifugal/electronic speed sensor) must reduce the jet discharge to avoid overspeed. To prevent water hammer the spear (needle) is moved slowly to reduce the nozzle opening. For sudden large load rejection, a deflector is first swung into the jet to instantly divert water away from the buckets (no sudden flow change in the penstock, so no water hammer); the spear then closes gradually. On load increase the spear opens to admit more flow. This two-element (deflector + spear) action keeps the runner speed (and hence frequency) constant while limiting pressure rise.
A 30 MW RoR hydropower project in Nepal has the following data:
- Total installed cost (overnight): NPR 5,400 million; built with 70 % loan at 10 % interest, 30 % equity expecting 14 % return.
- Construction period assumed instantaneous (ignore IDC).
- Annual O&M cost: 1.5 % of installed cost.
- Plant capacity factor: 0.60; transmission/auxiliary losses: 4 %.
- Plant economic life: 30 years; loan repaid over 12 years (equal annual installments).
(a) Compute the annual net saleable energy (GWh). (3)
(b) Compute the annual revenue requirement (debt service + return on equity + O&M) for a representative year within the loan period. (4)
(c) Hence estimate the required average tariff (NPR/kWh) and comment on its competitiveness for Nepal. (3)
(a) Net saleable energy
Gross generation:
After 4 % losses:
Net saleable energy ≈ 151.4 GWh/year.
(b) Annual revenue requirement
Loan = M NPR; Equity = M NPR.
Debt service (capital recovery over 12 yr at 10 %): CRF with .
. CRF .
Annual debt service M NPR.
Return on equity (14 % of equity): M NPR.
O&M (1.5 % of installed cost): M NPR.
Annual revenue requirement .
(c) Required average tariff
Required tariff ≈ NPR 5.7/kWh (during the 12-year loan-repayment phase; after the loan is retired the debt-service component disappears and the tariff falls to roughly NPR 2.0/kWh).
Comment: A levelised price near NPR 5–6/kWh during repayment is broadly in line with NEA's wet-/dry-season PPA rates for RoR projects (historically around NPR 4.8 wet / NPR 8.4 dry). The project is competitive provided generation is firm; the high front-loaded debt burden means tariffs are highest early and drop sharply after year 12, which is typical of Nepali hydropower economics. Sensitivity to capacity factor (dry-season flow) and interest rate is the main risk.
Section B: Short Answer Questions
Attempt all questions.
Classify hydropower plants on the basis of (i) head and (ii) operation/load, giving the typical head ranges and one example/turbine for each head class. Differentiate clearly between a run-of-river and a storage (reservoir) plant.
(i) Classification by head
| Class | Typical head | Suitable turbine | Example/feature |
|---|---|---|---|
| Low head | < 30 m (some texts < 15 m) | Kaplan / propeller, bulb | Canal-fall, barrage plants |
| Medium head | 30 – 250 m | Francis | Most river-valley plants |
| High head | > 250 m | Pelton (and high-head Francis) | Himalayan steep-gradient schemes |
(ii) Classification by operation / load
- Base-load plant: runs continuously near full capacity (high plant factor); typically large storage/RoR with firm flow.
- Peak-load plant: operates during peak-demand hours only (low plant factor, high capacity); needs storage or pondage.
- Pumped-storage plant: pumps water to an upper reservoir off-peak and generates during peak.
Run-of-river vs Storage plant
| Feature | Run-of-river (RoR) | Storage (reservoir) |
|---|---|---|
| Storage | Little/none (only daily pondage) | Large seasonal/annual reservoir |
| Output | Depends on instantaneous river flow; varies seasonally | Regulated, firm; can shift water from wet to dry season |
| Capacity factor | Moderate (0.4–0.6) | Can be high or used for peaking |
| Cost/impact | Lower cost, smaller submergence | Higher cost, dam + large submergence |
| Nepal example | Most existing plants (Marsyangdi, Kaligandaki-A — pondage type) | Kulekhani (only seasonal-storage plant in Nepal) |
A simple cylindrical surge tank of cross-sectional area is connected to a headrace tunnel of area and length m. The steady tunnel velocity before complete, sudden load rejection is m/s. Neglecting friction, compute the maximum surge amplitude above the reservoir level and the period of mass oscillation.
For a frictionless simple surge tank, sudden complete load rejection produces undamped mass oscillation.
Maximum surge amplitude (frictionless):
m above reservoir level.
Period of oscillation:
s (≈ 2.4 min). Friction would reduce the amplitude and slightly alter the period in practice.
Distinguish between a forebay and a surge tank. State the functions of a forebay and explain where each is used (RoR canal scheme vs. tunnel scheme). Also list the main functions of an intake.
Forebay vs Surge tank
| Aspect | Forebay | Surge tank |
|---|---|---|
| Location | End of an open headrace canal, just before the penstock | On a long pressurised headrace tunnel, near the penstock |
| Flow type | At the junction of free-surface (open-channel) flow and pressure flow | Within a pressurised system |
| Primary role | Acts as a small reservoir/balancing pond; transition to penstock | Controls water hammer & mass oscillation; protects tunnel |
| Used in | RoR scheme with canal headrace | Scheme with tunnel headrace under pressure |
Functions of a forebay
- Provides temporary storage (pondage) to meet sudden load demand and absorb load fluctuations.
- Allows final settling of fine sediment and removal of floating debris (trashrack).
- Maintains the required submergence/head over the penstock intake to prevent air entrainment (vortex).
- Provides a smooth transition from open-channel to pressure flow and a place for spillway/overflow during load rejection.
Functions of an intake
- Divert/admit the required design discharge into the conveyance system with minimum head loss.
- Control flow (gates) and exclude floating debris, ice and bed-load sediment (trashrack, sill, gravel trap).
- Prevent entry of air (adequate submergence, anti-vortex design).
- Permit shut-off for maintenance and protect downstream structures during floods.
Water flows through a steel penstock at . A trial diameter of m and length m is proposed. Using the Darcy–Weisbach equation with friction factor , compute the velocity, friction head loss, and the power lost in friction. Briefly state the principle of economic penstock diameter.
Velocity
Friction head loss (Darcy–Weisbach)
m.
Power lost in friction
kW.
Economic diameter principle: A larger diameter reduces velocity and hence friction loss (more energy/revenue) but increases the capital cost of the pipe; a smaller diameter is cheaper but wastes energy. The economic diameter is the one that minimises the total annual cost = (annualised capital cost of penstock) + (annual cost of lost energy). It is found where , i.e. where the marginal saving in energy cost equals the marginal increase in capital cost.
A Francis turbine operates at a net head of m. The runner outlet (where minimum pressure occurs) is set m above the tailwater. Atmospheric pressure head m and vapour pressure head m of water. The critical Thoma cavitation factor for this runner is . Check whether the turbine is safe against cavitation and state the function of the draft tube.
Thoma's cavitation factor (plant/available value)
Safety check: Cavitation is avoided when .
Margin: . The setting has a small but positive margin. (Maximum permissible suction head for the critical condition: m; since actual , the setting is acceptable.)
Function of the draft tube
- Recovers a large part of the kinetic energy at the runner exit by gradual expansion (converts velocity head to pressure head), increasing the effective/net head and efficiency.
- Allows the turbine to be set above the tailwater while still utilising the head between the runner exit and tailrace (creates negative/suction pressure at outlet).
- By controlling the outlet pressure it helps keep pressure above vapour pressure, mitigating cavitation when correctly designed and submerged.
Write short notes (any THREE): (a) Components of a surface powerhouse (sub/super-structure). (b) Hydropower potential of Nepal (theoretical, technical, economically feasible figures) and current development status. (c) Pondage and pondage factor for a peaking RoR plant. (d) Advantages of underground powerhouse in Himalayan terrain.
(a) Components of a surface powerhouse
- Sub-structure: the foundation and the water-passage components below the generator floor — spiral/scroll casing, draft tube, turbine pit, and the concrete substructure supporting the machines.
- Super-structure: the building above the generator floor housing the generator, control room, switchgear, overhead travelling (EOT) crane for erection/maintenance, ventilation and auxiliaries. Typically divided into machine hall, erection bay, and service/control bays.
(b) Hydropower potential of Nepal
- Theoretical potential: ≈ 83,000 MW (about 83 GW), based on Dr. Hari Man Shrestha's 1966 estimate.
- Technically feasible: ≈ 45,000 MW.
- Economically feasible: ≈ 42,000 MW.
- Status (≈2078 BS): installed capacity has grown to the order of ~2,000+ MW (NEA + IPPs combined), still only a small fraction (~2–3 %) of the economically feasible potential; mostly RoR, with Kulekhani as the only seasonal-storage plant. Large projects (Upper Tamakoshi 456 MW) commissioned around this period.
(c) Pondage and pondage factor
- Pondage is the small storage (typically for a few hours to a day) provided in/just upstream of a RoR plant (e.g. in the forebay or a daily-regulating pond) to meet short-duration peak demand that exceeds the instantaneous river flow.
- Pondage factor . A pondage factor > 1 means the plant can peak above the run-of-river flow using stored water, recharged during off-peak hours.
(d) Advantages of underground powerhouse (Himalayan terrain)
- Suits steep, narrow, unstable valleys where no flat surface site exists.
- Protected from landslides, rockfall, avalanches and floods (GLOFs).
- Shorter/steeper penstock or pressure shaft, often reducing conveyance length.
- Lower environmental/visual impact and better security; rock provides natural support and thermal stability. (Disadvantage: higher excavation cost and need for good rock and careful geotechnical investigation.)
Frequently asked questions
- Where can I find the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper 2078?
- The full BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2078 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
- Does the Hydropower Engineering (IOE, CE 755) 2078 paper come with solutions?
- Yes. Every question on this Hydropower Engineering (IOE, CE 755) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
- How many marks is the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2078 paper?
- The BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2078 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
- Is practising this Hydropower Engineering (IOE, CE 755) past paper free?
- Yes — reading and attempting this Hydropower Engineering (IOE, CE 755) past paper on Kekkei is completely free.