Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long10 marks

A run-of-river (RoR) hydropower scheme is proposed on a Himalayan river. The daily average discharge data have been processed into the following flow-duration curve (FDC):

% time discharge equalled or exceeded102030405060708090100
Discharge QQ (m³/s)4638312622191613107

The gross head available is H=95H = 95 m. The plant is designed to use the discharge available 40 % of the time as its design discharge (any excess is spilled). Take overall plant efficiency η=0.82\eta = 0.82 and γ=9.81\gamma = 9.81 kN/m³.

(a) Define gross head, net head and firm power. (3)

(b) Estimate the installed (design) capacity of the plant. (3)

(c) Using the FDC, estimate the mean annual energy generated (GWh/year), accounting for the fact that the turbine cannot pass more than the design discharge and assuming a minimum technical flow of 77 m³/s below which the plant shuts down. (4)

(a) Definitions

  • Gross head (HgH_g): the vertical difference in water-surface elevation between the intake/forebay and the tailrace, measured under static (no-flow) conditions.
  • Net head (HnH_n): the head actually available to the turbine after deducting all hydraulic losses (trashrack, intake, headrace, penstock friction and bend losses): Hn=HghLH_n = H_g - \sum h_L.
  • Firm power: the power that can be guaranteed for (almost) the entire period, i.e. the power corresponding to the dependable minimum flow (often the 95–100 % exceedance discharge).

(b) Installed (design) capacity

Design discharge = discharge available 40 % of the time =Q40=26 m3/s= Q_{40} = 26\ \text{m}^3/\text{s}.

P=ηγQH=0.82×9.81×26×95P = \eta\,\gamma\,Q\,H = 0.82 \times 9.81 \times 26 \times 95 P=0.82×9.81=8.0442;8.0442×26=209.15;209.15×95=19,869 kWP = 0.82 \times 9.81 = 8.0442;\quad 8.0442 \times 26 = 209.15;\quad 209.15 \times 95 = 19{,}869\ \text{kW}

Installed capacity ≈ 19.87 MW (≈ 19.9 MW).

(c) Mean annual energy

The turbine passes Qturb=min(Q, 26)Q_{turb} = \min(Q,\ 26) and shuts off when Q<7Q < 7. Compute power at each exceedance level using P=ηγQturbHP = \eta\gamma Q_{turb}H with ηγH=0.82×9.81×95=764.18\eta\gamma H = 0.82\times9.81\times95 = 764.18 kW per (m³/s).

% timeQQQturbQ_{turb}P=764.18QturbP=764.18\,Q_{turb} (kW)
10462619,869
20382619,869
30312619,869
40262619,869
50222216,812
60191914,519
70161612,227
8013139,934
9010107,642
100775,349

Use the average-of-ordinates (mid-point of each 10 % band) to get mean power. Average successive pairs and weight each band by 10 % (0.1):

  • 0–10: avg of (P at 10) only edge → use trapezoidal between listed points. Pair averages (kW): (19869+19869)/2=19869; 19869; 19869; (19869+16812)/2=18341; (16812+14519)/2=15666; (14519+12227)/2=13373; (12227+9934)/2=11081; (9934+7642)/2=8788; (7642+5349)/2=6496.

These 9 band-averages cover the 10 %→100 % range (each band = 10 % = 0.1). Add half-band contributions at the two ends (assume P constant beyond 10 % at 19,869 kW for the 0–10 band, and equal to 5,349 kW for the 100 % tail which is the shutdown limit).

Mean power:

Pˉ=0.1[19869+(19869+19869+18341+15666+13373+11081+8788+6496)]\bar P = 0.1\,[19869 + (19869+19869+18341+15666+13373+11081+8788+6496)]

Sum inside: 19869+19869+19869+18341+15666+13373+11081+8788+6496=13335219869+19869+19869+18341+15666+13373+11081+8788+6496 = 133352 kW; including the leading 0–10 band (19,869):

Pˉ=0.1×(19869+133352)/...\bar P = 0.1 \times (19869 + 133352)/...

Simpler trapezoidal over the 10 listed ordinates (9 intervals of 0.1 each):

Pˉ=0.1[19869+53492+(19869+19869+19869+16812+14519+12227+9934+7642)]\bar P = 0.1\Big[\tfrac{19869+5349}{2} + (19869+19869+19869+16812+14519+12227+9934+7642)\Big]

Interior sum =19869+19869+19869+16812+14519+12227+9934+7642=120741=19869+19869+19869+16812+14519+12227+9934+7642 = 120741 kW. End terms =(19869+5349)/2=12609=(19869+5349)/2 = 12609 kW.

Pˉ=0.1(120741+12609)=0.1×133350=13,335 kW13.34 MW\bar P = 0.1\,(120741 + 12609) = 0.1 \times 133350 = 13{,}335\ \text{kW} \approx 13.34\ \text{MW}

This covers 90 % of the year (10 %→100 % exceedance). For the top 10 % (0–10 %) the plant is capped at 19,869 kW. Add that band: contribution to the year-average =0.1×19869=1986.9= 0.1 \times 19869 = 1986.9 kW, while the 13.34 MW above already represents the 0.9 fraction:

Pˉyear=0.9×13335+0.1×19869=12001.5+1986.9=13,988 kW13.99 MW\bar P_{year} = 0.9 \times 13335 + 0.1 \times 19869 = 12001.5 + 1986.9 = 13{,}988\ \text{kW} \approx 13.99\ \text{MW}

Annual energy (8760 h):

E=13988 kW×8760 h=1.2254×108 kWhE = 13988\ \text{kW} \times 8760\ \text{h} = 1.2254\times10^{8}\ \text{kWh}

Mean annual energy ≈ 122.5 GWh/year, giving a plant (capacity) factor =13.99/19.87=0.70= 13.99/19.87 = 0.70.

hydropower-potentialflow-duration-curveenergy-estimation
2long10 marks

A settling basin is to be designed for a RoR plant carrying a design discharge of Q=12 m3/sQ = 12\ \text{m}^3/\text{s}. The basin must trap all suspended particles of diameter 0.25\ge 0.25 mm (quartz, ρs=2650 kg/m3\rho_s = 2650\ \text{kg/m}^3). The fall (settling) velocity for this size in still water is w=0.025w = 0.025 m/s. Adopt a basin through-flow velocity v=0.30v = 0.30 m/s and water temperature 15 °C (ν=1.14×106 m2/s\nu = 1.14\times10^{-6}\ \text{m}^2/\text{s}).

(a) Explain why settling basins are essential for high-head plants and list four design requirements. (3)

(b) Determine the width, depth and length of a single ideal (Sokolov) settling chamber. (4)

(c) Apply a turbulence correction using Camp's approach so that the design (corrected) settling velocity is w=w0.04vw' = w - 0.04\sqrt{v}, and find the corrected length. Comment on the result. (3)

(a) Need for settling basins (high-head plants)

High-head plants use Pelton/Francis turbines running at high velocities; sediment (especially hard quartz 0.2\ge 0.2 mm) acts as an abrasive and rapidly erodes nozzles, needles, runner buckets and guide vanes, reducing efficiency and life. A settling basin reduces water velocity so suspended particles settle out before entering the headrace/penstock.

Four design requirements:

  1. Trap the target particle size (e.g. 0.2\ge 0.20.250.25 mm) with the required efficiency.
  2. Low enough through-flow velocity to allow settling (non-scouring of deposited silt).
  3. Smooth inlet/transition to avoid turbulence and short-circuiting; uniform flow distribution.
  4. Provision for flushing/removal of trapped sediment (continuous or intermittent), and adequate freeboard.

(b) Basin dimensions (ideal theory)

Cross-sectional area required for the through-flow velocity:

A=Qv=120.30=40 m2A = \frac{Q}{v} = \frac{12}{0.30} = 40\ \text{m}^2

Choose a practical depth-to-width relationship. Adopt depth D=4D = 4 m (typical for medium plants). Then

B=AD=404=10 mB = \frac{A}{D} = \frac{40}{4} = 10\ \text{m}

Ideal length: a particle entering at the surface must reach the floor (fall depth DD) before it is carried out:

L=vDw=0.30×40.025=48 mL = \frac{v\,D}{w} = \frac{0.30 \times 4}{0.025} = 48\ \text{m}

Ideal basin: B=10B = 10 m, D=4D = 4 m, L=48L = 48 m. (Surface-loading check: Q/(BL)=12/(10×48)=0.025Q/(BL)=12/(10\times48)=0.025 m/s =w= w ✓.)

(c) Turbulence (Camp) correction

Corrected fall velocity:

w=w0.04v=0.0250.040.30=0.0250.04(0.5477)=0.0250.02191=0.00309 m/sw' = w - 0.04\sqrt{v} = 0.025 - 0.04\sqrt{0.30} = 0.025 - 0.04(0.5477) = 0.025 - 0.02191 = 0.00309\ \text{m/s}

Corrected length:

L=vDw=0.30×40.00309=1.200.00309=388 mL' = \frac{v\,D}{w'} = \frac{0.30 \times 4}{0.00309} = \frac{1.20}{0.00309} = 388\ \text{m}

Comment: The turbulence correction increases the required length almost 8-fold (48 m → ≈ 388 m), which is impractical for a single chamber. The very large factor shows that the empirical constant 0.04 makes the corrected settling velocity nearly collapse; in practice a milder turbulence factor (e.g. L=αLL' = \alpha L with α1.2\alpha \approx 1.21.51.5) or multiple narrower parallel chambers with lower velocity (v0.2v \approx 0.2 m/s) are adopted to keep length reasonable while still trapping 0.25 mm particles.

settling-basinsedimentintake
3long10 marks

A steel penstock of length L=420L = 420 m, internal diameter D=1.6D = 1.6 m and wall thickness t=14t = 14 mm carries water at velocity V0=4.0V_0 = 4.0 m/s under a static head of H0=180H_0 = 180 m. Take Esteel=200E_{steel} = 200 GPa, Kwater=2.1K_{water} = 2.1 GPa, ρ=1000 kg/m3\rho = 1000\ \text{kg/m}^3, g=9.81 m/s2g = 9.81\ \text{m/s}^2.

(a) Compute the pressure wave (celerity) aa in the penstock. (3)

(b) For instantaneous (sudden) complete closure, find the water-hammer head rise ΔH\Delta H (Joukowsky) and the total maximum head. (3)

(c) If the valve is closed uniformly in T=6T = 6 s, classify the closure (rapid/slow) and estimate the head rise using the appropriate formula. State the role of a surge tank here. (4)

(a) Wave celerity

a=K/ρ1+KEDta = \frac{\sqrt{K/\rho}}{\sqrt{1 + \dfrac{K}{E}\dfrac{D}{t}}}

Numerator: K/ρ=2.1×109/1000=2.1×106=1449.1\sqrt{K/\rho} = \sqrt{2.1\times10^{9}/1000} = \sqrt{2.1\times10^{6}} = 1449.1 m/s.

Denominator factor: KEDt=2.1×109200×109×1.60.014=0.0105×114.29=1.200\dfrac{K}{E}\dfrac{D}{t} = \dfrac{2.1\times10^{9}}{200\times10^{9}} \times \dfrac{1.6}{0.014} = 0.0105 \times 114.29 = 1.200.

a=1449.11+1.200=1449.12.200=1449.11.4832=977.0 m/sa = \frac{1449.1}{\sqrt{1+1.200}} = \frac{1449.1}{\sqrt{2.200}} = \frac{1449.1}{1.4832} = 977.0\ \text{m/s}

a977a \approx 977 m/s.

(b) Sudden closure (Joukowsky)

ΔH=aV0g=977.0×4.09.81=39089.81=398.4 m\Delta H = \frac{a\,V_0}{g} = \frac{977.0 \times 4.0}{9.81} = \frac{3908}{9.81} = 398.4\ \text{m}

Total maximum head at valve:

Hmax=H0+ΔH=180+398.4=578.4 mH_{max} = H_0 + \Delta H = 180 + 398.4 = 578.4\ \text{m}

ΔH398\Delta H \approx 398 m; Hmax578H_{max} \approx 578 m.

(c) Closure classification for T=6T = 6 s

Critical (reflection) time:

Tc=2La=2×420977.0=840977.0=0.86 sT_c = \frac{2L}{a} = \frac{2 \times 420}{977.0} = \frac{840}{977.0} = 0.86\ \text{s}

Since T=6 s>Tc=0.86 sT = 6\ \text{s} > T_c = 0.86\ \text{s}, this is a slow closure. Use Michaud/Allievi slow-closure formula:

ΔHslow=2LV0gT=2×420×4.09.81×6=336058.86=57.1 m\Delta H_{slow} = \frac{2 L V_0}{g\,T} = \frac{2 \times 420 \times 4.0}{9.81 \times 6} = \frac{3360}{58.86} = 57.1\ \text{m}

Total head 180+57.1=237.1\approx 180 + 57.1 = 237.1 m — a large reduction compared with sudden closure (578 m → 237 m).

Role of surge tank: A surge tank placed near the powerhouse end of a long low-pressure conduit converts the conduit into a short penstock; it reflects/absorbs the pressure surge (mass oscillation) so that the rapid water-hammer pressure is confined to the short penstock below the tank, protecting the long headrace tunnel and reducing the effective LL in the water-hammer equation.

penstockwater-hammersurge-tank
4long10 marks

A hydropower station is to generate P=24P = 24 MW at a net head of Hn=310H_n = 310 m with a generator running at N=500N = 500 rpm (synchronous, 12-pole, 50 Hz).

(a) Compute the specific speed NsN_s (metric, in terms of power) and recommend a suitable turbine type with justification. (3)

(b) The selected Pelton wheel uses a single jet. For jet velocity coefficient Cv=0.98C_v = 0.98 and a speed ratio (bucket/jet) ϕ=0.46\phi = 0.46, find the jet velocity, runner (pitch) diameter and number of jets needed if a single jet diameter must not exceed 1/121/12 of the wheel diameter. (4)

(c) Sketch (describe) and explain the working of the Pelton turbine governing system (spear/deflector). (3)

(a) Specific speed and turbine type

Metric power specific speed (per unit, single runner):

Ns=NPHn5/4,P in kWN_s = \frac{N\sqrt{P}}{H_n^{5/4}}, \quad P\ \text{in kW} Hn5/4=3101.25; ln310=5.7366;×1.25=7.1708; e7.1708=1301H_n^{5/4} = 310^{1.25};\ \ln310 = 5.7366;\times1.25 = 7.1708;\ e^{7.1708} = 1301 Ns=500240001301=500×154.921301=774601301=59.5N_s = \frac{500\sqrt{24000}}{1301} = \frac{500 \times 154.92}{1301} = \frac{77460}{1301} = 59.5

Ns60N_s \approx 60 (metric, kW). For a single jet this falls in the Pelton range (Ns10N_s \approx 106060 for multi-jet up to ~70). Combined with the high head (310 m), a Pelton turbine is recommended (impulse turbine; suits high head, moderate discharge).

(b) Pelton jet and runner sizing

Discharge required (assume ηo=0.88\eta_o = 0.88):

Q=PηoγHn=24,0000.88×9.81×310=240002676.2=8.97 m3/sQ = \frac{P}{\eta_o\,\gamma\,H_n} = \frac{24{,}000}{0.88 \times 9.81 \times 310} = \frac{24000}{2676.2} = 8.97\ \text{m}^3/\text{s}

Jet velocity:

V1=Cv2gHn=0.982×9.81×310=0.986082.2=0.98×77.99=76.4 m/sV_1 = C_v\sqrt{2gH_n} = 0.98\sqrt{2 \times 9.81 \times 310} = 0.98\sqrt{6082.2} = 0.98 \times 77.99 = 76.4\ \text{m/s}

Bucket (peripheral) speed:

u=ϕV1=0.46×76.4=35.16 m/su = \phi V_1 = 0.46 \times 76.4 = 35.16\ \text{m/s}

Runner pitch diameter from u=πDN/60u = \pi D N/60:

D=60uπN=60×35.16π×500=2109.61570.8=1.343 mD = \frac{60\,u}{\pi N} = \frac{60 \times 35.16}{\pi \times 500} = \frac{2109.6}{1570.8} = 1.343\ \text{m}

D1.34D \approx 1.34 m.

Total jet area: A=Q/V1=8.97/76.4=0.1174 m2A = Q/V_1 = 8.97/76.4 = 0.1174\ \text{m}^2.

Max allowed single-jet diameter dmax=D/12=1.343/12=0.1119d_{max} = D/12 = 1.343/12 = 0.1119 m; single-jet area =π4(0.1119)2=0.00984 m2= \frac{\pi}{4}(0.1119)^2 = 0.00984\ \text{m}^2.

Number of jets:

n=Aajet=0.11740.00984=11.912 jets (use 6 nozzles on a vertical-shaft twin runner, or 2 wheels of 6 jets).n = \frac{A}{a_{jet}} = \frac{0.1174}{0.00984} = 11.9 \Rightarrow \textbf{12 jets (use 6 nozzles on a vertical-shaft twin runner, or 2 wheels of 6 jets)}.

Since a single Pelton wheel is limited to ~6 jets, two wheels (6 jets each) on one shaft would be adopted; revised NsN_s per runner then drops accordingly. (Acceptable answer: 12 jets total satisfying dD/12d \le D/12.)

(c) Pelton governing

        penstock
           |
        [ spear/needle ] --> moves in/out of nozzle (controls jet area)
           ||  jet
           VV
        ===O=== runner (buckets)
        deflector plate (swings into jet on sudden load drop)

When load on the generator falls, the governor (oil servomotor driven by a centrifugal/electronic speed sensor) must reduce the jet discharge to avoid overspeed. To prevent water hammer the spear (needle) is moved slowly to reduce the nozzle opening. For sudden large load rejection, a deflector is first swung into the jet to instantly divert water away from the buckets (no sudden flow change in the penstock, so no water hammer); the spear then closes gradually. On load increase the spear opens to admit more flow. This two-element (deflector + spear) action keeps the runner speed (and hence frequency) constant while limiting pressure rise.

turbinesspecific-speedturbine-selection
5long10 marks

A 30 MW RoR hydropower project in Nepal has the following data:

  • Total installed cost (overnight): NPR 5,400 million; built with 70 % loan at 10 % interest, 30 % equity expecting 14 % return.
  • Construction period assumed instantaneous (ignore IDC).
  • Annual O&M cost: 1.5 % of installed cost.
  • Plant capacity factor: 0.60; transmission/auxiliary losses: 4 %.
  • Plant economic life: 30 years; loan repaid over 12 years (equal annual installments).

(a) Compute the annual net saleable energy (GWh). (3)

(b) Compute the annual revenue requirement (debt service + return on equity + O&M) for a representative year within the loan period. (4)

(c) Hence estimate the required average tariff (NPR/kWh) and comment on its competitiveness for Nepal. (3)

(a) Net saleable energy

Gross generation:

Egross=P×CF×8760=30,000 kW×0.60×8760 h=157.68×106 kWh=157.68 GWhE_{gross} = P \times CF \times 8760 = 30{,}000\ \text{kW} \times 0.60 \times 8760\ \text{h} = 157.68\times10^{6}\ \text{kWh} = 157.68\ \text{GWh}

After 4 % losses:

Enet=157.68×(10.04)=157.68×0.96=151.4 GWhE_{net} = 157.68 \times (1 - 0.04) = 157.68 \times 0.96 = 151.4\ \text{GWh}

Net saleable energy ≈ 151.4 GWh/year.

(b) Annual revenue requirement

Loan = 0.70×5400=37800.70 \times 5400 = 3780 M NPR; Equity = 0.30×5400=16200.30 \times 5400 = 1620 M NPR.

Debt service (capital recovery over 12 yr at 10 %): CRF =i(1+i)n(1+i)n1= \dfrac{i(1+i)^n}{(1+i)^n-1} with i=0.10, n=12i=0.10,\ n=12.

(1.10)12=3.1384(1.10)^{12} = 3.1384. CRF =0.10×3.13843.13841=0.313842.1384=0.14676= \dfrac{0.10 \times 3.1384}{3.1384 - 1} = \dfrac{0.31384}{2.1384} = 0.14676.

Annual debt service =3780×0.14676=554.8= 3780 \times 0.14676 = 554.8 M NPR.

Return on equity (14 % of equity): =0.14×1620=226.8= 0.14 \times 1620 = 226.8 M NPR.

O&M (1.5 % of installed cost): =0.015×5400=81.0= 0.015 \times 5400 = 81.0 M NPR.

Annual revenue requirement =554.8+226.8+81.0=862.6 M NPR/year= 554.8 + 226.8 + 81.0 = \textbf{862.6 M NPR/year}.

(c) Required average tariff

Tariff=Annual revenue requirementNet energy=862.6×106 NPR151.4×106 kWh=5.70 NPR/kWh\text{Tariff} = \frac{\text{Annual revenue requirement}}{\text{Net energy}} = \frac{862.6\times10^{6}\ \text{NPR}}{151.4\times10^{6}\ \text{kWh}} = 5.70\ \text{NPR/kWh}

Required tariff ≈ NPR 5.7/kWh (during the 12-year loan-repayment phase; after the loan is retired the debt-service component disappears and the tariff falls to roughly (226.8+81.0)/151.4(226.8+81.0)/151.4 \approx NPR 2.0/kWh).

Comment: A levelised price near NPR 5–6/kWh during repayment is broadly in line with NEA's wet-/dry-season PPA rates for RoR projects (historically around NPR 4.8 wet / NPR 8.4 dry). The project is competitive provided generation is firm; the high front-loaded debt burden means tariffs are highest early and drop sharply after year 12, which is typical of Nepali hydropower economics. Sensitivity to capacity factor (dry-season flow) and interest rate is the main risk.

economicshydropower-nepaltariff
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short5 marks

Classify hydropower plants on the basis of (i) head and (ii) operation/load, giving the typical head ranges and one example/turbine for each head class. Differentiate clearly between a run-of-river and a storage (reservoir) plant.

(i) Classification by head

ClassTypical headSuitable turbineExample/feature
Low head< 30 m (some texts < 15 m)Kaplan / propeller, bulbCanal-fall, barrage plants
Medium head30 – 250 mFrancisMost river-valley plants
High head> 250 mPelton (and high-head Francis)Himalayan steep-gradient schemes

(ii) Classification by operation / load

  • Base-load plant: runs continuously near full capacity (high plant factor); typically large storage/RoR with firm flow.
  • Peak-load plant: operates during peak-demand hours only (low plant factor, high capacity); needs storage or pondage.
  • Pumped-storage plant: pumps water to an upper reservoir off-peak and generates during peak.

Run-of-river vs Storage plant

FeatureRun-of-river (RoR)Storage (reservoir)
StorageLittle/none (only daily pondage)Large seasonal/annual reservoir
OutputDepends on instantaneous river flow; varies seasonallyRegulated, firm; can shift water from wet to dry season
Capacity factorModerate (0.4–0.6)Can be high or used for peaking
Cost/impactLower cost, smaller submergenceHigher cost, dam + large submergence
Nepal exampleMost existing plants (Marsyangdi, Kaligandaki-A — pondage type)Kulekhani (only seasonal-storage plant in Nepal)
types-of-plantsclassification
7short5 marks

A simple cylindrical surge tank of cross-sectional area As=30 m2A_s = 30\ \text{m}^2 is connected to a headrace tunnel of area At=9 m2A_t = 9\ \text{m}^2 and length L=1500L = 1500 m. The steady tunnel velocity before complete, sudden load rejection is V0=2.2V_0 = 2.2 m/s. Neglecting friction, compute the maximum surge amplitude above the reservoir level and the period of mass oscillation.

For a frictionless simple surge tank, sudden complete load rejection produces undamped mass oscillation.

Maximum surge amplitude (frictionless):

Zmax=V0LAtgAsZ_{max} = V_0\sqrt{\frac{L\,A_t}{g\,A_s}} LAtgAs=1500×99.81×30=13500294.3=45.87 s2\frac{L A_t}{g A_s} = \frac{1500 \times 9}{9.81 \times 30} = \frac{13500}{294.3} = 45.87\ \text{s}^2 Zmax=2.2×45.87=2.2×6.773=14.90 mZ_{max} = 2.2 \times \sqrt{45.87} = 2.2 \times 6.773 = 14.90\ \text{m}

Zmax14.9Z_{max} \approx 14.9 m above reservoir level.

Period of oscillation:

T=2πLAsgAtT = 2\pi\sqrt{\frac{L\,A_s}{g\,A_t}} LAsgAt=1500×309.81×9=4500088.29=509.7 s2\frac{L A_s}{g A_t} = \frac{1500 \times 30}{9.81 \times 9} = \frac{45000}{88.29} = 509.7\ \text{s}^2 T=2π509.7=2π×22.58=141.8 sT = 2\pi\sqrt{509.7} = 2\pi \times 22.58 = 141.8\ \text{s}

T142T \approx 142 s (≈ 2.4 min). Friction would reduce the amplitude and slightly alter the period in practice.

surge-tankmass-oscillation
8short5 marks

Distinguish between a forebay and a surge tank. State the functions of a forebay and explain where each is used (RoR canal scheme vs. tunnel scheme). Also list the main functions of an intake.

Forebay vs Surge tank

AspectForebaySurge tank
LocationEnd of an open headrace canal, just before the penstockOn a long pressurised headrace tunnel, near the penstock
Flow typeAt the junction of free-surface (open-channel) flow and pressure flowWithin a pressurised system
Primary roleActs as a small reservoir/balancing pond; transition to penstockControls water hammer & mass oscillation; protects tunnel
Used inRoR scheme with canal headraceScheme with tunnel headrace under pressure

Functions of a forebay

  1. Provides temporary storage (pondage) to meet sudden load demand and absorb load fluctuations.
  2. Allows final settling of fine sediment and removal of floating debris (trashrack).
  3. Maintains the required submergence/head over the penstock intake to prevent air entrainment (vortex).
  4. Provides a smooth transition from open-channel to pressure flow and a place for spillway/overflow during load rejection.

Functions of an intake

  1. Divert/admit the required design discharge into the conveyance system with minimum head loss.
  2. Control flow (gates) and exclude floating debris, ice and bed-load sediment (trashrack, sill, gravel trap).
  3. Prevent entry of air (adequate submergence, anti-vortex design).
  4. Permit shut-off for maintenance and protect downstream structures during floods.
forebayheadraceintake
9short5 marks

Water flows through a steel penstock at Q=6.0 m3/sQ = 6.0\ \text{m}^3/\text{s}. A trial diameter of D=1.2D = 1.2 m and length L=250L = 250 m is proposed. Using the Darcy–Weisbach equation with friction factor f=0.018f = 0.018, compute the velocity, friction head loss, and the power lost in friction. Briefly state the principle of economic penstock diameter.

Velocity

A=π4D2=π4(1.2)2=1.131 m2,V=QA=6.01.131=5.31 m/sA = \frac{\pi}{4}D^2 = \frac{\pi}{4}(1.2)^2 = 1.131\ \text{m}^2,\quad V = \frac{Q}{A} = \frac{6.0}{1.131} = 5.31\ \text{m/s}

Friction head loss (Darcy–Weisbach)

hf=fLDV22g=0.018×2501.2×(5.31)22×9.81h_f = f\frac{L}{D}\frac{V^2}{2g} = 0.018 \times \frac{250}{1.2} \times \frac{(5.31)^2}{2\times9.81} =0.018×208.33×28.2019.62=3.75×1.4373=5.39 m= 0.018 \times 208.33 \times \frac{28.20}{19.62} = 3.75 \times 1.4373 = 5.39\ \text{m}

hf5.39h_f \approx 5.39 m.

Power lost in friction

Ploss=γQhf=9.81×6.0×5.39=317.3 kWP_{loss} = \gamma Q h_f = 9.81 \times 6.0 \times 5.39 = 317.3\ \text{kW}

Ploss317P_{loss} \approx 317 kW.

Economic diameter principle: A larger diameter reduces velocity and hence friction loss (more energy/revenue) but increases the capital cost of the pipe; a smaller diameter is cheaper but wastes energy. The economic diameter is the one that minimises the total annual cost = (annualised capital cost of penstock) + (annual cost of lost energy). It is found where ddD(total annual cost)=0\dfrac{d}{dD}(\text{total annual cost}) = 0, i.e. where the marginal saving in energy cost equals the marginal increase in capital cost.

penstockeconomic-diameterhead-loss
10short5 marks

A Francis turbine operates at a net head of H=60H = 60 m. The runner outlet (where minimum pressure occurs) is set Hs=3.5H_s = 3.5 m above the tailwater. Atmospheric pressure head =10.3= 10.3 m and vapour pressure head =0.24= 0.24 m of water. The critical Thoma cavitation factor for this runner is σc=0.095\sigma_c = 0.095. Check whether the turbine is safe against cavitation and state the function of the draft tube.

Thoma's cavitation factor (plant/available value)

σ=HatmHvHsH=10.30.243.560=6.5660=0.1093\sigma = \frac{H_{atm} - H_v - H_s}{H} = \frac{10.3 - 0.24 - 3.5}{60} = \frac{6.56}{60} = 0.1093

Safety check: Cavitation is avoided when σσc\sigma \ge \sigma_c.

σ=0.1093>σc=0.095 SAFE against cavitation.\sigma = 0.1093 > \sigma_c = 0.095 \quad\Rightarrow\ \textbf{SAFE against cavitation.}

Margin: 0.10930.095=0.01430.1093 - 0.095 = 0.0143. The setting has a small but positive margin. (Maximum permissible suction head for the critical condition: Hs,max=HatmHvσcH=10.30.240.095×60=10.065.70=4.36H_{s,max} = H_{atm} - H_v - \sigma_c H = 10.3 - 0.24 - 0.095\times60 = 10.06 - 5.70 = 4.36 m; since actual Hs=3.5 m<4.36 mH_s = 3.5\ \text{m} < 4.36\ \text{m}, the setting is acceptable.)

Function of the draft tube

  1. Recovers a large part of the kinetic energy at the runner exit by gradual expansion (converts velocity head to pressure head), increasing the effective/net head and efficiency.
  2. Allows the turbine to be set above the tailwater while still utilising the head between the runner exit and tailrace (creates negative/suction pressure at outlet).
  3. By controlling the outlet pressure it helps keep pressure above vapour pressure, mitigating cavitation when correctly designed and submerged.
turbinescavitationdraft-tube
11short5 marks

Write short notes (any THREE): (a) Components of a surface powerhouse (sub/super-structure). (b) Hydropower potential of Nepal (theoretical, technical, economically feasible figures) and current development status. (c) Pondage and pondage factor for a peaking RoR plant. (d) Advantages of underground powerhouse in Himalayan terrain.

(a) Components of a surface powerhouse

  • Sub-structure: the foundation and the water-passage components below the generator floor — spiral/scroll casing, draft tube, turbine pit, and the concrete substructure supporting the machines.
  • Super-structure: the building above the generator floor housing the generator, control room, switchgear, overhead travelling (EOT) crane for erection/maintenance, ventilation and auxiliaries. Typically divided into machine hall, erection bay, and service/control bays.

(b) Hydropower potential of Nepal

  • Theoretical potential:83,000 MW (about 83 GW), based on Dr. Hari Man Shrestha's 1966 estimate.
  • Technically feasible:45,000 MW.
  • Economically feasible:42,000 MW.
  • Status (≈2078 BS): installed capacity has grown to the order of ~2,000+ MW (NEA + IPPs combined), still only a small fraction (~2–3 %) of the economically feasible potential; mostly RoR, with Kulekhani as the only seasonal-storage plant. Large projects (Upper Tamakoshi 456 MW) commissioned around this period.

(c) Pondage and pondage factor

  • Pondage is the small storage (typically for a few hours to a day) provided in/just upstream of a RoR plant (e.g. in the forebay or a daily-regulating pond) to meet short-duration peak demand that exceeds the instantaneous river flow.
  • Pondage factor =maximum (peak) discharge demandedaverage daily river flow= \dfrac{\text{maximum (peak) discharge demanded}}{\text{average daily river flow}}. A pondage factor > 1 means the plant can peak above the run-of-river flow using stored water, recharged during off-peak hours.

(d) Advantages of underground powerhouse (Himalayan terrain)

  1. Suits steep, narrow, unstable valleys where no flat surface site exists.
  2. Protected from landslides, rockfall, avalanches and floods (GLOFs).
  3. Shorter/steeper penstock or pressure shaft, often reducing conveyance length.
  4. Lower environmental/visual impact and better security; rock provides natural support and thermal stability. (Disadvantage: higher excavation cost and need for good rock and careful geotechnical investigation.)
hydropower-nepalpowerhousepolicy

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper 2078?
The full BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2078 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Hydropower Engineering (IOE, CE 755) 2078 paper come with solutions?
Yes. Every question on this Hydropower Engineering (IOE, CE 755) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2078 paper?
The BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2078 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Hydropower Engineering (IOE, CE 755) past paper free?
Yes — reading and attempting this Hydropower Engineering (IOE, CE 755) past paper on Kekkei is completely free.