Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long8 marks

A run-of-river hydropower scheme on a Himalayan river is designed for a firm discharge of Q=12 m3/sQ = 12\ \text{m}^3/\text{s} at a gross head of H=85 mH = 85\ \text{m}. The overall plant efficiency (turbine ×\times generator ×\times transformer) is ηo=0.86\eta_o = 0.86.

(a) Define theoretical, technical and economically feasible hydropower potential, and state the latest accepted figures for Nepal. (2)

(b) Compute the installed capacity of the plant. (2)

(c) If the annual plant (capacity) factor is 0.550.55, compute the annual energy generation in GWh. (2)

(d) Explain why the annual capacity factor of a run-of-river plant in Nepal is typically much lower in the dry season than in the monsoon. (2)

(a) Categories of hydropower potential (Nepal figures)

  • Theoretical potential – the gross power available from all flowing water assuming 100% conversion and full exploitation of every drop and head. For Nepal this is about 83,000 MW (~83 GW).
  • Technical potential – the portion that can be developed using current engineering technology, accounting for site access, geology and head/flow limits. For Nepal this is about 42,000–45,000 MW.
  • Economically feasible potential – the part of the technical potential that can be developed at a cost competitive with alternatives. For Nepal this is about 42,000 MW in the classic studies (often quoted alongside the technical figure).

(b) Installed capacity

P=ρgQHηoP = \rho g Q H \eta_o P=1000×9.81×12×85×0.86P = 1000 \times 9.81 \times 12 \times 85 \times 0.86 P=8,604,900 W8.605 MWP = 8{,}604{,}900\ \text{W} \approx 8.605\ \text{MW}

Installed capacity P8.61 MWP \approx 8.61\ \text{MW}.

(c) Annual energy

With capacity factor Cf=0.55C_f = 0.55 and 87608760 hours/year:

E=P×Cf×8760E = P \times C_f \times 8760 E=8.605 MW×0.55×8760 h=41,460 MWhE = 8.605\ \text{MW} \times 0.55 \times 8760\ \text{h} = 41{,}460\ \text{MWh}

Annual energy E41.5 GWhE \approx 41.5\ \text{GWh}.

(d) A run-of-river plant has little or no storage, so its output tracks the natural river hydrograph. In the monsoon (Jun–Sep) snowmelt plus rainfall keep discharge well above the design flow, so the plant runs near full capacity. In the dry season (Dec–Apr) base flow can fall to a small fraction of the design discharge, so the turbines must be throttled or shut off, sharply reducing the capacity factor. This seasonal energy deficit is why Nepal historically imported power in winter and why storage/PRoR projects are emphasised.

hydropower-potentialenergy-economicsnepal
2long8 marks

A settling basin (de-sander) is to be designed to remove suspended particles of size 0.20 mm\ge 0.20\ \text{mm} from a design discharge of Q=8.0 m3/sQ = 8.0\ \text{m}^3/\text{s}. The fall (settling) velocity of the limiting particle is w=0.021 m/sw = 0.021\ \text{m/s}. A horizontal through-flow velocity of vh=0.30 m/sv_h = 0.30\ \text{m/s} and an effective settling depth of d=1.5 md = 1.5\ \text{m} are adopted.

(a) With a neat sketch, explain the four zones of a settling basin and the function of each. (3)

(b) Determine the required settling length LL, the basin width WW and check the plan (surface) area against the overflow-rate criterion. (4)

(c) Why is a continuous (hopper-bottom) flushing arrangement preferred over an intermittent one for high-sediment Himalayan rivers? (1)

(a) Four functional zones (longitudinal flow shown left to right):

  inlet                                              outlet
   |   transition   |        settling zone        |  weir |
  ==>~~~~~~~~~~~~~~~~|=============================|~~~~~~~==> to headrace
   |                |   ....particles settle....  |       |
   |________________|_____________________________|_______|
            \                                         /
             \----------- SEDIMENT (storage) --------/  --> flushing gate
  1. Inlet / transition zone – spreads the concentrated intake flow gently across the full basin width so velocity is uniform and low; abrupt expansion is avoided to prevent turbulence and short-circuiting.
  2. Settling (working) zone – the main length where the horizontal velocity is low enough that particles settle to the bed before reaching the outlet.
  3. Sediment storage zone – the hopper/sloping floor below the settling zone where deposited sediment collects between (or during) flushes.
  4. Outlet zone – an overflow weir/transition that draws clarified water uniformly into the headrace without re-suspending deposited material.

(b) Sizing

Settling length (a particle entering at the surface must reach the bed before leaving):

Lvh=dw    L=vhdw=0.30×1.50.021=21.43 m\frac{L}{v_h} = \frac{d}{w} \;\Rightarrow\; L = \frac{v_h\, d}{w} = \frac{0.30 \times 1.5}{0.021} = 21.43\ \text{m}

Width from continuity (Q=vhdWQ = v_h\, d\, W):

W=Qvhd=8.00.30×1.5=17.78 mW = \frac{Q}{v_h\, d} = \frac{8.0}{0.30 \times 1.5} = 17.78\ \text{m}

Overflow-rate (surface-loading) check – ideal-basin theory requires the surface area As=Q/wA_s = Q/w:

As,req=Qw=8.00.021=380.95 m2A_{s,\text{req}} = \frac{Q}{w} = \frac{8.0}{0.021} = 380.95\ \text{m}^2 As,provided=L×W=21.43×17.78=381.0 m2A_{s,\text{provided}} = L \times W = 21.43 \times 17.78 = 381.0\ \text{m}^2

The provided plan area equals the required surface-loading area, confirming the design is consistent. Adopt L21.5 mL \approx 21.5\ \text{m}, W17.8 mW \approx 17.8\ \text{m}, d=1.5 md = 1.5\ \text{m} (a settling efficiency factor of 1.2–1.5 is normally applied to LL for turbulence; e.g. L26L \approx 2632 m32\ \text{m} in practice).

(c) Continuous (hopper-bottom, e.g. Bieri/Serpent-Sand or Dufour) flushing keeps removing sediment while the plant runs, so the basin never silts up during the flood season when Himalayan rivers carry extreme suspended loads (often >5000 ppm). Intermittent flushing requires periodic shutdown and wastes water and generation; with very high inflow concentrations the basin would fill faster than it could be emptied, allowing abrasive sediment to pass to the turbines and accelerate runner erosion. Hence continuous flushing protects the runners and maximises availability.

settling-basinintakesediment
3long8 marks

A steel penstock conveys Q=12 m3/sQ = 12\ \text{m}^3/\text{s} over a length L=420 mL = 420\ \text{m} to the powerhouse. The gross head is Hg=180 mH_g = 180\ \text{m}. Use Darcy friction factor f=0.018f = 0.018 and ignore minor losses for the head-loss estimate.

(a) State the factors governing the economic diameter of a penstock and sketch the cost-vs-diameter trade-off. (2)

(b) For an adopted internal diameter D=1.8 mD = 1.8\ \text{m}, compute the flow velocity, the friction head loss and the net head. (4)

(c) Compute the turbine power output if the turbine efficiency is 0.880.88, and the electrical power if the generator efficiency is 0.960.96. (2)

(a) Economic-diameter factors. The optimum diameter minimises the sum of annualised capital cost (increases with DD, since more steel/excavation) and annual energy-loss cost (decreases with DD, because friction loss 1/D5\propto 1/D^5 for a given QQ). Governing factors: discharge QQ, available head, length, steel/fabrication cost, energy value (tariff), plant load/capacity factor, interest rate and design life, and a velocity limit (usually 4–6 m/s to control water hammer and loss).

cost
 |  \ capital cost                /
 |   \                          /  total cost
 |    \____                ____/
 |         \___        ___/   <- minimum = economic D
 |             \______/
 |     energy-loss cost (falling)
 +---------------------------------- diameter D -->

(b) Velocity, friction loss, net head

Area: A=π4D2=π4(1.8)2=2.545 m2A = \dfrac{\pi}{4}D^2 = \dfrac{\pi}{4}(1.8)^2 = 2.545\ \text{m}^2

Velocity: V=QA=122.545=4.716 m/sV = \dfrac{Q}{A} = \dfrac{12}{2.545} = 4.716\ \text{m/s} (within 4–6 m/s — acceptable)

Friction head loss (Darcy–Weisbach):

hf=fLDV22g=0.018×4201.8×4.71622×9.81h_f = f\frac{L}{D}\frac{V^2}{2g} = 0.018 \times \frac{420}{1.8} \times \frac{4.716^2}{2 \times 9.81} hf=0.018×233.33×1.1336=4.76 mh_f = 0.018 \times 233.33 \times 1.1336 = 4.76\ \text{m}

Net head:

Hn=Hghf=1804.76=175.24 mH_n = H_g - h_f = 180 - 4.76 = 175.24\ \text{m}

Net head Hn175.2 mH_n \approx 175.2\ \text{m}.

(c) Power output

Turbine (shaft) power:

Pt=ρgQHnηt=1000×9.81×12×175.24×0.88P_t = \rho g Q H_n \eta_t = 1000 \times 9.81 \times 12 \times 175.24 \times 0.88 Pt=18,154,000 W18.15 MWP_t = 18{,}154{,}000\ \text{W} \approx 18.15\ \text{MW}

Electrical power at generator terminals:

Pe=Pt×ηg=18.154×0.96=17.43 MWP_e = P_t \times \eta_g = 18.154 \times 0.96 = 17.43\ \text{MW}

Turbine power 18.15 MW\approx 18.15\ \text{MW}; electrical power 17.4 MW\approx 17.4\ \text{MW}.

penstockhead-losspower-output
4long8 marks

For the penstock of Q.3 (D=1.8 mD = 1.8\ \text{m}, L=420 mL = 420\ \text{m}, V=4.716 m/sV = 4.716\ \text{m/s}, Hg=180 mH_g = 180\ \text{m}), the pressure-wave celerity in the steel pipe is a=1100 m/sa = 1100\ \text{m/s}.

(a) Explain water hammer and the difference between rapid and slow valve closure, defining the critical time. (2)

(b) Compute the maximum head rise for instantaneous closure (Joukowsky) and the critical closure time. (3)

(c) The guide vanes close in Tc=6 sT_c = 6\ \text{s}. Using the Michaud (Allievi) slow-closure formula, find the surge head, the design head and the required pipe-shell thickness. Take allowable stress σ=110 MPa\sigma = 110\ \text{MPa} and weld joint efficiency ηj=0.90\eta_j = 0.90. (3)

(a) Water hammer is the transient pressure surge produced when the flow velocity in a closed conduit is changed rapidly (e.g. valve/guide-vane closure). The kinetic energy of the moving water column is converted into a pressure (elastic) wave that travels back and forth at celerity aa. The critical (or phase) time is the time for the pressure wave to travel to the reservoir and return:

Tcr=2LaT_{cr} = \frac{2L}{a}
  • Rapid closure: TcTcrT_c \le T_{cr} → the reflected relief wave has not yet returned, so the full Joukowsky head develops.
  • Slow closure: Tc>TcrT_c > T_{cr} → relief waves reduce the peak, and the surge is given by the slow-closure (Michaud/Allievi) formula.

(b) Instantaneous closure (Joukowsky) and critical time

ΔHmax=aVg=1100×4.7169.81=528.8 m\Delta H_{max} = \frac{a\,V}{g} = \frac{1100 \times 4.716}{9.81} = 528.8\ \text{m} Tcr=2La=2×4201100=0.764 sT_{cr} = \frac{2L}{a} = \frac{2 \times 420}{1100} = 0.764\ \text{s}

Since Tc=6 s>Tcr=0.764 sT_c = 6\ \text{s} > T_{cr} = 0.764\ \text{s}, the closure is slow and the Joukowsky value is not used for design.

(c) Slow-closure surge, design head, thickness

Michaud (Allievi) slow-closure surge:

ΔH=2LVgTc=2×420×4.7169.81×6=67.3 m\Delta H = \frac{2 L V}{g\, T_c} = \frac{2 \times 420 \times 4.716}{9.81 \times 6} = 67.3\ \text{m}

Design head (static gross + surge):

Hd=Hg+ΔH=180+67.3=247.3 mH_d = H_g + \Delta H = 180 + 67.3 = 247.3\ \text{m}

Design internal pressure:

p=ρgHd=1000×9.81×247.3=2.426×106 Pa=2.426 MPap = \rho g H_d = 1000 \times 9.81 \times 247.3 = 2.426 \times 10^6\ \text{Pa} = 2.426\ \text{MPa}

Required shell thickness (thin-cylinder hoop formula with joint efficiency):

t=pD2σηj=2.426×106×1.82×110×106×0.90=0.02205 m=22.05 mmt = \frac{p\,D}{2\,\sigma\,\eta_j} = \frac{2.426\times10^6 \times 1.8}{2 \times 110\times10^6 \times 0.90} = 0.02205\ \text{m} = 22.05\ \text{mm}

Adding a corrosion allowance of ~1.5 mm gives a fabricated thickness of about 24 mm.

Surge head 67.3 m\approx 67.3\ \text{m}, design head 247.3 m\approx 247.3\ \text{m}, shell thickness 22 mm\approx 22\ \text{mm} (≈24 mm with corrosion allowance).

water-hammerpenstockpipe-thickness
5long8 marks

A 18 MW run-of-river project has a capital cost of C=NRs 2.4×109C = \text{NRs}\ 2.4 \times 10^9, an economic life of n=30n = 30 years and a discount rate of i=10%i = 10\%. Annual operation and maintenance cost is 2.5%2.5\% of the capital cost. The plant generates E=42×106 kWhE = 42 \times 10^6\ \text{kWh} of saleable energy per year, sold at an average tariff of NRs 8.50/kWh\text{NRs}\ 8.50/\text{kWh}.

(a) Define firm power, secondary power, load factor and plant (capacity) factor. (2)

(b) Using the capital recovery factor, compute the annualised capital cost and the total annual cost. (3)

(c) Compute the levelised generation cost per kWh and the benefit–cost ratio, and comment on the financial viability. (3)

(a) Definitions

  • Firm (primary) power – the power that can be guaranteed to be available essentially at all times (corresponds to the minimum dependable flow/head), used to meet base demand.
  • Secondary power – the surplus power available only when flow exceeds the firm value (e.g. in the monsoon); it is non-guaranteed and usually sold cheaply or dumped.
  • Load factor – ratio of average load to peak load over a period: LF=average loadpeak loadLF = \dfrac{\text{average load}}{\text{peak load}}.
  • Plant (capacity) factor – ratio of actual energy generated to the energy that would be generated at full installed capacity over the same period: Cf=EactualPinstalled×8760C_f = \dfrac{E_{actual}}{P_{installed}\times 8760}.

(b) Annual costs

Capital recovery factor (CRF):

CRF=i(1+i)n(1+i)n1=0.10(1.10)30(1.10)301\text{CRF} = \frac{i(1+i)^n}{(1+i)^n - 1} = \frac{0.10(1.10)^{30}}{(1.10)^{30}-1}

With (1.10)30=17.449(1.10)^{30} = 17.449:

CRF=0.10×17.44917.4491=1.744916.449=0.10608\text{CRF} = \frac{0.10 \times 17.449}{17.449 - 1} = \frac{1.7449}{16.449} = 0.10608

Annualised capital cost:

Acap=C×CRF=2.4×109×0.10608=NRs 254.6 millionA_{cap} = C \times \text{CRF} = 2.4\times10^9 \times 0.10608 = \text{NRs}\ 254.6\ \text{million}

Annual O&M:

Aom=0.025×2.4×109=NRs 60.0 millionA_{om} = 0.025 \times 2.4\times10^9 = \text{NRs}\ 60.0\ \text{million}

Total annual cost:

Atotal=254.6+60.0=NRs 314.6 millionA_{total} = 254.6 + 60.0 = \text{NRs}\ 314.6\ \text{million}

(c) Unit cost and BCR

Levelised generation cost:

c=AtotalE=314.6×10642×106=NRs 7.49/kWhc = \frac{A_{total}}{E} = \frac{314.6\times10^6}{42\times10^6} = \text{NRs}\ 7.49/\text{kWh}

Annual revenue (benefit):

B=E×tariff=42×106×8.50=NRs 357.0 millionB = E \times \text{tariff} = 42\times10^6 \times 8.50 = \text{NRs}\ 357.0\ \text{million}

Benefit–cost ratio:

BCR=BAtotal=357.0314.6=1.135\text{BCR} = \frac{B}{A_{total}} = \frac{357.0}{314.6} = 1.135

Comment: The levelised cost (NRs 7.49/kWh) is below the tariff (NRs 8.50/kWh) and BCR=1.135>1\text{BCR} = 1.135 > 1, so the project is financially viable, with about a 13.5% margin of benefits over costs. The margin is modest, so the result is sensitive to discount rate, generation shortfall and tariff — a sensitivity analysis is advisable.

economicsbenefit-costnepal
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short7 marks

Classify hydropower plants on the basis of (i) head and (ii) operating regime/storage. Give the typical head range and one Nepali example for each head class.

(i) Classification by head

ClassTypical headUsual turbineNepali example
Low head< 30 mKaplan / propeller(canal-fall / barrage type, e.g. small terai canal plants)
Medium head30–300 mFrancisMarsyangdi (132 MW), Kali Gandaki A (144 MW)
High head> 300 mPelton (and high-head Francis)Khimti (60 MW), Upper Tamakoshi (456 MW)

(Boundaries vary slightly between textbooks; some take low <15 m, high >250 m.)

(ii) Classification by operating regime / storage

  • Run-of-river (RoR): no storage; output follows river flow (most Nepali plants).
  • Peaking RoR (PRoR): small pondage for a few hours of daily peaking (e.g. Upper Tamakoshi has limited pondage).
  • Storage (reservoir) plants: large reservoir for seasonal regulation and firm dry-season power (e.g. proposed Budhi Gandaki, existing Kulekhani — Nepal's only major storage scheme).
  • Pumped-storage plants: pump water to an upper reservoir off-peak and generate at peak (under study in Nepal).
plant-typesclassification
7short7 marks

A trapezoidal lined headrace canal has bed width b=2.5 mb = 2.5\ \text{m}, side slope 1H:1V1\text{H}:1\text{V} (z=1z = 1), normal depth y=1.2 my = 1.2\ \text{m}, bed slope S=0.0008S = 0.0008 and Manning's n=0.018n = 0.018. Compute the area, hydraulic radius, velocity and discharge capacity, and check whether the velocity is non-silting/non-scouring.

Geometry

Area: A=(b+zy)y=(2.5+1×1.2)×1.2=3.7×1.2=4.44 m2A = (b + zy)y = (2.5 + 1\times1.2)\times1.2 = 3.7 \times 1.2 = 4.44\ \text{m}^2

Wetted perimeter: P=b+2y1+z2=2.5+2(1.2)2=2.5+3.394=5.894 mP = b + 2y\sqrt{1+z^2} = 2.5 + 2(1.2)\sqrt{2} = 2.5 + 3.394 = 5.894\ \text{m}

Hydraulic radius: R=AP=4.445.894=0.7533 mR = \dfrac{A}{P} = \dfrac{4.44}{5.894} = 0.7533\ \text{m}

Manning velocity

V=1nR2/3S1/2=10.018(0.7533)2/3(0.0008)1/2V = \frac{1}{n}R^{2/3}S^{1/2} = \frac{1}{0.018}(0.7533)^{2/3}(0.0008)^{1/2} V=55.556×0.8276×0.02828=1.30 m/sV = 55.556 \times 0.8276 \times 0.02828 = 1.30\ \text{m/s}

Discharge

Q=AV=4.44×1.30=5.78 m3/sQ = A V = 4.44 \times 1.30 = 5.78\ \text{m}^3/\text{s}

Check: V=1.30 m/sV = 1.30\ \text{m/s} lies in the usual non-silting / non-scouring band for a lined canal (about 0.6–3 m/s). It is high enough to keep fine sediment in suspension (no silting) yet well below the scour limit for a concrete lining, so the velocity is acceptable.

Result: A=4.44 m2A = 4.44\ \text{m}^2, R=0.753 mR = 0.753\ \text{m}, V=1.30 m/sV = 1.30\ \text{m/s}, Q5.78 m3/sQ \approx 5.78\ \text{m}^3/\text{s}.

headraceopen-channelmanning
8short7 marks

A simple cylindrical surge tank (area As=28 m2A_s = 28\ \text{m}^2) is provided at the downstream end of a low-pressure tunnel of length L=2500 mL = 2500\ \text{m} and cross-sectional area At=7.0 m2A_t = 7.0\ \text{m}^2. The steady tunnel velocity is V0=2.2 m/sV_0 = 2.2\ \text{m/s}.

(a) State the functions of a surge tank and how it differs from a forebay. (3)

(b) Estimate the maximum upsurge above reservoir level for a sudden, complete load rejection, neglecting friction. (4)

(a) Functions of a surge tank

  • Provides a free water surface close to the turbines so that water-hammer pressure waves in the long tunnel are reflected/relieved and do not travel up the headrace tunnel.
  • Supplies/absorbs the differential flow during load changes (gives water on sudden load increase, stores it on load rejection), improving turbine governing/regulation.
  • Stores the rising water (upsurge) on load rejection and dampens the mass oscillation of the tunnel water column.

Difference from a forebay: a forebay sits between an open headrace (canal) and the penstock, acting mainly as a small balancing reservoir/transition with a spillway; a surge tank is used with a closed pressure tunnel and is specifically designed to handle pressure transients (water hammer) and mass oscillation. A surge tank must be tall enough to contain the surge; a forebay relieves to atmosphere through a spillway.

(b) Maximum upsurge (frictionless)

For a simple surge tank with frictionless tunnel, the amplitude of mass oscillation is:

Zmax=V0LAtgAsZ_{max} = V_0\sqrt{\frac{L\,A_t}{g\,A_s}} Zmax=2.22500×7.09.81×28Z_{max} = 2.2\sqrt{\frac{2500 \times 7.0}{9.81 \times 28}} Zmax=2.217500274.68=2.263.71=2.2×7.982=17.56 mZ_{max} = 2.2\sqrt{\frac{17500}{274.68}} = 2.2\sqrt{63.71} = 2.2 \times 7.982 = 17.56\ \text{m}

Maximum upsurge Zmax17.6 mZ_{max} \approx 17.6\ \text{m} above reservoir level. (Friction reduces the actual upsurge; the tank height above static level is fixed at this value plus freeboard.)

surge-tankforebaytransient
9short7 marks

A turbine is to develop P=8000 kWP = 8000\ \text{kW} under a net head of H=300 mH = 300\ \text{m} running at N=600 rpmN = 600\ \text{rpm}.

(a) Compute the specific speed (metric, power form) and select a suitable turbine type. (4)

(b) Briefly justify the choice and compare Pelton vs Francis turbines on two further points. (3)

(a) Specific speed

Power-form specific speed (metric, PP in kW, HH in m):

Ns=NPH5/4=60080003001.25N_s = \frac{N\sqrt{P}}{H^{5/4}} = \frac{600\sqrt{8000}}{300^{1.25}}

8000=89.44\sqrt{8000} = 89.44; 3001.25=300×3000.25=300×4.162=1248.6300^{1.25} = 300 \times 300^{0.25} = 300 \times 4.162 = 1248.6

Ns=600×89.441248.6=53,6661248.6=42.98N_s = \frac{600 \times 89.44}{1248.6} = \frac{53{,}666}{1248.6} = 42.98

Ns43N_s \approx 43. This value (roughly 8–30 per jet for Pelton, up to ~70 for multi-jet) together with the high head (300 m) points to a Pelton (impulse) turbine, likely a 2- to 4-jet machine. (A single-jet Pelton has Ns10N_s \approx 103030; Ns=43N_s = 43 implies a multi-jet Pelton, since NsN_s per jet =43/njets= 43/\sqrt{n_{jets}}.)

(b) Justification and comparison

  • At H=300 mH = 300\ \text{m} a Francis runner would suffer high pressures and cavitation risk near the outlet; an impulse (Pelton) turbine handles high head efficiently and is favoured above ~250–300 m.
  • Pelton vs Francis:
    1. Head range / sediment: Pelton suits high head and tolerates abrasive Himalayan sediment better (buckets/needles are easier to repair); Francis suits medium head but its runner erodes badly under high sediment.
    2. Part-load efficiency: Pelton holds high efficiency over a wide flow range (jets can be shut individually), whereas Francis efficiency drops more sharply at part load.

Selection: a multi-jet Pelton turbine (Ns43N_s \approx 43).

turbinesspecific-speedselection
10short6 marks

(a) Describe the main components housed in a surface powerhouse of a medium-head Francis plant. (3)

(b) Explain cavitation in reaction turbines, the role of the draft tube, and define Thoma's cavitation factor. (3)

(a) Powerhouse components (super-, intermediate- and sub-structure):

  • Main units: turbine(s), generator(s) on a common vertical shaft, governor and main inlet valve (MIV).
  • Water passages: spiral (scroll) casing, guide-vane/wicket-gate mechanism, runner, and draft tube leading to the tailrace.
  • Electrical/mechanical auxiliaries: excitation system, busbars, step-up transformers, switchgear/control room, cooling water and lubrication systems, drainage/dewatering pumps, compressed-air system, and the EOT crane for erection/maintenance.
  • Structure: machine hall (superstructure), generator floor, turbine floor and the substructure (draft-tube and foundation).

(b) Cavitation, draft tube, Thoma factor

  • Cavitation: where local pressure in the flowing water falls below the vapour pressure (typically at the runner outlet / draft-tube inlet of a reaction turbine), vapour bubbles form and then collapse violently in higher-pressure zones, causing pitting, vibration, noise and efficiency loss.
  • Draft tube role: a gradually expanding (diverging) conduit from runner exit to tailwater that (i) recovers part of the exit kinetic energy as a pressure rise (regains head), and (ii) allows the runner to be set above tailwater while still using the full head — but its setting must avoid sub-vapour pressures.
  • Thoma's cavitation factor:
σ=HaHvHsH\sigma = \frac{H_a - H_v - H_s}{H}

where HaH_a = atmospheric pressure head, HvH_v = vapour-pressure head, HsH_s = suction head (runner setting above tailwater), HH = net head. To avoid cavitation, σσc\sigma \ge \sigma_c (the critical value, which depends on specific speed); a higher specific-speed runner requires a larger σc\sigma_c and hence a lower (or submerged) setting.

powerhousecavitationdraft-tube
11short6 marks

Write short notes on the status and challenges of hydropower development in Nepal, covering (i) two major completed/under-construction projects, (ii) two technical/environmental challenges, and (iii) two institutional or policy issues.

(i) Major projects

  • Upper Tamakoshi (456 MW) – Nepal's largest plant (commissioned 2021), a peaking-RoR scheme on the Tamakoshi, developed largely with domestic financing.
  • Kali Gandaki A (144 MW) and Kulekhani (92 MW, the only seasonal-storage plant) are other landmarks; large storage projects such as Budhi Gandaki (~1200 MW) are under development to provide dry-season firm power.

(ii) Technical / environmental challenges

  • Sediment / Himalayan geology: very high suspended-sediment loads cause severe turbine and waterway abrasion; young, fragile geology brings landslides, GLOF risk and difficult tunnelling.
  • Hydrological seasonality and climate risk: large monsoon-vs-dry-season flow variation lowers dry-season output, and glacier-fed flows are changing with climate; environmental/e-flow release requirements reduce usable flow.

(iii) Institutional / policy issues

  • Transmission, evacuation and market: weak transmission grid and limited domestic demand cause spillage in the monsoon; cross-border trade (power-export agreements with India/Bangladesh) is being developed but constrained by grid and policy.
  • Financing, licensing and land/social issues: lengthy licensing (PPA, survey/generation licences), financing-cost and currency risk, plus land acquisition, resettlement and benefit-sharing with local communities slow project delivery.

Overall Nepal has shifted from chronic load-shedding to seasonal surplus, but firm (storage) capacity, grid evacuation, sediment management and export markets remain the key issues.

hydropower-nepalpolicydevelopment

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper 2076?
The full BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2076 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Hydropower Engineering (IOE, CE 755) 2076 paper come with solutions?
Yes. Every question on this Hydropower Engineering (IOE, CE 755) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2076 paper?
The BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2076 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Hydropower Engineering (IOE, CE 755) past paper free?
Yes — reading and attempting this Hydropower Engineering (IOE, CE 755) past paper on Kekkei is completely free.