Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long10 marks

A run-of-river hydropower scheme is proposed on a Himalayan river. The mean daily flows for one representative year have been arranged in descending order and the following exceedance values were read from the flow-duration curve (FDC):

Exceedance (%)102040608090100
Discharge (m³/s)9570483322169

The gross head available at the site is Hg=120 mH_g = 120\ \text{m}, the combined hydraulic losses are 5%5\% of the gross head, and the overall plant efficiency is ηo=0.82\eta_o = 0.82. The plant is designed for the 40% exceedance flow as the design (installed) discharge.

(a) Define firm (primary) power and secondary power and explain the significance of the flow-duration curve in fixing the installed capacity of a run-of-river plant.

(b) Compute the installed capacity (at design flow) and the firm power (taken at the 90% exceedance flow).

(c) Estimate the annual energy that would be generated if the plant operated for the full year at the 60% exceedance flow as a representative mean. State the plant (capacity) factor.

(a) Definitions and significance

  • Firm (primary) power is the power that can be guaranteed to be available for essentially the whole year (commonly taken at a high exceedance flow such as 90–95%). It corresponds to the dependable flow and is the marketable, reliable base load of the plant.
  • Secondary (surplus) power is the additional power available only during periods of higher-than-firm flow (the wet season). It is non-guaranteed and is usually sold at a lower tariff or used for non-essential loads.
  • Significance of the FDC: The flow-duration curve shows the percentage of time a given discharge is equalled or exceeded. The area under the curve represents the total volume / energy potential. Choosing the design discharge at a low exceedance (e.g. 30–50%) gives high installed capacity but lower plant factor and much spilled water; choosing a higher exceedance gives a smaller, more fully-utilised plant. It therefore lets the designer trade installed capacity against firmness of supply, spill and economics.

(b) Installed capacity and firm power

Net head: Hn=Hg(10.05)=120×0.95=114 mH_n = H_g(1-0.05) = 120 \times 0.95 = 114\ \text{m}.

Power equation: P=ρgQHnηo=9.81QHnηo (kW, with ρg9.81kN/m3).P = \rho g Q H_n \eta_o = 9.81 \, Q H_n \eta_o\ \text{(kW, with }\rho g \approx 9.81\,\text{kN/m}^3).

Installed capacity (design flow Qd=48 m3/sQ_d = 48\ \text{m}^3/\text{s} at 40% exceedance):

Pinst=9.81×48×114×0.82=44019 kW44.0 MW.P_{inst} = 9.81 \times 48 \times 114 \times 0.82 = 44\,019\ \text{kW} \approx \textbf{44.0 MW}.

Step check: 9.81×48=470.889.81\times48 = 470.88; ×114=53680.3\times114 = 53\,680.3; ×0.82=44017.8 kW\times0.82 = 44\,017.8\ \text{kW}.

Firm power (90% exceedance flow Q90=16 m3/sQ_{90} = 16\ \text{m}^3/\text{s}):

Pfirm=9.81×16×114×0.82=14672 kW14.7 MW.P_{firm} = 9.81 \times 16 \times 114 \times 0.82 = 14\,672\ \text{kW} \approx \textbf{14.7 MW}.

Step check: 9.81×16=156.969.81\times16 = 156.96; ×114=17893.4\times114 = 17\,893.4; ×0.82=14672.6 kW\times0.82 = 14\,672.6\ \text{kW}.

(c) Annual energy at 60% exceedance flow (Q60=33 m3/sQ_{60}=33\ \text{m}^3/\text{s}) and capacity factor

Representative power: P60=9.81×33×114×0.82=30262 kW30.26 MW.P_{60} = 9.81 \times 33 \times 114 \times 0.82 = 30\,262\ \text{kW} \approx 30.26\ \text{MW}. Step check: 9.81×33=323.739.81\times33 = 323.73; ×114=36905.2\times114 = 36\,905.2; ×0.82=30262.3 kW\times0.82 = 30\,262.3\ \text{kW}.

Hours per year: 8760 h8760\ \text{h}.

E=30262.3 kW×8760 h=2.651×108 kWh265.1 GWh.E = 30\,262.3\ \text{kW} \times 8760\ \text{h} = 2.651\times10^8\ \text{kWh} \approx \textbf{265.1 GWh}.

Capacity (plant) factor:

CF=P60Pinst=3026244018=0.68768.7%.CF = \frac{P_{60}}{P_{inst}} = \frac{30\,262}{44\,018} = 0.687 \approx \textbf{68.7\%}.

(Equivalently Eactual/Erated=265.1/(44.018×8.76)=265.1/385.6=0.687E_{actual}/E_{rated} = 265.1/(44.018\times8.76) = 265.1/385.6 = 0.687.)

The relatively high plant factor reflects designing at the 40% exceedance flow rather than the peak flow.

hydropower-potentialflow-duration-curvefirm-power
2long8 marks

A settling (de-sanding) basin is to be designed for a run-of-river plant carrying a design discharge of Q=12 m3/sQ = 12\ \text{m}^3/\text{s}. The basin must remove all suspended particles with diameter d0.30 mmd \geq 0.30\ \text{mm}. The fall velocity of a 0.30 mm0.30\ \text{mm} particle in still water is w=0.035 m/sw = 0.035\ \text{m/s}.

(a) Explain why a settling basin is essential upstream of the turbines of a Himalayan run-of-river plant, and list the three functional zones of a continuous-flow settling basin.

(b) Using the ideal (Camp) approach, determine the required surface area and hence a suitable length and width of the basin if the mean through-flow velocity is limited to v=0.20 m/sv = 0.20\ \text{m/s} and the basin depth is D=3.0 mD = 3.0\ \text{m}.

(c) Apply a turbulence/short-circuiting factor and comment on the practical length adopted, taking the design fall velocity reduced to 80%80\% of the still-water value.

(a) Need and zones

Himalayan rivers carry very high suspended sediment, much of it hard quartz and feldspar. If not removed, particles 0.2\gtrsim 0.20.3 mm0.3\ \text{mm} cause severe abrasion of penstock, valves and especially turbine runners (Pelton needles/buckets, Francis runners), reducing efficiency and life. A settling basin reduces the through-flow velocity so that target particles settle out before reaching the headrace/turbine.

Three functional zones:

  1. Inlet (transition / inlet zone) – flow spreads gradually from the inlet channel to the full basin width to give uniform, low velocity.
  2. Settling (working) zone – the main length where particles fall to the bed.
  3. Outlet zone – clarified water is collected (often by an overflow weir) and conveyed to the headrace; sediment collects in a hopper/flushing zone at the bottom for periodic flushing.

(b) Ideal (Camp) design

In the ideal basin a particle is just removed if its settling time equals the flow-through time. The governing relation is:

wv=DLL=vDw,and surface-load: w=QAsurface=QBL.\frac{w}{v} = \frac{D}{L} \quad\Rightarrow\quad L = \frac{vD}{w}, \qquad \text{and surface-load: } w = \frac{Q}{A_{surface}} = \frac{Q}{B L}.

Required surface area from overflow-rate criterion:

A=Qw=120.035=342.9 m2343 m2.A = \frac{Q}{w} = \frac{12}{0.035} = 342.9\ \text{m}^2 \approx \textbf{343 m}^2.

Width from continuity (cross-section =BD= B D, velocity vv):

BDv=QB=QDv=123.0×0.20=120.60=20.0 m.B D v = Q \Rightarrow B = \frac{Q}{D v} = \frac{12}{3.0 \times 0.20} = \frac{12}{0.60} = \textbf{20.0 m}.

Length (from settling criterion L=vD/wL = vD/w):

L=0.20×3.00.035=0.600.035=17.14 m17.2 m.L = \frac{0.20 \times 3.0}{0.035} = \frac{0.60}{0.035} = 17.14\ \text{m} \approx \textbf{17.2 m}.

Check: A=BL=20.0×17.14=342.9 m2A = B L = 20.0 \times 17.14 = 342.9\ \text{m}^2 — consistent with the overflow-rate area. ✔

(c) Turbulence / short-circuiting correction

Real basins have turbulence and short-circuiting, so the effective fall velocity is reduced. Using w=0.80w=0.80×0.035=0.028 m/sw' = 0.80\,w = 0.80 \times 0.035 = 0.028\ \text{m/s}:

L=vDw=0.600.028=21.4 m.L' = \frac{vD}{w'} = \frac{0.60}{0.028} = 21.4\ \text{m}.

Alternatively the area becomes A=Q/w=12/0.028=428.6 m2A' = Q/w' = 12/0.028 = 428.6\ \text{m}^2, i.e. about 25%25\% larger.

Practical adoption: Provide a settling length of about 22 m (round up from 21.4 m) with width 20 m and depth 3.0 m, plus additional inlet-transition and outlet lengths (each roughly 0.250.250.50.5 of the basin length). The 80% factor adds the safety margin needed to ensure the 0.30 mm particles are reliably trapped despite turbulence.

settling-basinsedimentintake
3long8 marks

A medium-head plant has a low-pressure headrace tunnel of length L=1800 mL = 1800\ \text{m} and cross-sectional area At=9.0 m2A_t = 9.0\ \text{m}^2 feeding a simple cylindrical surge tank of cross-sectional area As=45 m2A_s = 45\ \text{m}^2. The steady design discharge is Q=18 m3/sQ = 18\ \text{m}^3/\text{s}. Friction in the tunnel may be neglected for the idealised analysis.

(a) State the function of a surge tank and name three types.

(b) For a sudden complete load rejection (frictionless tunnel), derive/state the expression for the maximum upsurge amplitude ZmaxZ_{max} above reservoir level and the period of oscillation TT, and evaluate both.

(c) Comment on how tunnel friction would change ZmaxZ_{max} in practice.

(a) Function and types

A surge tank is a free-water-surface storage placed between the long low-pressure conduit (headrace tunnel) and the pressure conduit (penstock). Its functions are: (i) to absorb/relieve water-hammer pressure rises by reflecting the pressure wave so the long tunnel is protected; (ii) to supply water to the turbine during sudden load increase before the tunnel flow accelerates, and to store water during load rejection; (iii) to improve the speed-regulation (governing) of the plant.

Three types: simple (cylindrical) surge tank, restricted-orifice (throttled) surge tank, and differential (Johnson) surge tank. (Others: gallery/expansion-chamber type.)

(b) Maximum upsurge and period (frictionless)

Velocity in tunnel: v0=Q/At=18/9.0=2.0 m/s.v_0 = Q/A_t = 18/9.0 = 2.0\ \text{m/s}.

For a frictionless simple surge tank, conservation of energy between the surging mass in the tunnel and the rise in the tank gives the maximum surge amplitude:

Zmax=v0LAtgAs.Z_{max} = v_0 \sqrt{\frac{L A_t}{g A_s}}.

Evaluate the term under the root:

LAtgAs=1800×9.09.81×45=16200441.45=36.70 s2.\frac{L A_t}{g A_s} = \frac{1800 \times 9.0}{9.81 \times 45} = \frac{16\,200}{441.45} = 36.70\ \text{s}^2. 36.70=6.058 s.\sqrt{36.70} = 6.058\ \text{s}. Zmax=2.0×6.058=12.12 m12.1 m above reservoir level.Z_{max} = 2.0 \times 6.058 = 12.12\ \text{m} \approx \textbf{12.1 m above reservoir level}.

Period of the (undamped) oscillation:

T=2πLAsgAt.T = 2\pi \sqrt{\frac{L A_s}{g A_t}}. LAsgAt=1800×459.81×9.0=8100088.29=917.4 s2,917.4=30.29 s.\frac{L A_s}{g A_t} = \frac{1800 \times 45}{9.81 \times 9.0} = \frac{81\,000}{88.29} = 917.4\ \text{s}^2,\quad \sqrt{917.4} = 30.29\ \text{s}. T=2π×30.29=190.3 s190 s  (3.2 min).T = 2\pi \times 30.29 = 190.3\ \text{s} \approx \textbf{190 s} \;(\approx 3.2\ \text{min}).

(c) Effect of tunnel friction

In reality friction dissipates energy. For an upsurge (load rejection) friction opposes the rising flow into the tank and therefore reduces the maximum upsurge below the frictionless value of 12.1 m. The oscillation is also damped, decaying over several cycles to the new steady level. Conversely, for the first downsurge the friction loss makes the lowest level deeper than the frictionless estimate. The frictionless ZmaxZ_{max} is thus a conservative (over-estimate) for the upsurge and is often used for freeboard fixing, while damped analysis is used for accurate design.

surge-tankwater-hammerheadrace
4long8 marks

A steel penstock of length L=400 mL = 400\ \text{m} conveys Q=6.0 m3/sQ = 6.0\ \text{m}^3/\text{s} under a gross head of 250 m250\ \text{m}. The wave (celerity) of the pressure wave in the pipe is a=1100 m/sa = 1100\ \text{m/s}.

(a) The penstock internal diameter is D=1.4 mD = 1.4\ \text{m}. Compute the flow velocity vv, the critical (pipe) time Tc=2L/aT_c = 2L/a, and—using the Joukowsky equation for sudden (instantaneous) closure—the maximum water-hammer pressure rise ΔH\Delta H (in metres of water) and the corresponding total head at the valve.

(b) If instead the valve is closed slowly in Tclose=8 sT_{close} = 8\ \text{s}, classify the closure (rapid vs. slow) and estimate ΔH\Delta H using the Michaud/Allievi slow-closure relation ΔH=2LvgTclose\Delta H = \dfrac{2 L v}{g\, T_{close}}.

(c) State two reasons why slow closure is preferred and one structural consequence of water hammer for penstock design.

(a) Velocity, critical time, sudden-closure surge

Pipe area: A=πD24=π(1.4)24=π×1.964=1.539 m2.A = \dfrac{\pi D^2}{4} = \dfrac{\pi (1.4)^2}{4} = \dfrac{\pi \times 1.96}{4} = 1.539\ \text{m}^2.

Velocity: v=QA=6.01.539=3.898 m/s3.90 m/s.v = \dfrac{Q}{A} = \dfrac{6.0}{1.539} = 3.898\ \text{m/s} \approx \textbf{3.90 m/s}.

Critical (pipe reflection) time:

Tc=2La=2×4001100=8001100=0.727 s0.73 s.T_c = \frac{2L}{a} = \frac{2 \times 400}{1100} = \frac{800}{1100} = 0.727\ \text{s} \approx \textbf{0.73 s}.

Joukowsky (instantaneous closure) pressure rise:

ΔH=avg=1100×3.8989.81=4287.89.81=437.1 m437 m of water.\Delta H = \frac{a\,v}{g} = \frac{1100 \times 3.898}{9.81} = \frac{4287.8}{9.81} = 437.1\ \text{m} \approx \textbf{437 m of water}.

Total head at valve (gross static + surge):

Htotal=250+437.1=687.1 m687 m of water.H_{total} = 250 + 437.1 = 687.1\ \text{m} \approx \textbf{687 m of water}.

This is the worst-case (instantaneous) value and governs the safety check.

(b) Slow closure in 8 s

Since Tclose=8 s>Tc=0.73 sT_{close} = 8\ \text{s} > T_c = 0.73\ \text{s}, the closure is slow (gradual) — the reflected wave returns long before the valve is fully shut, so the full Joukowsky surge does not develop. Use the Michaud (Allievi) slow-closure estimate:

ΔH=2LvgTclose=2×400×3.8989.81×8=3118.478.48=39.7 m39.7 m of water.\Delta H = \frac{2 L v}{g\, T_{close}} = \frac{2 \times 400 \times 3.898}{9.81 \times 8} = \frac{3118.4}{78.48} = 39.7\ \text{m} \approx \textbf{39.7 m of water}.

Total head at valve 250+39.7=289.7 m290 m\approx 250 + 39.7 = 289.7\ \text{m} \approx \textbf{290 m} — far below the instantaneous case, confirming the benefit of slow closure.

(c) Reasons for slow closure and a structural consequence

Reasons slow closure is preferred:

  1. It drastically reduces the water-hammer pressure rise (here from 437 m to 40 m), so the penstock wall and anchors need not be designed for the extreme Joukowsky head.
  2. It avoids damaging pressure spikes/fatigue on valves, joints and the spiral casing, improving safety and life.

Structural consequence of water hammer: the penstock shell thickness must be sized for the maximum internal pressure (static + surge) using the thin-cylinder hoop-stress relation t=pD2σallow+ct = \dfrac{p\,D}{2\,\sigma_{allow}} + c (plus corrosion allowance cc); anchor blocks and expansion joints must also resist the transient thrust. Inadequate provision can cause pipe bursting or buckling.

penstockwater-hammereconomic-diameter
5long8 marks

A hydropower plant is to develop a shaft power of P=22 MWP = 22\ \text{MW} per unit under a net head of H=95 mH = 95\ \text{m}. The generator is to run at synchronous speed N=500 rpmN = 500\ \text{rpm} (50 Hz50\ \text{Hz}).

(a) Compute the specific speed NsN_s (in metric units, with PP in kW) and, using standard head/specific-speed ranges, select the appropriate turbine type. Justify.

(b) Determine the number of poles of the directly-coupled generator.

(c) Distinguish between impulse and reaction turbines and explain why a draft tube is essential for reaction turbines but not for impulse turbines.

(a) Specific speed and turbine selection

Metric specific speed (power form, PP in kW, HH in m):

Ns=NPH5/4.N_s = \frac{N\sqrt{P}}{H^{5/4}}.

With P=22000 kWP = 22\,000\ \text{kW}:

  • P=22000=148.32.\sqrt{P} = \sqrt{22\,000} = 148.32.
  • H5/4=951.25H^{5/4} = 95^{1.25}. Compute: ln95=4.5539\ln 95 = 4.5539; ×1.25=5.6924\times1.25 = 5.6924; e5.6924=296.6e^{5.6924} = 296.6.
Ns=500×148.32296.6=74162296.6=250.0250 (metric, kW).N_s = \frac{500 \times 148.32}{296.6} = \frac{74\,162}{296.6} = 250.0 \approx \textbf{250 (metric, kW)}.

For H95 mH \approx 95\ \text{m} and Ns250N_s \approx 250, the value lies in the Francis turbine range (Francis: roughly Ns60N_s \approx 60400400 metric; heads 30\sim 30300 m300\ \text{m}). A Pelton (Ns35N_s \lesssim 35 per jet, very high head) is unsuitable at 95 m, and a Kaplan (Ns300N_s \gtrsim 30010001000, low head) is unsuitable at this head. Select a (medium-speed) Francis turbine.

(b) Number of poles

Synchronous-speed relation: N=120fpp=120fN.N = \dfrac{120 f}{p}\Rightarrow p = \dfrac{120 f}{N}.

p=120×50500=6000500=12 poles  (12 poles,i.e.6polepairs).p = \frac{120 \times 50}{500} = \frac{6000}{500} = 12\ \text{poles} \;(\textbf{12 poles}, i.e. 6 pole-pairs).

This is an even integer, so the direct coupling at 500 rpm is feasible. ✔

(c) Impulse vs reaction turbines and the draft tube

FeatureImpulse (e.g. Pelton)Reaction (e.g. Francis/Kaplan)
Energy at runner inletAll kinetic (water at atmospheric pressure)Both pressure + kinetic energy
Pressure across runnerConstant (atmospheric)Drops through the runner
FlowPartial admission (jets on some buckets)Full admission (runner fully in water)
CasingOpen to atmosphereClosed spiral casing, runs full
Head rangeHigh head, low dischargeMedium–low head, larger discharge

Why a draft tube is essential for reaction turbines: A reaction runner is set above the tailwater and the water leaves it with appreciable pressure and velocity. The gradually diverging draft tube (i) recovers the residual kinetic energy at the runner exit by converting it to pressure (reducing exit losses, raising efficiency), and (ii) allows the runner to be set above tailwater while still using the full head down to the tailrace by creating a partial vacuum (suction head). For an impulse turbine the water already leaves the buckets at atmospheric pressure with little useful kinetic energy and the runner must sit above the tailwater discharging freely to atmosphere; a draft tube would serve no purpose (and any submergence would drown the buckets), so it is not used.

turbinesspecific-speedturbine-selection
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short6 marks

(a) Classify hydropower plants on the basis of head and on the basis of flow availability / operation (storage, run-of-river, peaking run-of-river, pumped storage), giving the distinguishing feature of each.

(b) With reference to Nepal, explain why most developed schemes are run-of-river rather than large storage, and name two operating storage/peaking projects or one prominent reservoir scheme under development.

(a) Classification of hydropower plants

By head:

  • Low head (typically <30 m< 30\ \text{m}): large discharge, Kaplan/propeller turbines, often river-bed plants.
  • Medium head (30\approx 30300 m300\ \text{m}): Francis turbines common.
  • High head (>300 m> 300\ \text{m}): small discharge, long penstocks, Pelton/Turgo turbines.

By flow availability / operation:

  • Storage (reservoir) plant: a dam stores monsoon water in a reservoir and releases it on demand; can firm up flow and provide seasonal regulation and peaking.
  • Run-of-river (RoR) plant: little or no storage; generation follows the natural river flow, so output is high in the wet season and low in the dry season.
  • Peaking run-of-river (PRoR): has a small pondage (hours to a day) to re-time daily flow and meet peak demand while still essentially passing the river flow.
  • Pumped-storage plant: pumps water to an upper reservoir during off-peak (cheap) hours and generates during peaks; a net energy consumer but valuable for peaking/storage of energy.

(b) Nepalese context

Most Nepalese schemes are run-of-river because: large storage dams require huge reservoirs, large investment, long lead times, resettlement and submergence of land in steep valleys, and carry seismic and sediment (rapid reservoir-sedimentation) risks; RoR plants are cheaper, quicker to build and well-suited to steep rivers with high heads. The drawback is large seasonal variation (dry-season power deficit), which is why peaking/storage projects are increasingly pursued.

Examples: Kulekhani I and II (Nepal's principal storage/peaking reservoir scheme) provide dry-season peaking. A prominent reservoir/storage scheme under development is the Budhi Gandaki (and the proposed Nalsing Gad / Tanahu Seti storage projects). Large RoR examples include Upper Tamakoshi (456 MW, PRoR).

hydropower-in-nepalplant-types
7short6 marks

(a) Differentiate between a forebay and a surge tank, stating clearly when each is provided.

(b) A forebay is to provide pondage for 15 minutes15\ \text{minutes} of operation at the full design discharge of Q=10 m3/sQ = 10\ \text{m}^3/\text{s}. If the usable water-level fluctuation in the forebay is limited to 2.5 m2.5\ \text{m}, estimate the required plan (surface) area of the forebay.

(c) List three essential components/features that a forebay should incorporate.

(a) Forebay vs surge tank

  • A forebay is an enlarged basin (a small pond) at the end of an open/free-surface headrace canal, just before the penstock intake. Because the headrace is already at atmospheric pressure, the forebay simply provides a small pondage and a smooth transition into the penstock, and traps any remaining floating debris/sediment. It is provided when the headrace is an open canal.
  • A surge tank is provided when the conveyance is a closed pressure conduit (tunnel/pipe); it gives a free water surface to relieve water-hammer pressures and supply/store water during load changes. It is provided for long pressurised headrace tunnels.

In short: forebay ↔ open-channel headrace (no pressure-transient role); surge tank ↔ pressurised tunnel (controls water hammer).

(b) Required forebay plan area

Required pondage volume = discharge × time:

V=Q×t=10 m3/s×(15×60) s=10×900=9000 m3.V = Q \times t = 10\ \text{m}^3/\text{s} \times (15 \times 60)\ \text{s} = 10 \times 900 = 9000\ \text{m}^3.

Plan area from usable depth fluctuation Δh=2.5 m\Delta h = 2.5\ \text{m}:

A=VΔh=90002.5=3600 m23600 m2.A = \frac{V}{\Delta h} = \frac{9000}{2.5} = 3600\ \text{m}^2 \approx \textbf{3600 m}^2.

(E.g. a basin roughly 90 m×40 m90\ \text{m} \times 40\ \text{m}.)

(c) Three essential components/features of a forebay

  1. A trash rack at the penstock intake to stop floating debris.
  2. A spillway / overflow weir to discharge excess water safely during load rejection.
  3. A gate / control & flushing arrangement (penstock intake gate plus a bottom flushing/scour outlet for settled sediment); often with sufficient submergence over the penstock mouth to prevent air-entraining vortices.
forebayintakeheadrace
8short6 marks

A hydropower project has an installed capacity of 30 MW30\ \text{MW} and an estimated capital (overnight) cost of NRs 4.5 billion\text{NRs } 4.5\ \text{billion}. The annual fixed charges (interest + depreciation + insurance) are 11%11\% of the capital cost and the annual operation & maintenance (O&M) cost is NRs 60 million\text{NRs } 60\ \text{million}. The plant operates at a capacity factor of 0.550.55.

(a) Compute the annual energy generated (in GWh).

(b) Compute the total annual cost and hence the generation (unit) cost of energy in NRs per kWh.

(c) Define load factor and capacity factor and state how they differ.

(a) Annual energy generated

Rated annual energy =Pinst×8760 h= P_{inst}\times 8760\ \text{h}, actual energy == rated ×\times capacity factor:

E=30000 kW×8760 h×0.55.E = 30\,000\ \text{kW} \times 8760\ \text{h} \times 0.55.

Step: 30000×8760=262800000 kWh=262.8 GWh (rated).30\,000 \times 8760 = 262\,800\,000\ \text{kWh} = 262.8\ \text{GWh (rated)}.

E=262.8×0.55=144.54 GWh144.5 GWh/yr  (=1.4454×108 kWh).E = 262.8 \times 0.55 = 144.54\ \text{GWh} \approx \textbf{144.5 GWh/yr} \;(= 1.4454\times10^8\ \text{kWh}).

(b) Annual cost and unit generation cost

Annual fixed charges =0.11×4.5×109=NRs 495×106=NRs 495 million.= 0.11 \times 4.5\times10^9 = \text{NRs } 495\times10^6 = \text{NRs } 495\ \text{million}.

Total annual cost == fixed charges ++ O&M:

Cannual=495+60=NRs 555 million=5.55×108 NRs/yr.C_{annual} = 495 + 60 = \text{NRs } 555\ \text{million} = 5.55\times10^8\ \text{NRs/yr}.

Unit generation cost:

c=CannualE=5.55×108 NRs1.4454×108 kWh=3.840 NRs/kWhNRs 3.84 per kWh.c = \frac{C_{annual}}{E} = \frac{5.55\times10^8\ \text{NRs}}{1.4454\times10^8\ \text{kWh}} = 3.840\ \text{NRs/kWh} \approx \textbf{NRs 3.84 per kWh}.

Step check: 5.55/1.4454=3.840.5.55/1.4454 = 3.840.

(c) Load factor vs capacity factor

  • Load factor =average loadpeak (maximum) load over the period= \dfrac{\text{average load}}{\text{peak (maximum) load over the period}}. It describes how uniformly the load/demand is spread; it is a property of the load curve.
  • Capacity (plant) factor =actual energy generatedenergy if run at installed capacity for the whole period=average loadinstalled capacity.= \dfrac{\text{actual energy generated}}{\text{energy if run at installed capacity for the whole period}} = \dfrac{\text{average load}}{\text{installed capacity}}. It describes how fully the plant is utilised.

Difference: they share the same numerator (average load) but different denominators — load factor uses the maximum demand, capacity factor uses the installed capacity. If maximum demand equals installed capacity the two are equal; since installed capacity \geq peak load generally, capacity factor \leq load factor.

economicsannual-costtariff
9short5 marks

(a) Define cavitation in a reaction turbine and explain the role of Thoma's cavitation factor σ\sigma.

(b) A Francis turbine operates under a net head of H=80 mH = 80\ \text{m}. The critical Thoma factor for the runner is σc=0.10\sigma_c = 0.10. The atmospheric pressure head at site is Ha=9.6 mH_a = 9.6\ \text{m} (water column) and the vapour-pressure head is Hv=0.3 mH_v = 0.3\ \text{m}. Determine the maximum permissible suction head (turbine setting above tailwater) HsH_s to just avoid cavitation.

(c) State two practical measures to reduce cavitation damage.

(a) Cavitation and Thoma's factor

Cavitation is the formation of vapour bubbles in regions where the local pressure in the flowing water falls to (or below) the vapour pressure — typically on the suction side of the runner blades and at the draft-tube inlet. When these bubbles are carried to higher-pressure zones they collapse violently, producing pitting/erosion of the metal, noise, vibration and loss of efficiency.

Thoma's cavitation factor is the dimensionless number

σ=HaHvHsH,\sigma = \frac{H_a - H_v - H_s}{H},

where HsH_s is the suction head (runner set above tailwater). Cavitation is avoided as long as the actual σ\sigma is greater than the critical value σc\sigma_c for that runner; σc\sigma_c rises with specific speed, so high-specific-speed runners must be set lower (smaller or even negative HsH_s).

(b) Maximum permissible suction head

At the limiting condition σ=σc\sigma = \sigma_c:

σc=HaHvHsH    Hs=HaHvσcH.\sigma_c = \frac{H_a - H_v - H_s}{H} \;\Rightarrow\; H_s = H_a - H_v - \sigma_c H.

Substitute:

Hs=9.60.3(0.10×80)=9.60.38.0=1.3 m.H_s = 9.6 - 0.3 - (0.10 \times 80) = 9.6 - 0.3 - 8.0 = 1.3\ \text{m}. Hs1.3 m above tailwater.\boxed{H_s \le \textbf{1.3 m above tailwater}.}

The runner must be set no higher than 1.3 m above the tailwater level; a lower setting (more submergence) gives an additional safety margin.

(c) Two measures to reduce cavitation damage

  1. Set the runner lower (reduce or make negative the suction head) so that σ>σc\sigma > \sigma_c with a margin.
  2. Use cavitation-resistant materials / surfacing (e.g. stainless-steel runners or weld-overlay on vulnerable zones) and maintain smooth, well-profiled blade surfaces; admitting a small amount of air to the draft tube also cushions bubble collapse.
turbinescavitationdraft-tube
10short5 marks

(a) Distinguish between a surface powerhouse and an underground powerhouse, giving one advantage of each.

(b) Sketch (describe) and label the main components of a typical surface powerhouse, identifying the substructure, intermediate and superstructure divisions.

(c) State two factors that govern the choice of an underground powerhouse.

(a) Surface vs underground powerhouse

  • Surface powerhouse: built at ground level (usually near the tailrace/river). Advantage: lower construction cost, simpler access, ventilation and crane handling, easier construction and maintenance.
  • Underground powerhouse: excavated as a cavern inside the rock mass. Advantage: protection from rockfall/avalanche/flood, shorter pressure conduits in steep terrain, security, and freedom from surface land/topographic constraints (good for high-head Himalayan sites).

(b) Components of a surface powerhouse (described layout)

            ____________________________________
           |  Superstructure: roof, walls,      |
           |  EOT gantry/travelling crane,      |
           |  control room, switchgear          |
           |------------------------------------|
  Penstock |  Intermediate (generator floor):   |
  =====>===|  generator, governor, valves,      |
           |  turbine inlet / spiral casing     |
           |------------------------------------|
           |  Substructure: turbine, draft tube,|
           |  draft-tube gates -> TAILRACE ===> |
           |____________________________________|
  • Substructure (below generator floor): foundation, scroll/spiral casing, turbine runner, draft tube and draft-tube gates discharging to the tailrace. It transmits loads to the foundation and houses the water-conducting parts.
  • Intermediate part (generator/machine floor): turbine main shaft, generator, governor, main inlet valve, auxiliaries.
  • Superstructure: building enclosure (walls, roof), the EOT travelling crane for erection/maintenance, control room, switchgear and ventilation.

(c) Two factors governing choice of an underground powerhouse

  1. Geology/rock quality — sound, self-supporting rock is needed to form a stable cavern economically.
  2. Topography & hazards — steep, narrow gorges or high-head sites where there is no safe surface bench, or where avalanche/landslide/flood protection (and security) makes a cavern preferable.
powerhouselayoutcomponents
11short10 marks

A Pelton turbine is supplied through a single nozzle under a net head of H=320 mH = 320\ \text{m}. The discharge is Q=0.85 m3/sQ = 0.85\ \text{m}^3/\text{s}. The coefficient of velocity of the nozzle is Cv=0.98C_v = 0.98, the bucket speed ratio (peripheral-velocity factor) is ϕ=0.46\phi = 0.46, and the wheel runs at N=600 rpmN = 600\ \text{rpm}.

(a) Compute the jet velocity V1V_1 and the jet diameter dd.

(b) Compute the wheel (pitch) diameter DD and verify the jet-ratio m=D/dm = D/d (state whether it is acceptable).

(c) If the bucket deflection angle gives a hydraulic (wheel) efficiency of ηh=0.88\eta_h = 0.88 and the overall efficiency is ηo=0.85\eta_o = 0.85, compute the water power, shaft power, and check the required number of buckets using z=0.5m+15z = 0.5\,m + 15.

(a) Jet velocity and jet diameter

Jet velocity from the nozzle:

V1=Cv2gH=0.982×9.81×320.V_1 = C_v\sqrt{2gH} = 0.98\sqrt{2 \times 9.81 \times 320}.

2×9.81×320=6278.42 \times 9.81 \times 320 = 6278.4; 6278.4=79.24 m/s\sqrt{6278.4} = 79.24\ \text{m/s}.

V1=0.98×79.24=77.66 m/s77.7 m/s.V_1 = 0.98 \times 79.24 = 77.66\ \text{m/s} \approx \textbf{77.7 m/s}.

Jet diameter from continuity, Q=π4d2V1Q = \dfrac{\pi}{4}d^2 V_1:

d=4QπV1=4×0.85π×77.66=3.40243.97=0.013936=0.1181 m.d = \sqrt{\frac{4Q}{\pi V_1}} = \sqrt{\frac{4 \times 0.85}{\pi \times 77.66}} = \sqrt{\frac{3.40}{243.97}} = \sqrt{0.013936} = 0.1181\ \text{m}. d0.118 m  (118 mm).d \approx \textbf{0.118 m} \;(118\ \text{mm}).

(b) Wheel (pitch) diameter and jet ratio

Bucket (peripheral) velocity:

u=ϕ2gH=0.46×79.24=36.45 m/s.u = \phi\sqrt{2gH} = 0.46 \times 79.24 = 36.45\ \text{m/s}.

Wheel diameter from u=πDN60u = \dfrac{\pi D N}{60}:

D=60uπN=60×36.45π×600=2187.01884.96=1.160 m1.16 m.D = \frac{60\,u}{\pi N} = \frac{60 \times 36.45}{\pi \times 600} = \frac{2187.0}{1884.96} = 1.160\ \text{m} \approx \textbf{1.16 m}.

Jet ratio:

m=Dd=1.1600.1181=9.829.8.m = \frac{D}{d} = \frac{1.160}{0.1181} = 9.82 \approx \textbf{9.8}.

The usual acceptable range is m10m \approx 101414 (sometimes 6–35). A value of 9.8\approx 9.8 is at the low but acceptable end for a single-jet wheel; if a larger ratio were wanted, a lower speed (larger DD) or smaller jet (more jets) could be used.

(c) Water power, shaft power, number of buckets

Water (available) power:

Pwater=ρgQH=9.81×0.85×320=2668.3 kW2.67 MW.P_{water} = \rho g Q H = 9.81 \times 0.85 \times 320 = 2668.3\ \text{kW} \approx \textbf{2.67 MW}.

Step: 9.81×0.85=8.33859.81\times0.85 = 8.3385; ×320=2668.3 kW\times320 = 2668.3\ \text{kW}.

Shaft (output) power using overall efficiency:

Pshaft=ηoPwater=0.85×2668.3=2268.1 kW2.27 MW.P_{shaft} = \eta_o\, P_{water} = 0.85 \times 2668.3 = 2268.1\ \text{kW} \approx \textbf{2.27 MW}.

(The hydraulic efficiency ηh=0.88\eta_h = 0.88 represents the runner/wheel conversion; the runner (wheel) power would be 0.88×2668.3=2348 kW0.88 \times 2668.3 = 2348\ \text{kW}, and the remaining mechanical/volumetric losses bring the shaft output down to ηoPwater=2268 kW\eta_o\,P_{water} = 2268\ \text{kW}.)

Number of buckets (Taygun's rule, z=0.5m+15z = 0.5\,m + 15):

z=0.5×9.82+15=4.91+15=19.920 buckets.z = 0.5 \times 9.82 + 15 = 4.91 + 15 = 19.9 \approx \textbf{20 buckets}.

Providing about 20 buckets ensures no jet water escapes between successive buckets, which is satisfactory for this wheel.

pelton-turbineturbine-designpower

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) question paper 2077?
The full BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2077 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Hydropower Engineering (IOE, CE 755) 2077 paper come with solutions?
Yes. Every question on this Hydropower Engineering (IOE, CE 755) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2077 paper?
The BE Civil Engineering (IOE, TU) Hydropower Engineering (IOE, CE 755) 2077 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Hydropower Engineering (IOE, CE 755) past paper free?
Yes — reading and attempting this Hydropower Engineering (IOE, CE 755) past paper on Kekkei is completely free.