Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long10 marks

The recorded census population of a hill town in Nepal is given below:

Year (AD)1991200120112021
Population24,00030,00039,00050,000

(a) Forecast the population for the year 2041 using the Geometric Increase (geometric mean) method and the Incremental Increase method.

(b) Adopting the geometric forecast for 2041 and a per-capita demand of 135 litres per capita per day (lpcd), estimate the maximum daily demand in m3/day\text{m}^3/\text{day} assuming the maximum-day factor is 1.8. State one limitation of the geometric method for Nepali hill towns.

Decadal data and increments

YearPopulationIncrease% Increase (geometric)Incremental increase
199124,000
200130,0006,0006000/24000 = 25.00%
201139,0009,0009000/30000 = 30.00%+3,000
202150,00011,00011000/39000 = 28.205%+2,000

(a) Geometric Increase method

Geometric mean of the percentage increases (use the decadal growth ratios):

rg=0.2500×0.3000×0.282053=0.0211543=0.27645    27.645% per decader_g = \sqrt[3]{0.2500 \times 0.3000 \times 0.28205} = \sqrt[3]{0.021154} = 0.27645 \;\Rightarrow\; 27.645\% \text{ per decade}

Forecast to 2041 = 2 decades beyond 2021:

Pn=P0(1+rg)n=50000×(1.27645)2P_n = P_0 (1+r_g)^n = 50000 \times (1.27645)^2 =50000×1.62933=81,46681,500 persons= 50000 \times 1.62933 = 81{,}466 \approx \mathbf{81{,}500 \text{ persons}}

Incremental Increase method

Average increase xˉ=6000+9000+110003=260003=8,666.7\bar{x} = \dfrac{6000+9000+11000}{3} = \dfrac{26000}{3} = 8{,}666.7

Average incremental increase yˉ=3000+20002=2,500\bar{y} = \dfrac{3000+2000}{2} = 2{,}500

Pn=P0+nxˉ+n(n+1)2yˉ,n=2P_n = P_0 + n\bar{x} + \frac{n(n+1)}{2}\bar{y}, \quad n = 2 =50000+2(8666.7)+2×32(2500)=50000+17333.4+7500=74,83374,800 persons= 50000 + 2(8666.7) + \frac{2 \times 3}{2}(2500) = 50000 + 17333.4 + 7500 = \mathbf{74{,}833 \approx 74{,}800 \text{ persons}}

(b) Maximum daily demand (geometric forecast = 81,466)

Average daily demand:

Qavg=81466×1351000=10,998  m3/dayQ_{avg} = \frac{81466 \times 135}{1000} = 10{,}998 \;\text{m}^3/\text{day}

Maximum daily demand:

Qmax=1.8×10998=19,79719,800  m3/dayQ_{max} = 1.8 \times 10998 = \mathbf{19{,}797 \approx 19{,}800 \;\text{m}^3/\text{day}}

Limitation: The geometric method assumes a constant percentage growth and tends to over-estimate for towns approaching saturation. Nepali hill towns often grow by migration spurts and out-migration, so growth is irregular; the geometric method ignores topographic and economic ceilings on growth.

population-forecastingwater-demand
2long10 marks

(a) Derive the expression for the settling velocity of a discrete spherical particle in the laminar (Stokes') regime, starting from the balance of gravity, buoyancy and drag forces.

(b) A plain rectangular sedimentation tank is to treat 6 MLD (6,000m3/day6{,}000 \,\text{m}^3/\text{day}). Design the tank to remove particles having a settling velocity of 0.5 mm/s (vs=0.0005m/sv_s = 0.0005\,\text{m/s}). Determine the required surface area, and if the tank length-to-width ratio is 4:1 with an effective depth of 3 m, find the dimensions, the detention time, and the horizontal flow velocity. Comment whether the horizontal velocity is acceptable.

(a) Settling velocity (Stokes' law)

For a particle of diameter dd, density ρs\rho_s settling in water of density ρw\rho_w and dynamic viscosity μ\mu:

Net downward force (gravity − buoyancy):

Fg=π6d3(ρsρw)gF_g = \frac{\pi}{6} d^3 (\rho_s - \rho_w) g

Drag force in laminar flow (Stokes): FD=3πμdvsF_D = 3\pi \mu d \, v_s

At terminal (settling) velocity, Fg=FDF_g = F_D:

π6d3(ρsρw)g=3πμdvs\frac{\pi}{6} d^3 (\rho_s - \rho_w) g = 3\pi \mu d\, v_s vs=g(ρsρw)d218μ\boxed{v_s = \frac{g(\rho_s - \rho_w) d^2}{18\mu}}

This is valid for Reynolds number Re=ρwvsd/μ<1R_e = \rho_w v_s d/\mu < 1.

(b) Sedimentation tank design

Flow: Q=6000m3/day=600086400=0.06944m3/sQ = 6000\,\text{m}^3/\text{day} = \dfrac{6000}{86400} = 0.06944\,\text{m}^3/\text{s}

Surface area (overflow rate = settling velocity of design particle):

A=Qvs=0.069440.0005=138.9m2139m2A = \frac{Q}{v_s} = \frac{0.06944}{0.0005} = 138.9\,\text{m}^2 \approx \mathbf{139\,\text{m}^2}

Dimensions with L=4BL = 4B:

A=L×B=4B2=138.9B2=34.72B=5.89mA = L \times B = 4B^2 = 138.9 \Rightarrow B^2 = 34.72 \Rightarrow B = 5.89\,\text{m}

Adopt B=6mB = 6\,\text{m}, L=24mL = 24\,\text{m} (provided area =144m2139= 144\,\text{m}^2 \ge 139, OK).

Volume and detention time (depth = 3 m):

V=L×B×H=24×6×3=432m3V = L \times B \times H = 24 \times 6 \times 3 = 432\,\text{m}^3 td=VQ=4320.06944=6221s=1.73hourst_d = \frac{V}{Q} = \frac{432}{0.06944} = 6221\,\text{s} = \mathbf{1.73\,\text{hours}}

Horizontal flow velocity: Cross-sectional area =B×H=6×3=18m2= B \times H = 6 \times 3 = 18\,\text{m}^2

vh=QB×H=0.0694418=0.00386m/s=3.86mm/sv_h = \frac{Q}{B \times H} = \frac{0.06944}{18} = 0.00386\,\text{m/s} = \mathbf{3.86\,\text{mm/s}}

Comment: Horizontal velocity of 3.86 mm/s is well below the usual limit of ~9 mm/s (and below the scour velocity), so no re-suspension of settled flocs is expected. Detention time of ~1.7 h is slightly low for plain sedimentation (typical 2–4 h); depth or area could be increased if a longer detention is desired.

sedimentationtreatment
3long8 marks

(a) Differentiate between a slow sand filter and a rapid sand filter with respect to rate of filtration, mechanism of purification, area required, and cleaning method (any four points in tabular form).

(b) A rapid sand filter unit treats 4 MLD at a filtration rate of 5,000 litres/m²/hour. Determine the total filter area required and the number of filter beds, taking each bed as 5 m × 4 m and providing one additional bed as standby. What is the filtration rate per working bed when the standby bed is in service?

(a) Slow vs Rapid sand filter

FeatureSlow Sand FilterRapid Sand Filter
Rate of filtration100–200 L/m²/h (low)3,000–6,000 L/m²/h (high)
Purification mechanismMainly biological (schmutzdecke) + strainingMainly physical–chemical; needs prior coagulation
Area requiredLarge (low rate)Small (high rate)
CleaningScraping top sand layer (manual, infrequent)Backwashing with water/air (frequent, ~24–48 h)

(b) Rapid sand filter sizing

Flow: Q=4MLD=4,000,000L/dayQ = 4\,\text{MLD} = 4{,}000{,}000\,\text{L/day}

Filtration over 24 h, rate =5000L/m2/h= 5000\,\text{L/m}^2/\text{h}:

Hourly flow=4,000,00024=166,667L/h\text{Hourly flow} = \frac{4{,}000{,}000}{24} = 166{,}667\,\text{L/h} Required area=166,6675000=33.33m2\text{Required area} = \frac{166{,}667}{5000} = 33.33\,\text{m}^2

Area of one bed =5×4=20m2= 5 \times 4 = 20\,\text{m}^2

Number of working beds =33.3320=1.67= \dfrac{33.33}{20} = 1.67 \Rightarrow 2 working beds

Provide 1 standby \Rightarrow total = 3 beds.

Provided working area =2×20=40m2= 2 \times 20 = 40\,\text{m}^2.

Filtration rate when standby in service (i.e. one working bed out, all 3 used = still only need to cover Q with available beds; with 2 beds working the rate is):

Rate per working bed (2 beds)=166,6672×20=4,167L/m2/h\text{Rate per working bed (2 beds)} = \frac{166{,}667}{2 \times 20} = \mathbf{4{,}167\,\text{L/m}^2/\text{h}}

If one of the three beds is under backwash and only 2 remain in service, the rate is 4,167 L/m²/h, which is below the design maximum of 5,000 L/m²/h — so operation with the standby maintains a safe filtration rate. Adopt 3 beds, each 5 m × 4 m.

filtrationtreatment
4long8 marks

A dead-end (branched) distribution main carries water from a service reservoir at point A (ground level reservoir water surface at RL 100.0 m) to a node B at RL 70.0 m, a distance of 1,500 m. The design flow is 40 litres/second. Using the Hazen–Williams formula with C=120C = 120, determine a suitable commercial pipe diameter (choose from 250 mm, 300 mm, 350 mm) so that the residual head at B is at least 12 m. Show the head-loss check for the selected diameter.

Hazen–Williams: hf=10.67Q1.852C1.852D4.87Lh_f = \dfrac{10.67\,Q^{1.852}}{C^{1.852}\,D^{4.87}}\,L (SI: QQ in m³/s, DD in m, LL in m).

Given data

  • Q=40L/s=0.040m3/sQ = 40\,\text{L/s} = 0.040\,\text{m}^3/\text{s}, L=1500mL = 1500\,\text{m}, C=120C = 120
  • Available static head =100.070.0=30.0m= 100.0 - 70.0 = 30.0\,\text{m}
  • Required residual head at B 12m\ge 12\,\text{m} \Rightarrow allowable head loss hf,allow=3012=18mh_{f,allow} = 30 - 12 = 18\,\text{m}

Hazen–Williams constant part:

hf=10.67×Q1.852C1.852×D4.87×Lh_f = \frac{10.67 \times Q^{1.852}}{C^{1.852} \times D^{4.87}} \times L

Q1.852=0.0401.852Q^{1.852} = 0.040^{1.852}. ln0.040=3.2189\ln 0.040 = -3.2189; ×1.852=5.9614\times 1.852 = -5.9614; e5.9614=0.002576e^{-5.9614} = 0.002576.

C1.852=1201.852C^{1.852} = 120^{1.852}. ln120=4.7875\ln 120 = 4.7875; ×1.852=8.8665\times 1.852 = 8.8665; e8.8665=7102e^{8.8665} = 7102.

Numerator constant =10.67×0.002576×1500=41.23= 10.67 \times 0.002576 \times 1500 = 41.23

So hf=41.237102×D4.87=0.005806D4.87h_f = \dfrac{41.23}{7102 \times D^{4.87}} = \dfrac{0.005806}{D^{4.87}}

Check D = 250 mm = 0.25 m: D4.87=0.254.87D^{4.87} = 0.25^{4.87}: ln0.25=1.3863\ln 0.25 = -1.3863; ×4.87=6.7513\times 4.87 = -6.7513; e6.7513=0.001168e^{-6.7513} = 0.001168.

hf=0.0058060.001168=4.97mh_f = \frac{0.005806}{0.001168} = 4.97\,\text{m}

Wait — recompute carefully. 0.005806/0.001168=4.970.005806/0.001168 = 4.97. This is less than 18 m, so even 250 mm appears adequate. Let us verify the velocity to choose sensibly.

Velocity in 250 mm pipe: A=π4(0.25)2=0.04909m2A = \dfrac{\pi}{4}(0.25)^2 = 0.04909\,\text{m}^2; v=0.040/0.04909=0.815m/sv = 0.040/0.04909 = 0.815\,\text{m/s} — acceptable (0.6–2.0 m/s range).

Selected diameter: 250 mm, giving head loss hf=4.97mh_f = 4.97\,\text{m}.

Residual head check at B:

HB=30.04.97=25.0m    12mH_B = 30.0 - 4.97 = 25.0\,\text{m} \;\ge\; 12\,\text{m} \quad ✓

Conclusion: A 250 mm diameter pipe is sufficient. Residual head at B =25.0m= \mathbf{25.0\,\text{m}} (well above the 12 m requirement), and the velocity of 0.82 m/s lies within the recommended range, so the 250 mm pipe is the economical choice. Larger diameters (300/350 mm) give even lower head loss but are unnecessarily costly and produce low velocities that risk sediment deposition.

distribution-systempipe-network
5long8 marks

A centrifugal pump lifts water from a sump to an overhead reservoir in a gravity-fed rural scheme upgrade. The pump delivers 25 litres/second against a static head of 45 m. Total friction and minor losses in the rising main amount to 6 m. Take pump efficiency 70% and motor efficiency 90%.

(a) Compute the total manometric head, the water power, the shaft (brake) power, and the input electrical power.

(b) If the pump runs 8 hours/day, compute the daily energy consumption in kWh and the daily energy cost at NPR 11 per kWh.

Given: Q=25L/s=0.025m3/sQ = 25\,\text{L/s} = 0.025\,\text{m}^3/\text{s}, static head Hs=45mH_s = 45\,\text{m}, losses hL=6mh_L = 6\,\text{m}, ηpump=0.70\eta_{pump} = 0.70, ηmotor=0.90\eta_{motor} = 0.90, ρg=9810N/m3\rho g = 9810\,\text{N/m}^3.

(a) Heads and powers

Total manometric head:

H=Hs+hL=45+6=51mH = H_s + h_L = 45 + 6 = \mathbf{51\,\text{m}}

Water (hydraulic) power:

Pw=ρgQH=9810×0.025×51=12,508W=12.51kWP_w = \rho g Q H = 9810 \times 0.025 \times 51 = 12{,}508\,\text{W} = \mathbf{12.51\,\text{kW}}

Shaft (brake) power = water power / pump efficiency:

Pshaft=12.510.70=17.87kWP_{shaft} = \frac{12.51}{0.70} = \mathbf{17.87\,\text{kW}}

Input electrical power = shaft power / motor efficiency:

Pelec=17.870.90=19.86kWP_{elec} = \frac{17.87}{0.90} = \mathbf{19.86\,\text{kW}}

(Equivalently Pelec=Pw/(ηpumpηmotor)=12.51/(0.70×0.90)=12.51/0.63=19.86kWP_{elec} = P_w/(\eta_{pump}\eta_{motor}) = 12.51/(0.70\times0.90) = 12.51/0.63 = 19.86\,\text{kW}.)

(b) Daily energy and cost

Running 8 h/day:

E=Pelec×t=19.86×8=158.9kWh/dayE = P_{elec} \times t = 19.86 \times 8 = \mathbf{158.9\,\text{kWh/day}}

Daily cost:

Cost=158.9×11=NPR  1,748/day\text{Cost} = 158.9 \times 11 = \mathbf{NPR\;1{,}748/\text{day}}

(Approximately NPR 1,750 per day; ~NPR 52,400 per 30-day month.)

pumpingrural-water-supply
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short6 marks

A water treatment plant treats 10 MLD and uses alum at a dose of 28 mg/L. (a) Compute the daily alum requirement in kg. (b) If alum is fed as a 5% (by weight) solution, what is the required solution feed rate in litres/hour (take solution density ≈ 1,000 kg/m³)? (c) Briefly state why alum requires sufficient natural alkalinity in the raw water.

(a) Daily alum requirement

Q=10MLD=10×106L/dayQ = 10\,\text{MLD} = 10 \times 10^6\,\text{L/day}, dose =28mg/L= 28\,\text{mg/L}.

Alum=10×106×28106mg/day in g?\text{Alum} = \frac{10\times10^6 \times 28}{10^6}\,\text{mg/day in g?}

Work in consistent units: mass =Q×dose=10×106L×28mg/L=2.8×108mg=280kg/day= Q \times \text{dose} = 10\times10^6\,\text{L} \times 28\,\text{mg/L} = 2.8\times10^8\,\text{mg} = 280\,\text{kg/day}.

=280kg/day\boxed{= \mathbf{280\,\text{kg/day}}}

(b) Solution feed rate (5% solution)

A 5% solution contains 5 kg alum per 100 kg solution. With density ≈ 1000 kg/m³ (1 kg/L), 100 kg solution = 100 L, so it carries 50 g alum per litre (i.e. 0.05 kg/L).

Daily solution volume:

V=280kg/day0.05kg/L=5,600L/dayV = \frac{280\,\text{kg/day}}{0.05\,\text{kg/L}} = 5{,}600\,\text{L/day}

Feed rate:

=560024=233.3L/hour= \frac{5600}{24} = \mathbf{233.3\,\text{L/hour}}

(c) Need for alkalinity: Alum [Al2(SO4)3\text{Al}_2(\text{SO}_4)_3] hydrolyses to form the insoluble floc Al(OH)3\text{Al(OH)}_3, releasing H+\text{H}^+ (acidity). Natural alkalinity (bicarbonates) neutralises this acid and supplies OH\text{OH}^- to complete floc formation. Without enough alkalinity, the pH drops, floc formation is poor, and supplementary alkali (lime/soda ash) must be added.

coagulationtreatment
7short6 marks

(a) A storage reservoir of 500 m³ is to be disinfected to a chlorine dose of 2.5 mg/L, of which 0.6 mg/L is the chlorine demand. Compute the mass of bleaching powder required if the bleaching powder contains 30% available chlorine, and find the residual chlorine left after demand is satisfied. (b) State two factors that affect the efficiency of chlorination.

(a) Bleaching powder and residual chlorine

Volume V=500m3=500,000LV = 500\,\text{m}^3 = 500{,}000\,\text{L}, applied dose =2.5mg/L= 2.5\,\text{mg/L}.

Mass of chlorine required:

Cl2=500,000×2.5=1,250,000mg=1.25kg\text{Cl}_2 = 500{,}000 \times 2.5 = 1{,}250{,}000\,\text{mg} = 1.25\,\text{kg}

Bleaching powder has 30% available chlorine:

Bleaching powder=1.250.30=4.17kg\text{Bleaching powder} = \frac{1.25}{0.30} = \mathbf{4.17\,\text{kg}}

Residual chlorine = applied dose − demand:

=2.50.6=1.9mg/L= 2.5 - 0.6 = \mathbf{1.9\,\text{mg/L}}

(This exceeds the typical minimum free residual of 0.2 mg/L at the consumer end, providing a safe margin.)

(b) Factors affecting chlorination efficiency (any two):

  1. Contact time — longer contact gives more complete disinfection (CT value).
  2. pH — at higher pH the weaker hypochlorite ion (OCl\text{OCl}^-) dominates over the more potent hypochlorous acid (HOCl\text{HOCl}), reducing efficiency.
  3. Temperature — higher temperature speeds kill rate.
  4. Turbidity/organic matter — shields organisms and exerts chlorine demand.
disinfectionwater-quality
8short6 marks

(a) Classify the sources of water for a public water supply with one example of each. (b) Define the following water-quality parameters and state their significance: turbidity, total hardness, and most probable number (MPN).

(a) Sources of water

CategorySub-typeExample
Surface sourcesRivers/streamsBagmati, Trishuli
Lakes/pondsPhewa Lake
Impounded reservoirsKulekhani reservoir
Sub-surface (ground) sourcesSpringsHill-side spring (kuwa/mul)
Wells (open/tube)Tube well in Terai
Infiltration galleriesRiver-bank gallery
Rain waterRoof catchmentRWH tank in hills

(b) Water-quality parameters

  • Turbidity: A measure of the cloudiness of water caused by suspended/colloidal matter; expressed in NTU. Significance: high turbidity shields pathogens from disinfection, is aesthetically objectionable, and indicates need for coagulation/filtration. Drinking-water guideline ≤ 5 NTU (ideally < 1 NTU).

  • Total hardness: The total concentration of multivalent cations, mainly Ca2+\text{Ca}^{2+} and Mg2+\text{Mg}^{2+}, expressed as mg/L as CaCO₃. Significance: hard water causes scale in pipes/boilers and excess soap consumption; very soft water can be corrosive. Acceptable up to ~500 mg/L.

  • Most Probable Number (MPN): A statistical estimate of the number of coliform organisms per 100 mL of water obtained from the multiple-tube fermentation test. Significance: it is the principal bacteriological indicator of faecal contamination; for drinking water the MPN of E. coli should be 0 per 100 mL.

sourceswater-quality
9short6 marks

(a) With neat sketches, describe any two systems of water distribution (layout types) and state one advantage of each. (b) A town has an average daily demand of 3,600 m³. Estimate the required balancing (service) reservoir capacity taking storage as 40% of the maximum-day demand, with a maximum-day factor of 1.5.

(a) Distribution layouts (any two)

  1. Dead-end / Tree system — a main with branching sub-mains and laterals.
   Main ----+----+----+----
            |    |    |
          lateral lateral

Advantage: simple to design and lay; less pipe length, so lower initial cost. (Disadvantage: stagnant dead ends, large area cut off during repair.)

  1. Grid-iron / Ring system — interconnected loops with no dead ends.
   +----+----+
   |    |    |
   +----+----+
   |    |    |
   +----+----+

Advantage: water reaches any point from more than one direction, so head loss is low and supply continues during repairs; better for fire-fighting.

(Other valid systems: radial, ring system.)

(b) Service reservoir capacity

Average daily demand =3,600m3= 3{,}600\,\text{m}^3.

Maximum-day demand:

Qmax=1.5×3600=5,400m3Q_{max} = 1.5 \times 3600 = 5{,}400\,\text{m}^3

Balancing storage at 40% of max-day demand:

Capacity=0.40×5400=2,160m3\text{Capacity} = 0.40 \times 5400 = \mathbf{2{,}160\,\text{m}^3}

(To this, fire reserve and breakdown/emergency storage are usually added in practice; here the balancing component alone is 2,160 m³.)

distribution-systemstorage-reservoir
10short6 marks

A gravity-flow rural water supply scheme serves 6 villages with a present total population of 2,400. Using a design period of 15 years, an arithmetic growth rate of 2.0% per year (of the present population), a demand of 45 lpcd, and a peak factor of 3.0 for the distribution system: (a) find the design population, (b) the average daily demand (m³/day), and (c) the peak flow (litres/second) the supply pipe network must carry.

(a) Design population (arithmetic increase)

Annual increase =2.0%= 2.0\% of present population =0.02×2400=48= 0.02 \times 2400 = 48 persons/year.

P15=P0+(rate×n)=2400+(48×15)=2400+720=3,120 personsP_{15} = P_0 + (\text{rate} \times n) = 2400 + (48 \times 15) = 2400 + 720 = \mathbf{3{,}120 \text{ persons}}

(b) Average daily demand

Demand =45lpcd= 45\,\text{lpcd}:

Qavg=3120×451000=140.4m3/dayQ_{avg} = \frac{3120 \times 45}{1000} = \mathbf{140.4\,\text{m}^3/\text{day}}

(c) Peak flow

Average flow in L/s:

Qavg=140.4×100086400=1.625L/sQ_{avg} = \frac{140.4 \times 1000}{86400} = 1.625\,\text{L/s}

Peak flow (peak factor 3.0):

Qpeak=3.0×1.625=4.88L/sQ_{peak} = 3.0 \times 1.625 = \mathbf{4.88\,\text{L/s}}

The distribution network and tap-stand sizing must be based on this peak demand of ~4.9 L/s, while the source intake and transmission main are sized on the average (or maximum-day) demand of 140.4 m³/day.

rural-water-supplydemand
11short6 marks

(a) What is aeration in water treatment? List three objectives. (b) A raw groundwater contains 6 mg/L of dissolved iron (Fe²⁺). Stoichiometrically, 0.14 mg of O₂ is required per mg of Fe²⁺ for oxidation. For a flow of 2 MLD, compute the theoretical daily oxygen demand for iron removal (in kg/day).

(a) Aeration

Aeration is the process of bringing water into intimate contact with air to exchange gases and add dissolved oxygen. Objectives (any three):

  1. To add dissolved oxygen and oxidise dissolved iron and manganese so they can be filtered out.
  2. To remove dissolved gases such as CO₂, H₂S, and other taste/odour-causing volatile substances.
  3. To drive off volatile organic compounds and improve the palatability (freshness) of the water.

(b) Theoretical oxygen demand for iron removal

Flow Q=2MLD=2×106L/dayQ = 2\,\text{MLD} = 2\times10^6\,\text{L/day}; iron =6mg/L= 6\,\text{mg/L}.

Daily iron load:

Fe=2×106×6106kg/day=12kg/day\text{Fe} = \frac{2\times10^6 \times 6}{10^6}\,\text{kg/day} = 12\,\text{kg/day}

Oxygen demand at 0.14 mg O₂ per mg Fe²⁺:

O2=0.14×12=1.68kg/day\text{O}_2 = 0.14 \times 12 = \mathbf{1.68\,\text{kg/day}}

Thus about 1.68 kg of oxygen per day must be supplied by aeration to oxidise the dissolved iron (in practice a surplus is provided to ensure complete oxidation and to satisfy other oxygen demands).

treatmentaeration

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Water Supply Engineering (IOE, CE 651) question paper 2077?
The full BE Civil Engineering (IOE, TU) Water Supply Engineering (IOE, CE 651) 2077 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Water Supply Engineering (IOE, CE 651) 2077 paper come with solutions?
Yes. Every question on this Water Supply Engineering (IOE, CE 651) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Water Supply Engineering (IOE, CE 651) 2077 paper?
The BE Civil Engineering (IOE, TU) Water Supply Engineering (IOE, CE 651) 2077 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Water Supply Engineering (IOE, CE 651) past paper free?
Yes — reading and attempting this Water Supply Engineering (IOE, CE 651) past paper on Kekkei is completely free.