Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long10 marks

The census population of a town for the last four decades is given below:

Year (AD)1980199020002010
Population28,00034,50043,80056,200

(a) Estimate the population of the town for the design year 2040 AD using the geometric increase method and the incremental increase method. (b) Taking the geometric-method population as the design population, and adopting an average per-capita demand of 135 lpcd, compute the design average daily demand and the maximum daily demand (use a maximum-day factor of 1.8). Comment briefly on which forecasting method is more appropriate for a fast-growing town.

(a) Population forecasting

Decadal data and increments

YearPopulationIncreaseIncrease ratio
198028,000
199034,5006,50034,500/28,000 = 1.2321
200043,8009,30043,800/34,500 = 1.2696
201056,20012,40056,200/43,800 = 1.2831

Number of future decades from 2010 to 2040 = (20402010)/10=3(2040-2010)/10 = 3 decades.

Geometric increase method

Geometric mean of the growth ratios:

r=1.2321×1.2696×1.28313r = \sqrt[3]{1.2321 \times 1.2696 \times 1.2831}

Product =1.2321×1.2696×1.2831=2.00723= 1.2321 \times 1.2696 \times 1.2831 = 2.00723.

r=(2.00723)1/3=1.2615r = (2.00723)^{1/3} = 1.2615

So the average decadal growth rate 26.15%\approx 26.15\%.

Projected population:

P2040=P2010r3=56,200×(1.2615)3P_{2040} = P_{2010}\, r^{3} = 56{,}200 \times (1.2615)^{3} (1.2615)3=2.0072(1.2615)^{3} = 2.0072 P2040=56,200×2.0072=112,805112,800P_{2040} = 56{,}200 \times 2.0072 = 112{,}805 \approx \mathbf{112{,}800}

Incremental increase method

DecadeIncreaseIncremental increase
1980–19906,500
1990–20009,300+2,800
2000–201012,400+3,100

Average increase xˉ=(6,500+9,300+12,400)/3=28,200/3=9,400\bar{x} = (6{,}500 + 9{,}300 + 12{,}400)/3 = 28{,}200/3 = 9{,}400.

Average incremental increase yˉ=(2,800+3,100)/2=5,900/2=2,950\bar{y} = (2{,}800 + 3{,}100)/2 = 5{,}900/2 = 2{,}950.

For nn decades ahead:

P=P2010+nxˉ+n(n+1)2yˉP = P_{2010} + n\bar{x} + \frac{n(n+1)}{2}\bar{y}

With n=3n = 3:

P2040=56,200+3(9,400)+3×42(2,950)P_{2040} = 56{,}200 + 3(9{,}400) + \frac{3 \times 4}{2}(2{,}950) =56,200+28,200+6×2,950= 56{,}200 + 28{,}200 + 6 \times 2{,}950 =56,200+28,200+17,700=102,100= 56{,}200 + 28{,}200 + 17{,}700 = \mathbf{102{,}100}

(b) Demand computation

Design population (geometric) =112,800= 112{,}800.

Average daily demand:

Qavg=112,800×135 lpcd=15,228,000 L/day=15.23 MLDQ_{avg} = 112{,}800 \times 135\ \text{lpcd} = 15{,}228{,}000\ \text{L/day} = \mathbf{15.23\ MLD}

Maximum daily demand (factor 1.8):

Qmaxday=1.8×15.23=27.41 MLDQ_{max\,day} = 1.8 \times 15.23 = \mathbf{27.41\ MLD}

Comment

For a fast-growing town with increasing decadal growth ratios, the geometric increase method is generally more appropriate because growth is compounding (proportional to the existing base). The arithmetic/incremental methods tend to under-predict for rapidly expanding settlements, as confirmed here (102,100 vs 112,800).

population-forecastingwater-demand
2long10 marks

A rectangular continuous-flow sedimentation tank is to be designed to treat 18 MLD of water. The settling velocity of the smallest particle to be removed is 0.30 mm/s.

(a) Determine the required surface area of the tank and the theoretical detention time if the effective water depth is 3.5 m. (b) If the tank length-to-width ratio is 4:1, find the suitable length and width, and check the horizontal (displacement) velocity, commenting whether scour is likely (limiting value ~ 9 mm/s). (c) Explain how a flow-through (short-circuiting) factor affects the real detention time.

(a) Surface area and detention time

Flow rate:

Q=18 MLD=18×106 L/day=18,000 m3/dayQ = 18\ \text{MLD} = 18 \times 10^{6}\ \text{L/day} = 18{,}000\ \text{m}^3/\text{day} Q=18,00086,400=0.2083 m3/sQ = \frac{18{,}000}{86{,}400} = 0.2083\ \text{m}^3/\text{s}

Surface overflow rate must equal the settling velocity:

vs=0.30 mm/s=0.30×103 m/s=3.0×104 m/sv_s = 0.30\ \text{mm/s} = 0.30 \times 10^{-3}\ \text{m/s} = 3.0 \times 10^{-4}\ \text{m/s}

Required surface area:

A=Qvs=0.20833.0×104=694.4 m2694 m2A = \frac{Q}{v_s} = \frac{0.2083}{3.0 \times 10^{-4}} = 694.4\ \text{m}^2 \approx \mathbf{694\ m^2}

Tank volume:

V=A×H=694.4×3.5=2,430.6 m3V = A \times H = 694.4 \times 3.5 = 2{,}430.6\ \text{m}^3

Theoretical detention time:

t=VQ=2,430.60.2083=11,669 s=3.24 hourst = \frac{V}{Q} = \frac{2{,}430.6}{0.2083} = 11{,}669\ \text{s} = \mathbf{3.24\ hours}

(b) Dimensions and horizontal velocity

With L=4BL = 4B and A=L×B=4B2A = L \times B = 4B^2:

4B2=694.4B2=173.6B=13.18 m13.2 m4B^2 = 694.4 \Rightarrow B^2 = 173.6 \Rightarrow B = 13.18\ \text{m} \approx \mathbf{13.2\ m} L=4×13.18=52.7 m52.7 mL = 4 \times 13.18 = 52.7\ \text{m} \approx \mathbf{52.7\ m}

Cross-sectional flow area =B×H=13.18×3.5=46.13 m2= B \times H = 13.18 \times 3.5 = 46.13\ \text{m}^2.

Horizontal velocity:

vH=QB×H=0.208346.13=4.515×103 m/s=4.52 mm/sv_H = \frac{Q}{B \times H} = \frac{0.2083}{46.13} = 4.515 \times 10^{-3}\ \text{m/s} = \mathbf{4.52\ mm/s}

Since 4.52 mm/s<9 mm/s4.52\ \text{mm/s} < 9\ \text{mm/s}, the horizontal velocity is below the scouring limit, so re-suspension of settled solids is unlikely — the design is acceptable.

(c) Effect of short-circuiting factor

Real tanks never behave as ideal plug flow. Density currents, wind, thermal stratification and inlet/outlet turbulence cause some water to traverse the tank faster than the mean. The flow-through (short-circuiting) factor η=tactual/ttheoretical\eta = t_{actual}/t_{theoretical} is typically 0.3–0.7. A lower η\eta means a portion of the flow has a shorter effective detention time than designed, reducing removal efficiency. Designers therefore provide baffles, good inlet diffusion, and adopt a higher detention time (or lower overflow rate) than the theoretical minimum to compensate.

sedimentationplain-settling
3long8 marks

A waterworks must filter 24 MLD of water using rapid gravity sand filters operating at a filtration rate of 5000 L/m²/hr.

(a) Determine the total filter area required and the number of filter units if each unit is limited to about 30 m², allowing one extra unit to remain in service during backwashing. (b) If each filter is backwashed for 10 minutes per day at a wash-water rate of 0.6 m³/m²/min, estimate the percentage of filtered water used for backwashing. (c) List the operations in one complete filtration cycle of a rapid sand filter.

(a) Filter area and number of units

Flow:

Q=24 MLD=24,000 m3/dayQ = 24\ \text{MLD} = 24{,}000\ \text{m}^3/\text{day}

Filtration rate:

5000 L/m2/hr=5 m3/m2/hr×24=120 m3/m2/day5000\ \text{L/m}^2/\text{hr} = 5\ \text{m}^3/\text{m}^2/\text{hr} \times 24 = 120\ \text{m}^3/\text{m}^2/\text{day}

Total area:

A=24,000120=200 m2A = \frac{24{,}000}{120} = 200\ \text{m}^2

Number of working units at 30 m² each:

n=20030=6.677 units (working)n = \frac{200}{30} = 6.67 \Rightarrow 7\ \text{units (working)}

Adopt area per unit =200/7=28.6 m2= 200/7 = 28.6\ \text{m}^2 (\approx within the 30 m² limit). Providing one stand-by/extra unit for backwashing:

Total=7+1=8 filter units\text{Total} = 7 + 1 = \mathbf{8\ filter\ units}

(b) Wash-water requirement

Area per unit 28.6 m2\approx 28.6\ \text{m}^2.

Wash water per unit per backwash:

=28.6 m2×0.6 m3/m2/min×10 min=171.6 m3= 28.6\ \text{m}^2 \times 0.6\ \text{m}^3/\text{m}^2/\text{min} \times 10\ \text{min} = 171.6\ \text{m}^3

With 7 working units backwashed once per day:

Total wash water=7×171.6=1,201.2 m3/day\text{Total wash water} = 7 \times 171.6 = 1{,}201.2\ \text{m}^3/\text{day}

Percentage of filtered water used:

1,201.224,000×100=5.0%\frac{1{,}201.2}{24{,}000} \times 100 = \mathbf{5.0\%}

This is within the typical acceptable range of 2–6 % for rapid sand filters.

(c) Operations in one filtration cycle

  1. Filtration (service run) — raw/coagulated-settled water passes downward through the sand bed; runs until head loss reaches the limit (~2.5 m) or turbidity breaks through.
  2. Backwashing — filtration stopped; water (sometimes with air scour) forced upward to fluidize and expand the bed, dislodging trapped floc.
  3. Washing/rinsing — dirty wash water carried to the wash-water troughs and drained.
  4. Filtering to waste (ripening) — initial filtrate after backwash run to waste until effluent turbidity is acceptable.
  5. Filter returned to service; cycle repeats.
rapid-sand-filterfiltration
4long8 marks

A centrifugal pump lifts 40 L/s of water from a sump to an overhead service reservoir. The static lift (difference between sump water level and delivery water level) is 32 m. The total length of pipe (suction + delivery) is 480 m of diameter 250 mm with a Darcy friction factor f=0.020f = 0.020. Minor losses may be taken as 15 % of the friction loss. The combined efficiency of the pump and motor is 70 %.

(a) Compute the total dynamic head the pump must work against. (b) Compute the power input required to drive the pump (in kW). (c) If electricity costs NRs 11 per kWh and the pump runs 16 hours/day, estimate the monthly (30-day) energy cost.

(a) Total dynamic head

Flow Q=40 L/s=0.040 m3/sQ = 40\ \text{L/s} = 0.040\ \text{m}^3/\text{s}.

Pipe diameter D=0.25 mD = 0.25\ \text{m}; area:

A=π4(0.25)2=0.04909 m2A = \frac{\pi}{4}(0.25)^2 = 0.04909\ \text{m}^2

Velocity:

V=QA=0.0400.04909=0.8148 m/sV = \frac{Q}{A} = \frac{0.040}{0.04909} = 0.8148\ \text{m/s}

Friction (Darcy–Weisbach) head loss:

hf=fLV22gD=0.020×480×(0.8148)22×9.81×0.25h_f = \frac{fLV^2}{2gD} = \frac{0.020 \times 480 \times (0.8148)^2}{2 \times 9.81 \times 0.25}

Numerator =0.020×480×0.6639=6.374= 0.020 \times 480 \times 0.6639 = 6.374. Denominator =2×9.81×0.25=4.905= 2 \times 9.81 \times 0.25 = 4.905.

hf=6.3744.905=1.299 mh_f = \frac{6.374}{4.905} = 1.299\ \text{m}

Minor losses =0.15×1.299=0.195 m= 0.15 \times 1.299 = 0.195\ \text{m}.

Total dynamic head:

H=Hstatic+hf+hminor=32+1.299+0.195=33.49 mH = H_{static} + h_f + h_{minor} = 32 + 1.299 + 0.195 = \mathbf{33.49\ m}

(b) Power input

Water (useful) power:

Pwater=ρgQH=1000×9.81×0.040×33.49=13,141 W=13.14 kWP_{water} = \rho g Q H = 1000 \times 9.81 \times 0.040 \times 33.49 = 13{,}141\ \text{W} = 13.14\ \text{kW}

Power input at 70 % efficiency:

Pinput=Pwaterη=13.140.70=18.78 kWP_{input} = \frac{P_{water}}{\eta} = \frac{13.14}{0.70} = \mathbf{18.78\ kW}

(c) Monthly energy cost

Daily energy:

E=18.78 kW×16 hr=300.5 kWh/dayE = 18.78\ \text{kW} \times 16\ \text{hr} = 300.5\ \text{kWh/day}

Monthly (30 days):

Emonth=300.5×30=9,014 kWhE_{month} = 300.5 \times 30 = 9{,}014\ \text{kWh}

Cost:

=9,014×11=NRs 99,154 per month= 9{,}014 \times 11 = \textbf{NRs 99{,}154 per month}
pumpingpump-power
5long8 marks

(a) Compare the dead-end (tree) and grid-iron (looped) systems of pipe distribution layout, giving two advantages and one disadvantage of each. (b) Explain the principle of the Hardy-Cross method of analysing a looped distribution network. State the two governing conditions a balanced network must satisfy and write the correction formula ΔQ\Delta Q for one loop, defining each term. (c) For a single loop, the assumed flows give kQn=+6.0\sum k Q^n = +6.0 and nkQn1=40\sum n k Q^{n-1} = 40 (consistent units, n=1.85n = 1.85). Compute the first flow correction ΔQ\Delta Q.

(a) Dead-end vs grid-iron systems

Dead-end (tree) system

  • Advantages: simple design and easy to compute flows; cheaper (less pipe), suited to irregularly developed/old towns.
  • Disadvantage: water at the far ends becomes stagnant (quality deteriorates); during repair a large area loses supply; limited fire-flow reliability.

Grid-iron (looped) system

  • Advantages: water can reach any point from more than one direction, so no stagnation and good for firefighting; a single pipe break isolates only a small zone.
  • Disadvantage: more pipe length and valves → higher cost; flow analysis is more complex (requires iterative methods).

(b) Hardy-Cross method

Principle: Successive approximation. Flows are first assumed in every pipe so that continuity at each node is satisfied (inflow = outflow). The head loss around each loop is then checked; a correction ΔQ\Delta Q is applied to all pipes of the loop and iterated until the loops balance.

Two governing conditions of a balanced network:

  1. Continuity (junction law): at every node, Qin=Qout\sum Q_{in} = \sum Q_{out}.
  2. Energy (loop law): around every closed loop, the algebraic sum of head losses is zero, hL=0\sum h_L = 0.

With head loss expressed as hL=kQnh_L = kQ^n, the loop correction is:

ΔQ=kQnnkQn1\Delta Q = -\frac{\sum kQ^{n}}{n\sum k|Q|^{\,n-1}}

where kk = pipe resistance coefficient, QQ = assumed discharge (signed, clockwise positive), nn = exponent (1.85 for Hazen–Williams, 2 for Darcy), and the denominator uses absolute values.

(c) First correction

ΔQ=kQnnkQn1=+6.040\Delta Q = -\frac{\sum kQ^{n}}{n\sum k Q^{\,n-1}} = -\frac{+6.0}{40}

(Note: the denominator nkQn1=40n\sum kQ^{n-1} = 40 is already supplied including the factor nn.)

ΔQ=0.15 (consistent units)\Delta Q = -0.15\ \text{(consistent units)}

So a correction of ΔQ=0.15\Delta Q = -0.15 is applied to every pipe in the loop (subtracted from clockwise flows, added to anticlockwise), and the procedure is repeated until kQn0\sum kQ^n \approx 0.

distribution-systemhardy-cross
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short6 marks

A treatment plant treating 20 MLD uses alum (filter alum, Al2(SO4)318H2OAl_2(SO_4)_3\cdot 18H_2O) at an optimum dose of 28 mg/L. (a) Compute the daily mass of alum required (kg/day). (b) Each mg/L of alum consumes alkalinity; if alum reacts to consume natural alkalinity of about 0.45 mg/L as CaCO₃ per mg/L of alum, check whether a raw-water alkalinity of 12 mg/L as CaCO₃ is sufficient, and if not, find the lime (as CaCO₃ equivalent) dose to be added.

(a) Daily alum requirement

Mass=dose×Q=28 mg/L×20×106 L/day\text{Mass} = \text{dose} \times Q = 28\ \text{mg/L} \times 20 \times 10^{6}\ \text{L/day} =28×20×106 mg/day=560×106 mg/day= 28 \times 20 \times 10^{6}\ \text{mg/day} = 560 \times 10^{6}\ \text{mg/day} =560 kg/day(since 106 mg=1 kg)= 560\ \text{kg/day} \quad (\text{since } 10^{6}\ \text{mg} = 1\ \text{kg}) Alum=560 kg/day\boxed{\text{Alum} = \mathbf{560\ kg/day}}

(b) Alkalinity check

Alkalinity consumed by alum:

=0.45 (mg/L as CaCO3)×28 mg/L alum=12.6 mg/L as CaCO3= 0.45\ \text{(mg/L as CaCO}_3) \times 28\ \text{mg/L alum} = 12.6\ \text{mg/L as CaCO}_3

Available raw-water alkalinity =12 mg/L as CaCO3= 12\ \text{mg/L as CaCO}_3.

Since required (12.6) > available (12), the natural alkalinity is insufficient by:

12.612=0.6 mg/L as CaCO312.6 - 12 = 0.6\ \text{mg/L as CaCO}_3

Therefore additional alkalinity must be supplied (as lime). Expressed as CaCO₃ equivalent, the deficit (and hence the make-up alkalinity dose) is:

0.6 mg/L as CaCO3\mathbf{0.6\ mg/L\ as\ CaCO_3}

Daily make-up mass:

0.6 mg/L×20×106 L/day=12×106 mg/day=12 kg/day (as CaCO3)0.6\ \text{mg/L} \times 20 \times 10^{6}\ \text{L/day} = 12 \times 10^{6}\ \text{mg/day} = \mathbf{12\ kg/day\ (as\ CaCO_3)}

So a small lime dose equivalent to 0.6 mg/L CaCO₃ (about 12 kg/day) is needed to ensure complete coagulation.

coagulationalum-dosing
7short6 marks

(a) Define chlorine demand, residual chlorine and break-point chlorination with the aid of a labelled break-point curve (described). (b) A water sample exerts a chlorine demand of 1.6 mg/L. To maintain a free residual of 0.5 mg/L, what chlorine dose must be applied? If the plant treats 15 MLD, compute the daily chlorine consumption (kg/day).

(a) Definitions

  • Chlorine demand: the amount of chlorine consumed in oxidising organic matter, ammonia, iron, manganese, etc. It equals applied dose minus residual: demand=doseresidual\text{demand} = \text{dose} - \text{residual}.
  • Residual chlorine: the chlorine remaining in water after the demand has been met; it provides continuing disinfection in the distribution system. It may be combined (chloramines) or free (HOCl, OCl⁻).
  • Break-point chlorination: dosing chlorine until all demand (especially ammonia) is satisfied and chloramines are destroyed, beyond which any further chlorine appears as free residual.

Break-point curve (described):

Residual
chlorine |        free residual zone
   ^     |               /
   |     |   combined   /
   |     |   residual  /
   |     |    /\      /
   |     |   /  \    /  <- break point (minimum)
   |     |  /    \  /
   |     | /      \/
   +-----+----------------------> Applied chlorine dose

Rising combined residual, then a dip as chloramines are oxidised (the break point), then a linear free-residual rise.

(b) Dose and daily consumption

Required applied dose:

Dose=demand+desired residual=1.6+0.5=2.1 mg/L\text{Dose} = \text{demand} + \text{desired residual} = 1.6 + 0.5 = \mathbf{2.1\ mg/L}

Daily chlorine consumption for Q=15 MLD=15×106 L/dayQ = 15\ \text{MLD} = 15 \times 10^{6}\ \text{L/day}:

=2.1 mg/L×15×106 L/day=31.5×106 mg/day= 2.1\ \text{mg/L} \times 15 \times 10^{6}\ \text{L/day} = 31.5 \times 10^{6}\ \text{mg/day} =31.5 kg/day= \mathbf{31.5\ kg/day}
disinfectionchlorination
8short6 marks

(a) Classify the principal sources of water for a public supply and state one advantage and one limitation of surface versus groundwater sources. (b) Define the following water-quality parameters and give the Nepal/WHO guideline value for drinking water: turbidity, total hardness, and pH. (c) Why is turbidity removed before disinfection?

(a) Sources of water

Classification:

  • Surface sources: rivers, streams, lakes, ponds, impounding reservoirs.
  • Sub-surface / groundwater sources: springs, infiltration galleries, wells (open/dug, tube/bore), aquifers.
  • Rainwater (precipitation): roof catchment, rainwater harvesting.

Surface vs groundwater

AdvantageLimitation
SurfaceLarge quantity available, easy to locate/abstractHigh turbidity & bacterial load → needs full treatment; seasonal variation
GroundwaterGenerally clear, low turbidity, fairly constant quality/temperatureLimited yield; may have high hardness/iron/arsenic; pumping cost

(b) Quality parameters and guideline values (NDWQS/WHO)

  • Turbidity: cloudiness caused by suspended/colloidal matter, measured in NTU. Guideline: 5 NTU (desirable < 1 NTU for effective disinfection).
  • Total hardness: sum of multivalent cations (mainly Ca²⁺, Mg²⁺), expressed as mg/L CaCO₃. Guideline: 500 mg/L as CaCO₃ (Nepal NDWQS).
  • pH: negative log of H⁺ activity, indicating acidity/alkalinity. Guideline: 6.5–8.5.

(c) Why remove turbidity before disinfection

Suspended/colloidal particles shield micro-organisms from contact with the disinfectant and exert chlorine demand, consuming the disinfectant before it can act on pathogens. Removing turbidity (by coagulation, sedimentation and filtration) ensures the chlorine reaches and inactivates the pathogens efficiently, giving a reliable residual.

water-sourceswater-quality
9short6 marks

A town has an average daily demand of 4.5 MLD. Determine the balancing (equalizing) storage capacity of the service reservoir using the mass-curve/tabular approach, given the following demand pattern relative to the constant 24-hour pumping (supply) rate:

PeriodHoursDemand as % of avg hourly
00:00–06:00640%
06:00–12:006150%
12:00–18:006130%
18:00–24:00680%

Water is pumped uniformly over 24 hours. Also add fire reserve of 0.4 ML and state the total reservoir capacity.

Step 1 — Average hourly demand and supply

Daily demand =4.5 ML=4,500 m3= 4.5\ \text{ML} = 4{,}500\ \text{m}^3.

Average hourly demand:

=4,50024=187.5 m3/hr= \frac{4{,}500}{24} = 187.5\ \text{m}^3/\text{hr}

Supply (uniform pumping) =187.5 m3/hr= 187.5\ \text{m}^3/\text{hr} (i.e. 100 % each hour).

Step 2 — Hourly demand by period

PeriodDemand %/hrDemand m³/hrSupply m³/hrExcess/Deficit per hr (Supply − Demand)Over 6 hr
00–0640%75.0187.5+112.5+675.0
06–12150%281.25187.5−93.75−562.5
12–18130%243.75187.5−56.25−337.5
18–2480%150.0187.5+37.5+225.0

Check total demand: (75+281.25+243.75+150)×6=750×6=4,500 m3(75+281.25+243.75+150)\times 6 = 750 \times 6 = 4{,}500\ \text{m}^3 ✓ (= daily demand).

Step 3 — Cumulative storage (running balance)

Starting from 00:00, track cumulative (supply − demand):

End of periodPeriod balanceCumulative
06:00+675.0+675.0 (max surplus)
12:00−562.5+112.5
18:00−337.5−225.0 (max deficit)
24:00+225.00.0

Step 4 — Balancing storage

Balancing storage == maximum surplus ++ maximum deficit (in magnitude):

=675.0+225.0=900 m3=0.90 ML= 675.0 + 225.0 = 900\ \text{m}^3 = \mathbf{0.90\ ML}

(Equivalently 20 % of the 4.5 MLD daily demand.)

Step 5 — Total reservoir capacity

Total=balancing+fire reserve=0.90+0.40=1.30 ML\text{Total} = \text{balancing} + \text{fire reserve} = 0.90 + 0.40 = \mathbf{1.30\ ML}

(A breakdown/emergency reserve could be added in practice; based on the data given the required capacity is 1.30 ML ≈ 1300 m³.)

service-reservoirstorage-capacity
10short6 marks

(a) Describe the typical components of a gravity-flow rural water supply scheme in a Nepali hill setting, from source to tap. (b) A community of 650 people is to be served at 45 lpcd. The spring yields 0.45 L/s in the dry season. Check whether the source is adequate for the present and for a 20-year design population at a geometric growth of 2.2 % per annum. (c) State two reasons community participation is emphasised in rural schemes.

(a) Components of a gravity-flow scheme

From source to tap:

  1. Intake / spring source protection (spring box or stream intake with screen).
  2. Collection chamber / sedimentation (silt) tank to remove grit.
  3. Transmission/conveyance pipe (HDPE/GI) running by gravity.
  4. Break-pressure tanks (BPT) at intervals to limit static head on the pipe.
  5. Reservoir / Reservoir-cum-Distribution tank (RVT) for balancing storage.
  6. Distribution pipe network.
  7. Tapstands (public/private) with drainage, and valve chambers.

(b) Source adequacy check

Present demand (650 people):

Qdemand=650×45 lpcd=29,250 L/dayQ_{demand} = 650 \times 45\ \text{lpcd} = 29{,}250\ \text{L/day}

Spring yield per day:

Qsource=0.45 L/s×86,400 s/day=38,880 L/dayQ_{source} = 0.45\ \text{L/s} \times 86{,}400\ \text{s/day} = 38{,}880\ \text{L/day}

Since 38,880>29,25038{,}880 > 29{,}250, the source is adequate at present (surplus of 9,630 L/day).

20-year design population (geometric growth, r=0.022r = 0.022):

P20=650×(1.022)20P_{20} = 650 \times (1.022)^{20} (1.022)20=e20ln1.022=e20×0.021761=e0.43522=1.5454(1.022)^{20} = e^{20\ln 1.022} = e^{20 \times 0.021761} = e^{0.43522} = 1.5454 P20=650×1.5454=1,0041,005 personsP_{20} = 650 \times 1.5454 = 1{,}004 \approx 1{,}005\ \text{persons}

Future demand:

=1,005×45=45,225 L/day= 1{,}005 \times 45 = 45{,}225\ \text{L/day}

Compare with dry-season yield 38,880 L/day:

45,225>38,88045{,}225 > 38{,}880

So the spring is NOT adequate for the 20-year design population — it falls short by about 6,345 L/day. An additional/supplementary source, increased storage to ride out peaks, or a reduced service level would be required.

(c) Reasons for community participation

  1. Ownership & sustainability — community contribution (labour, local materials, cash) builds a sense of ownership, improving operation, maintenance and tariff collection after handover.
  2. Appropriate design & equity — local knowledge ensures the source, tap locations and service level match real needs, and a water-users committee manages fair distribution and upkeep.
rural-water-supplyspring-source
11short6 marks

Water flows through a 300 mm diameter cast-iron pipe (Hazen–Williams C = 100) carrying 60 L/s. (a) Using the Hazen–Williams formula, compute the velocity and the head loss per kilometre of pipe. (b) State the head loss over a 2.4 km length and the residual pressure head at the downstream end if the upstream piezometric head is 48 m and the pipe is horizontal.

Use V=0.849CR0.63S0.54V = 0.849\,C\,R^{0.63}\,S^{0.54} (SI units, RR = hydraulic radius, SS = slope of energy line).

(a) Velocity and head loss per km

Diameter D=0.30 mD = 0.30\ \text{m}; area:

A=π4(0.30)2=0.070686 m2A = \frac{\pi}{4}(0.30)^2 = 0.070686\ \text{m}^2

Velocity from continuity:

V=QA=0.0600.070686=0.8488 m/s0.85 m/sV = \frac{Q}{A} = \frac{0.060}{0.070686} = 0.8488\ \text{m/s} \approx \mathbf{0.85\ m/s}

Hydraulic radius (full pipe):

R=D4=0.304=0.075 mR = \frac{D}{4} = \frac{0.30}{4} = 0.075\ \text{m}

Rearrange Hazen–Williams for SS:

V=0.849CR0.63S0.54S=(V0.849CR0.63)1/0.54V = 0.849\,C\,R^{0.63}\,S^{0.54} \Rightarrow S = \left(\frac{V}{0.849\,C\,R^{0.63}}\right)^{1/0.54}

Compute R0.63R^{0.63}: ln(0.075)=2.5903\ln(0.075) = -2.5903; ×0.63=1.6319\times 0.63 = -1.6319; R0.63=e1.6319=0.19556R^{0.63} = e^{-1.6319} = 0.19556.

Denominator =0.849×100×0.19556=16.603= 0.849 \times 100 \times 0.19556 = 16.603.

V0.849CR0.63=0.848816.603=0.051124\frac{V}{0.849 C R^{0.63}} = \frac{0.8488}{16.603} = 0.051124

Now S=(0.051124)1/0.54S = (0.051124)^{1/0.54}. Exponent 1/0.54=1.851851/0.54 = 1.85185.

ln(0.051124)=2.9737;×1.85185=5.5069\ln(0.051124) = -2.9737; \quad \times 1.85185 = -5.5069 S=e5.5069=0.004061S = e^{-5.5069} = 0.004061

Head loss per km:

hL=S×1000=0.004061×1000=4.06 m/kmh_L = S \times 1000 = 0.004061 \times 1000 = \mathbf{4.06\ m/km}

(b) Head loss over 2.4 km and residual head

hL,2.4=4.061×2.4=9.75 mh_{L,2.4} = 4.061 \times 2.4 = 9.75\ \text{m}

For a horizontal pipe, residual piezometric (pressure) head downstream:

Hdown=489.75=38.25 mH_{down} = 48 - 9.75 = \mathbf{38.25\ m}

So about 9.75 m is lost in friction over 2.4 km, leaving a residual head of roughly 38.3 m at the downstream end — comfortably adequate for distribution.

pipe-flowhazen-williams

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Water Supply Engineering (IOE, CE 651) question paper 2076?
The full BE Civil Engineering (IOE, TU) Water Supply Engineering (IOE, CE 651) 2076 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Water Supply Engineering (IOE, CE 651) 2076 paper come with solutions?
Yes. Every question on this Water Supply Engineering (IOE, CE 651) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Water Supply Engineering (IOE, CE 651) 2076 paper?
The BE Civil Engineering (IOE, TU) Water Supply Engineering (IOE, CE 651) 2076 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Water Supply Engineering (IOE, CE 651) past paper free?
Yes — reading and attempting this Water Supply Engineering (IOE, CE 651) past paper on Kekkei is completely free.