Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long12 marks

The longitudinal section of a proposed road embankment is given below. The road is to be formed to a uniform formation width of 10 m10\ \text{m} with side slopes of 2:12:1 (horizontal:vertical). The ground levels (G.L.) and the corresponding formation levels (F.L.) at chainages spaced 30 m30\ \text{m} apart are tabulated. Compute the volume of earthwork (filling) required using (a) the Trapezoidal (average-area) method and (b) the Prismoidal formula, and comment on the difference.

StationChainage (m)G.L. (m)F.L. (m)
00100.00100.00
13099.20100.60
26098.40101.20
39098.00101.80
412098.60102.40
515099.50103.00

Assume the cross-section at each station is a symmetrical trapezoid (level ground transversely).

Step 1 — Height of filling at each station

Height of fill h=F.L.G.L.h = \text{F.L.} - \text{G.L.}

StnF.L.G.L.hh (m)
0100.00100.000.00
1100.6099.201.40
2101.2098.402.80
3101.8098.003.80
4102.4098.603.80
5103.0099.503.50

Step 2 — Cross-sectional area at each station

For a symmetrical embankment of formation width b=10 mb=10\ \text{m}, side slope s:1s:1 with s=2s=2, on level transverse ground:

A=bh+sh2=10h+2h2A = bh + s\,h^2 = 10h + 2h^2
Stnhh10h10h2h22h^2AA (m²)
00.000.000.0000.000
11.4014.003.92017.920
22.8028.0015.68043.680
33.8038.0028.88066.880
43.8038.0028.88066.880
53.5035.0024.50059.500

Step 3 — Trapezoidal (average-area) method

With common distance d=30 md = 30\ \text{m} and n=6n=6 sections (5 intervals):

V=d[A0+A52+(A1+A2+A3+A4)]V = d\left[\frac{A_0 + A_5}{2} + (A_1 + A_2 + A_3 + A_4)\right] =30[0.000+59.5002+(17.920+43.680+66.880+66.880)]= 30\left[\frac{0.000 + 59.500}{2} + (17.920 + 43.680 + 66.880 + 66.880)\right] =30[29.750+195.360]=30×225.110=6753.30 m3= 30\left[29.750 + 195.360\right] = 30 \times 225.110 = 6753.30\ \text{m}^3

Trapezoidal volume = 6753.30 m³

Step 4 — Prismoidal formula

The prismoidal rule requires an odd number of sections (even number of intervals). We have 6 sections / 5 intervals. Apply the prismoidal rule to the first 4 intervals (stations 0–4, 5 sections) and treat the last interval (4–5) by the trapezoidal rule.

Prismoidal rule for stations 0–4 (even number of intervals = 4):

V1=d3[A0+A4+4(A1+A3)+2(A2)]V_1 = \frac{d}{3}\left[A_0 + A_4 + 4(A_1 + A_3) + 2(A_2)\right] =303[0.000+66.880+4(17.920+66.880)+2(43.680)]= \frac{30}{3}\left[0.000 + 66.880 + 4(17.920 + 66.880) + 2(43.680)\right] =10[66.880+4(84.800)+87.360]= 10\left[66.880 + 4(84.800) + 87.360\right] =10[66.880+339.200+87.360]=10×493.440=4934.40 m3= 10\left[66.880 + 339.200 + 87.360\right] = 10 \times 493.440 = 4934.40\ \text{m}^3

Last interval (4–5) by trapezoidal rule:

V2=dA4+A52=30×66.880+59.5002=30×63.190=1895.70 m3V_2 = d\cdot\frac{A_4 + A_5}{2} = 30 \times \frac{66.880 + 59.500}{2} = 30 \times 63.190 = 1895.70\ \text{m}^3 Vprismoidal=V1+V2=4934.40+1895.70=6830.10 m3V_{\text{prismoidal}} = V_1 + V_2 = 4934.40 + 1895.70 = 6830.10\ \text{m}^3

Prismoidal volume = 6830.10 m³

Step 5 — Comment

Difference =6830.106753.30=76.80 m3= 6830.10 - 6753.30 = 76.80\ \text{m}^3 (about 1.1%1.1\%). The prismoidal formula accounts for the curvature of the cross-section variation and is more accurate. The trapezoidal method under-estimates here because the area profile is concave (areas rise then level off). For tender/billing purposes the prismoidal result is preferred; the trapezoidal result may be corrected by the prismoidal correction where applicable.

earthwork-estimatemethods-of-measurementtrapezoidal-rule
2long12 marks

Prepare the rate analysis for 1 m³ of M20 (1:1.5:3) cast-in-situ reinforced cement concrete for a suspended floor slab, excluding the cost of reinforcement steel and its fabrication. Use the following data and present a complete rate-analysis table giving the rate per m³ inclusive of 15%15\% contractor's overhead and profit. Round the final rate to the nearest rupee.

Material requirement per m³ of wet concrete (1:1.5:3): dry mortar/aggregate factor =1.54=1.54.

Rates (NRs.): Cement = 850 per bag (50 kg, 0.0347 m30.0347\ \text{m}^3/bag); Sand = 2200/m³; Aggregate (20 mm) = 2600/m³; Mason = 1100/day; Unskilled labour = 850/day; Mixer + vibrator hire (machinery) = NRs. 600 per m³.

Labour constants per m³: Mason =0.20=0.20 day, Unskilled labour =2.5=2.5 days.

Take 1 bag of cement=0.0347 m31\ \text{bag of cement} = 0.0347\ \text{m}^3.

Step 1 — Quantity of dry materials for 1 m³ wet concrete

Total dry volume =1.54 m3= 1.54\ \text{m}^3. Proportion 1:1.5:31:1.5:3, sum of ratios =1+1.5+3=5.5=1+1.5+3 = 5.5.

  • Cement =15.5×1.54=0.2800 m3= \dfrac{1}{5.5}\times 1.54 = 0.2800\ \text{m}^3
  • Sand =1.55.5×1.54=0.4200 m3= \dfrac{1.5}{5.5}\times 1.54 = 0.4200\ \text{m}^3
  • Aggregate =35.5×1.54=0.8400 m3= \dfrac{3}{5.5}\times 1.54 = 0.8400\ \text{m}^3

Number of cement bags =0.28000.0347=8.0698.07 bags= \dfrac{0.2800}{0.0347} = 8.069 \approx 8.07\ \text{bags}.

Step 2 — Material cost

MaterialQuantityRate (NRs.)Amount (NRs.)
Cement8.07 bags850/bag6859.50
Sand0.42 m³2200/m³924.00
Aggregate0.84 m³2600/m³2184.00
Material sub-total9967.50

Cement: 8.07×850=6859.508.07 \times 850 = 6859.50

Step 3 — Labour cost

LabourConstantRate (NRs./day)Amount (NRs.)
Mason0.20 day1100220.00
Unskilled2.50 day8502125.00
Labour sub-total2345.00

Step 4 — Machinery

Mixer + vibrator hire =600.00= 600.00 per m³.

Step 5 — Build up the rate

ItemAmount (NRs.)
Materials9967.50
Labour2345.00
Machinery600.00
Prime cost12912.50
Add 15% O&P1936.88
Total per m³14849.38

O&P =0.15×12912.50=1936.88= 0.15 \times 12912.50 = 1936.88

Total =12912.50+1936.88=14849.38= 12912.50 + 1936.88 = 14849.38

Result

Rate of M20 RCC (excluding steel) = NRs. 14,849 per m³ (rounded).

Note on specifications

The rate assumes proper batching by volume with a measured water-cement ratio, machine mixing for at least 2 minutes, mechanical vibration for compaction, and curing for not less than 14 days as per standard specifications. Formwork/shuttering and reinforcement are paid for under separate items.

rate-analysisspecificationsrcc-work
3long10 marks

A single-room building has internal dimensions 5.00 m×4.00 m5.00\ \text{m} \times 4.00\ \text{m} (clear inside). All walls are 0.30 m0.30\ \text{m} thick and rise 3.00 m3.00\ \text{m} above the plinth. Using the centre-line method, estimate the quantity (volume) of superstructure brickwork, deducting one door 1.00 m×2.10 m1.00\ \text{m} \times 2.10\ \text{m} and two windows each 1.20 m×1.50 m1.20\ \text{m} \times 1.50\ \text{m}. Show the centre-line computation clearly.

Step 1 — Centre-line length

Internal dimensions =5.00×4.00 m= 5.00 \times 4.00\ \text{m}. Wall thickness t=0.30 mt = 0.30\ \text{m}.

Centre-to-centre dimensions (add one wall thickness to each internal dimension because the centre line lies half a wall thickness outside each face on both sides):

  • Length =5.00+0.30=5.30 m= 5.00 + 0.30 = 5.30\ \text{m}
  • Width =4.00+0.30=4.30 m= 4.00 + 0.30 = 4.30\ \text{m}

Total centre-line length for the rectangular plan:

Lcl=2(5.30+4.30)=2×9.60=19.20 mL_{cl} = 2(5.30 + 4.30) = 2 \times 9.60 = 19.20\ \text{m}

(For a continuous rectangular wall run the centre line closes on itself, so no corner correction is needed — the +t/−t corrections at the four corners cancel.)

Step 2 — Gross brickwork volume

Vgross=Lcl×t×H=19.20×0.30×3.00=17.280 m3V_{gross} = L_{cl} \times t \times H = 19.20 \times 0.30 \times 3.00 = 17.280\ \text{m}^3

Step 3 — Deductions for openings

Door: 1.00×2.10×0.30=0.630 m31.00 \times 2.10 \times 0.30 = 0.630\ \text{m}^3

Windows (2 No.): 2×(1.20×1.50×0.30)=2×0.540=1.080 m32 \times (1.20 \times 1.50 \times 0.30) = 2 \times 0.540 = 1.080\ \text{m}^3

Total deduction =0.630+1.080=1.710 m3= 0.630 + 1.080 = 1.710\ \text{m}^3

Step 4 — Net brickwork

Vnet=17.2801.710=15.570 m3V_{net} = 17.280 - 1.710 = 15.570\ \text{m}^3

Result

Net superstructure brickwork = 15.57 m³.

Verification by long-wall/short-wall method:

  • Long walls (out-to-out) =5.00+2(0.15)=5.30 m= 5.00 + 2(0.15) = 5.30\ \text{m} each → matches centre-to-centre because thickness folds in symmetrically; both methods give the same 19.20 m19.20\ \text{m} running length, confirming the result.
detailed-estimatecentre-line-methodbrickwork
4long8 marks

A building was constructed 20 years ago at a cost of NRs. 24,00,000 for the structure (excluding land). The present cost of land is NRs. 30,00,000. The total useful life of the building is taken as 60 years and the scrap value is 10%10\% of the construction cost.

(a) Determine the present depreciated value of the building using the straight-line method. (b) Determine the total present value of the property (building + land). (c) If the building is to be rebuilt at the end of its life, find the annual sinking-fund deposit required to accumulate the construction cost, taking interest at 8%8\% compounded annually over the full 60-year life.

(a) Depreciated value — straight-line method

Construction cost C=24,00,000C = 24{,}00{,}000. Scrap value S=10%×C=2,40,000S = 10\% \times C = 2{,}40{,}000.

Total depreciable amount =CS=24,00,0002,40,000=21,60,000= C - S = 24{,}00{,}000 - 2{,}40{,}000 = 21{,}60{,}000.

Annual depreciation D=CSn=21,60,00060=36,000D = \dfrac{C - S}{n} = \dfrac{21{,}60{,}000}{60} = 36{,}000 per year.

Depreciation in 20 years =20×36,000=7,20,000= 20 \times 36{,}000 = 7{,}20{,}000.

Depreciated (present) value of building:

Vb=C20D=24,00,0007,20,000=16,80,000V_b = C - 20D = 24{,}00{,}000 - 7{,}20{,}000 = 16{,}80{,}000

Present value of building = NRs. 16,80,000.

(b) Total present value of property

V=Vb+Vland=16,80,000+30,00,000=46,80,000V = V_b + V_{land} = 16{,}80{,}000 + 30{,}00{,}000 = 46{,}80{,}000

Total present value = NRs. 46,80,000.

(c) Annual sinking-fund deposit

Sinking-fund (annual deposit) to accumulate amount AA in nn years at rate ii:

I=Ai(1+i)n1I = A\cdot\frac{i}{(1+i)^n - 1}

Here A=24,00,000A = 24{,}00{,}000, i=0.08i = 0.08, n=60n = 60.

(1.08)60(1.08)^{60}: ln(1.08)=0.076961\ln(1.08)=0.076961; 60×0.076961=4.6176860\times0.076961 = 4.61768; e4.61768=101.257e^{4.61768} = 101.257.

So (1.08)601=101.2571=100.257(1.08)^{60} - 1 = 101.257 - 1 = 100.257.

I=24,00,000×0.08100.257=24,00,000×0.0007980=1915.1I = 24{,}00{,}000 \times \frac{0.08}{100.257} = 24{,}00{,}000 \times 0.0007980 = 1915.1

Annual sinking-fund deposit ≈ NRs. 1,915 per year.

(The very small deposit reflects the long 60-year accumulation period and compounding at 8%.)

valuationdepreciationsinking-fund
5long8 marks

(a) Explain the essential components that make up a complete set of tender (bid) documents for a civil engineering construction work in Nepal. (b) Differentiate between earnest money (bid security) and performance security (performance bond), stating typical percentages and their purposes. (c) Briefly describe three common methods of awarding a contract.

(a) Components of a complete set of tender documents

  1. Notice Inviting Tender (NIT) / Invitation for Bids — public advertisement giving brief scope, eligibility, cost of documents, bid security, submission deadline and opening date.
  2. Instructions to Bidders (ITB) — how to prepare, seal, submit and the evaluation criteria.
  3. Conditions of Contract — General Conditions (GCC) and Particular/Special Conditions (PCC/SCC) defining rights, obligations, payment terms, disputes, time, penalties.
  4. Bill of Quantities (BoQ) with measured items and the priced schedule of rates.
  5. Technical Specifications — material, workmanship and testing standards.
  6. Drawings — site/layout, structural and detailing drawings.
  7. Bid Forms and Schedules — bid letter, bid security form, schedule of unit rates, work programme, list of equipment and key personnel.
  8. Form of Contract Agreement and forms of performance security and advance payment guarantee.
  9. Appendices/Annexes — site information, soil report, addenda issued.

(b) Earnest money vs. performance security

AspectEarnest money / Bid securityPerformance security / Bond
When furnishedWith the bid, before openingBy the successful bidder before signing the contract
Typical amountAbout 2–3% of the estimated cost (lump-sum stated in NIT)About 5% of the contract amount
PurposeEnsures the bidder does not withdraw the bid and will sign the contract if awardedGuarantees due performance/completion of the work as per contract
If defaultedForfeited if bidder withdraws or fails to signForfeited / encashed if contractor fails to perform
ReturnRefunded to unsuccessful bidders; to winner on submitting performance securityReleased after successful completion / end of defect-liability period

(c) Three methods of awarding a contract

  1. Open competitive (lowest evaluated responsive bid): the contract is awarded to the bidder who submits the lowest substantially responsive and qualified bid; most common and transparent.
  2. Negotiated contract: the client negotiates terms and price directly with one or a few contractors, used for specialized, urgent or emergency works.
  3. Limited / selective tendering: invitations are issued only to a pre-qualified or shortlisted list of competent contractors, balancing competition with assured capability.
tender-contractcontract-documentsearnest-money
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short5 marks

Define an estimate. Explain any four types of estimates used in civil engineering practice, stating the purpose of each.

Definition

An estimate is the calculated, anticipated cost (and the quantities of work and materials) of a project, worked out in advance from the drawings and specifications before the work is actually executed. It guides budgeting, sanction of funds and tendering.

Four types of estimates

  1. Preliminary / approximate estimate: a rough cost found from approximate data (e.g., plinth-area rate, per-unit rate such as cost per bed for a hospital). Purpose: to decide the financial feasibility of a scheme and obtain administrative approval before detailing.
  2. Detailed estimate: the most accurate estimate, prepared item-by-item from complete drawings and specifications with full quantity take-off and rate analysis. Purpose: to obtain technical sanction, invite tenders and control the work.
  3. Revised estimate: a fresh detailed estimate prepared when the sanctioned cost is exceeded by more than a set limit (commonly 5%) or the scope changes. Purpose: to obtain revised financial sanction.
  4. Supplementary estimate: an additional detailed estimate prepared for extra works that become necessary during execution, in addition to the original. Purpose: to sanction and fund additional/unforeseen works.

(Other valid types: maintenance estimate, annual repair estimate, complete/abstract estimate.)

types-of-estimatesestimate-purpose
7short5 marks

A reinforced concrete beam is reinforced with 6 bars of 16 mm diameter main steel, each bar 6.50 m long, and stirrups of 8 mm diameter spaced at 150 mm150\ \text{mm} c/c over a 6.00 m6.00\ \text{m} length, each stirrup having a cut length of 1.20 m1.20\ \text{m}. Compute the total weight of steel in the beam. Use unit weight w=d2162 kg/mw = \dfrac{d^2}{162}\ \text{kg/m} (dd in mm).

Step 1 — Main bars (16 mm)

Total length =6×6.50=39.00 m= 6 \times 6.50 = 39.00\ \text{m}.

Unit weight =162162=256162=1.5802 kg/m= \dfrac{16^2}{162} = \dfrac{256}{162} = 1.5802\ \text{kg/m}.

Weight =39.00×1.5802=61.63 kg= 39.00 \times 1.5802 = 61.63\ \text{kg}.

Step 2 — Stirrups (8 mm)

Number of stirrups =6000150+1=40+1=41= \dfrac{6000}{150} + 1 = 40 + 1 = 41 Nos.

Total length =41×1.20=49.20 m= 41 \times 1.20 = 49.20\ \text{m}.

Unit weight =82162=64162=0.3951 kg/m= \dfrac{8^2}{162} = \dfrac{64}{162} = 0.3951\ \text{kg/m}.

Weight =49.20×0.3951=19.44 kg= 49.20 \times 0.3951 = 19.44\ \text{kg}.

Step 3 — Total weight

W=61.63+19.44=81.07 kgW = 61.63 + 19.44 = 81.07\ \text{kg}

Total weight of steel = 81.07 kg (≈ 81.1 kg).

measurement-civil-workssteel-reinforcementbar-bending
8short5 marks

Differentiate between general specifications and detailed specifications. State three purposes served by specifications in a construction contract.

General vs. detailed specifications

AspectGeneral specificationsDetailed specifications
ScopeBrief, overall statement of the class/nature of work and materials for the whole projectItem-by-item, full description of materials, proportions, workmanship and testing for each item
Detail levelLow; gives a general idea of the building's qualityHigh; gives exact requirements for execution
UseHelps form a general idea and approximate cost; used at preliminary stageUsed for execution, rate analysis, and as part of the contract for payment and quality control
Example"Superstructure in first-class brickwork in cement mortar""Brickwork with first-class bricks (min. crushing strength 10.5 N/mm²) in cement mortar 1:6, joints not exceeding 10 mm, properly cured for 7 days..."

Three purposes of specifications

  1. Define quality: they fix the standard/quality of materials and workmanship so the desired durability and performance are achieved.
  2. Basis for rate analysis and cost: the rate of each item depends on its specification; they enable correct estimation and fair payment.
  3. Legal/contractual control: being part of the contract, they let the client/engineer enforce quality, reject sub-standard work, and settle disputes.
specificationsgeneral-detailed-specifications
9short5 marks

A property fetches a net annual rental income of NRs. 4,80,000 after deducting all outgoings. If an investor expects a return (rate of interest) of 8%8\% on the investment, determine (a) the Year's Purchase (Y.P.) and (b) the capitalized value of the property by the rental (income) method.

(a) Year's Purchase

For a perpetual income, Year's Purchase:

Y.P.=100rate of interest=1008=12.5Y.P. = \frac{100}{\text{rate of interest}} = \frac{100}{8} = 12.5

Year's Purchase = 12.5.

(b) Capitalized value

Capitalized value=Net annual income×Y.P.=4,80,000×12.5\text{Capitalized value} = \text{Net annual income} \times Y.P. = 4{,}80{,}000 \times 12.5 =60,00,000= 60{,}00{,}000

Capitalized (present) value of the property = NRs. 60,00,000.

(Interpretation: at an 8% expected return, an investor would pay up to NRs. 60 lakh so that the NRs. 4.80 lakh annual income yields 8% on the outlay: 4,80,000/60,00,000=0.084{,}80{,}000 / 60{,}00{,}000 = 0.08.)

valuationcapitalized-valueyear-purchase
10short5 marks

State the conventional unit of measurement and the mode of payment for each of the following civil works. Present your answer as a table. (i) Earthwork in excavation, (ii) DPC (damp-proof course), (iii) Plastering, (iv) RCC work, (v) Painting, (vi) Reinforcement steel, (vii) White-washing, (viii) Doors and windows (wood shutter), (ix) Cement concrete in foundation, (x) Brick masonry in superstructure.

Units of measurement and mode of payment

S.N.Item of workUnit of measurementBasis of payment
(i)Earthwork in excavationcubic metre (m³)volume
(ii)DPC (damp-proof course)square metre (m²)area
(iii)Plasteringsquare metre (m²)area
(iv)RCC workcubic metre (m³)volume
(v)Paintingsquare metre (m²)area
(vi)Reinforcement steelquintal / kg (mass)weight
(vii)White-washingsquare metre (m²)area
(viii)Doors & windows (wood shutter)square metre (m²)area of shutter
(ix)Cement concrete in foundationcubic metre (m³)volume
(x)Brick masonry in superstructurecubic metre (m³)volume

Rule of thumb: work in which thickness varies or is substantial is paid by volume (m³); thin, surface-finish or uniform-thickness work is paid by area (m²); steel is paid by mass.

methods-of-measurementunits-of-measurement
11short5 marks

Compute the net area of 12 mm thick cement plaster (1:6) required on the inside faces of the four walls of a room measuring 5.00 m×4.00 m5.00\ \text{m} \times 4.00\ \text{m} (internal) and 3.20 m3.20\ \text{m} clear height. Deduct one door 1.00 m×2.10 m1.00\ \text{m} \times 2.10\ \text{m} and two windows each 1.20 m×1.50 m1.20\ \text{m} \times 1.50\ \text{m} (deduct full opening area for both faces of plaster; here plaster is only on the inside, so deduct the opening area once for each opening).

Step 1 — Gross plaster area (inside faces of 4 walls)

Internal perimeter =2(5.00+4.00)=18.00 m= 2(5.00 + 4.00) = 18.00\ \text{m}.

Gross area =perimeter×height=18.00×3.20=57.600 m2= \text{perimeter} \times \text{height} = 18.00 \times 3.20 = 57.600\ \text{m}^2.

Step 2 — Deduction for openings

Door =1.00×2.10=2.100 m2= 1.00 \times 2.10 = 2.100\ \text{m}^2.

Windows (2 No.) =2×(1.20×1.50)=2×1.800=3.600 m2= 2 \times (1.20 \times 1.50) = 2 \times 1.800 = 3.600\ \text{m}^2.

Total deduction =2.100+3.600=5.700 m2= 2.100 + 3.600 = 5.700\ \text{m}^2.

Step 3 — Net plaster area

Anet=57.6005.700=51.900 m2A_{net} = 57.600 - 5.700 = 51.900\ \text{m}^2

Net inside plaster area = 51.90 m².

(Note: in practice the door reveal/jamb plaster and window sill may be added per the method of measurement; here, as specified, full opening areas are deducted once for the single inside face.)

measurement-civil-worksplasteringdeductions

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) question paper 2079?
The full BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) 2079 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Estimating and Costing (IOE, CE 703) 2079 paper come with solutions?
Yes. Every question on this Estimating and Costing (IOE, CE 703) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) 2079 paper?
The BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) 2079 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Estimating and Costing (IOE, CE 703) past paper free?
Yes — reading and attempting this Estimating and Costing (IOE, CE 703) past paper on Kekkei is completely free.