BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) Question Paper 2077 Nepal
This is the official BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) question paper for 2077, as set in the regular annual examination. It carries 80 full marks and a time allowance of 180 minutes, across 11 questions. On Kekkei you can attempt this Estimating and Costing (IOE, CE 703) past paper online with a timer, get instant AI feedback and step-by-step solutions, and track the topics where you lose marks — completely free. Whether you are revising for your BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) exam or solving previous years' question papers, this 2077 paper is a great way to practise under real exam conditions.
Section A: Long Answer Questions
Attempt all questions.
A road embankment is to be constructed for a length of 300 m. The formation (top) width of the embankment is 7.0 m and the height of the bank is 1.5 m throughout. The side slopes are 2 horizontal : 1 vertical on both sides, and the ground is level along the entire length.
(a) Compute the volume of earthwork in filling using:
- the mid-sectional area (mean section) method, and
- the prismoidal (trapezoidal cross-section) method.
(b) Explain why both methods give the same answer in this particular case, and state one situation where they would differ.
(c) If the borrow-pit soil bulks by 12% when loosened and compacts to 0.90 of its loose volume in the embankment, estimate the loose (truck) volume of soil that must be carried.
Geometry of the cross-section
The embankment cross-section is a symmetrical trapezium:
- Top (formation) width
- Height
- Side slope (horizontal per unit vertical)
Bottom width
Cross-sectional area of trapezium:
(Check: area of trapezium ✓)
(a) Volume of earthwork
1. Mid-sectional (mean section) method
Since the height is constant, the mid-section area equals the end areas .
2. Prismoidal / trapezoidal method
With equal end areas and mid-area , the prismoidal formula gives:
(b) Why the answers agree
The ground is level and the height (hence the cross-sectional area) is constant over the whole length. Both methods then reduce to (uniform area) × (length), so they must coincide. They differ when the section area varies non-linearly along the length (e.g. when ground undulates or the bank height changes), because the mean-area method assumes a linear variation of area while the prismoidal method accounts for the curvature of the solid and is the more accurate.
(c) Loose (truck) volume required
Let the loose volume be . After hauling, the soil compacts to of its loose volume in the embankment:
The 12% bulking from bank (in-situ) state describes the bank→loose change at the borrow pit but the controlling requirement here is the loose-to-compacted shrinkage, so the volume of loose soil that must be carried is 5000 m³.
Carry out the rate analysis for 1 m³ of brickwork in 1:6 cement–sand mortar in the superstructure, using modular bricks of nominal size (laid with 10 mm joints).
Use the following data:
- Bricks required: 500 nos per m³ (allow 2% wastage)
- Dry mortar for 1 m³ brickwork: 0.30 m³
- Dry-to-wet (bulking) factor for mortar: 1.25
- Cement: 1 bag = 0.035 m³, sand sold loose
- Mason: 0.9 day, Labour (beldar): 1.4 day per m³
Rates: Bricks Rs 14/no; Cement Rs 850/bag; Sand Rs 2200/m³; Mason Rs 1200/day; Labour Rs 800/day. Add 10% contractor's overhead & profit and 3% for water, tools & sundries on the prime cost.
Step 1 — Materials
Bricks (with 2% wastage): nos
Mortar. Dry mortar required . (The 0.30 already represents the dry volume needed for the wet mortar in joints, so we proportion the dry volume directly.)
For 1:6 mortar, total parts .
Cement volume
Cement bags bags
Sand volume
Step 2 — Labour
| Item | Quantity | Rate (Rs) | Amount (Rs) |
|---|---|---|---|
| Mason | 0.9 day | 1200 | 1080.0 |
| Beldar (labour) | 1.4 day | 800 | 1120.0 |
| Labour sub-total | 2200.0 |
Step 3 — Prime cost
| Component | Amount (Rs) |
|---|---|
| Bricks | 7140.0 |
| Cement | 1040.7 |
| Sand | 565.7 |
| Labour | 2200.0 |
| Prime cost | 10946.4 |
Step 4 — Add-ons
Water, tools & sundries @ 3% Sub-total
Contractor's OH & Profit @ 10%
Rounded rate ≈ Rs 12,402 per m³ of brickwork in 1:6 mortar.
A single-room building has internal dimensions (clear inside). The walls are 0.30 m thick brickwork carried on a continuous RCC strip footing. Using the centre-line method, compute:
(a) the total centre-line length of the walls;
(b) the volume of brickwork in superstructure if the wall height above plinth is 3.0 m (ignore openings for this part);
(c) the volume of RCC in the footing if the footing is 0.60 m wide and 0.30 m deep, running continuously along the centre line.
Show how the centre-line method automatically handles the wall corners.
Centre-line concept
In the centre-line method we take the length of the centre line of the wall and multiply by the cross-sectional area. For a closed rectangular building the centre line forms a smaller rectangle, and using the centre line automatically accounts for the corners: each external corner adds material while each internal corner removes the same amount, and these cancel exactly when we use the mean (centre) line. No separate corner deduction is needed.
(a) Centre-line length
Internal size , wall thickness .
Centre-line dimensions internal one wall thickness (half thickness on each opposite side):
Total centre-line length (perimeter of centre-line rectangle):
(b) Volume of brickwork (superstructure)
(c) Volume of RCC footing
Footing runs along the same centre line, width , depth :
Corner-handling check
If we instead used the long-wall / short-wall method:
- Long walls (out-to-out) length each → 2 × 5.30 = 10.60 m
- Short walls (in-to-in) length each → 2 × 3.70 = 7.40 m
- Total of wall measured along its own line… but adding back the corner overlaps recovers of mean line. The centre-line method gives the corner-corrected length 19.20 m in a single step, confirming the result.
A residential building was constructed 25 years ago at a cost of Rs 30,00,000 (structure only). The present cost of the land is Rs 50,00,000. The estimated total life of the structure is 60 years and the scrap value is 10% of the original construction cost.
(a) Determine the depreciation per year and the present depreciated value of the building using the straight-line method.
(b) Compute the present total value of the property (land + building).
(c) If the property fetches a net annual rent of Rs 4,80,000, and an investor expects a net yield of 6% per annum, what capitalized value would the investor be willing to pay? Compare it with (b) and comment.
(a) Straight-line depreciation
Original cost Scrap value Total life years
Annual depreciation:
Depreciation in 25 years
Present depreciated value of building:
(b) Present total value of property
(c) Capitalized value (investor's view)
Year's purchase (YP) at 6% (perpetuity basis):
Capitalized value:
Comparison & comment. The capitalized (income) value of Rs 80,00,000 exceeds the cost-based value of Rs 68,75,000 by about Rs 11.25 lakh (≈16%). This means the property earns a higher return than the cost approach suggests — the location/rental demand is strong, so on a pure investment basis the property is worth more than its depreciated replacement cost. An investor seeking a 6% yield could justify paying up to Rs 80 lakh.
(a) Define a tender and explain, in sequence, the major stages of the competitive (open) tendering process for a public civil-works contract in Nepal.
(b) List the essential documents that together form a tender / contract document and briefly state the purpose of each.
(c) Distinguish between earnest money (bid security) and performance security (retention), including typical percentage values used in Nepal.
(a) Definition and tendering process
Tender: A tender is a formal written offer submitted by a contractor, in response to an invitation, to execute specified works (or supply goods/services) at quoted rates and within stated conditions. Acceptance of a tender forms a binding contract.
Stages of competitive (open) tendering:
- Preparation of drawings, specifications, BOQ and cost estimate by the client/engineer.
- Invitation for Bids (IFB) / Notice published (e.g. in national daily and on PPMO's e-GP portal).
- Issue/sale of bid documents to interested bidders.
- Pre-bid meeting and clarifications/addenda (if any).
- Submission of bids with bid security before the deadline.
- Opening of bids publicly at the stated time in presence of bidders.
- Evaluation — preliminary (completeness, security), technical, then financial; arithmetic correction.
- Award to the lowest substantially-responsive evaluated bidder; issue Letter of Acceptance.
- Signing of contract agreement after the successful bidder furnishes performance security.
(b) Documents forming the tender / contract document
| Document | Purpose |
|---|---|
| Notice / Invitation for Bids | Informs and invites contractors; states scope, eligibility, dates |
| Instructions to Bidders (ITB) | Rules for preparing and submitting bids |
| Conditions of Contract (General & Particular) | Legal rights, obligations, payment, disputes |
| Drawings | Define the geometry and details of the work |
| Technical Specifications | Define quality of materials and workmanship |
| Bill of Quantities (BOQ) | Itemised quantities for pricing and payment |
| Schedule of Rates / Priced BOQ | Contractor's quoted rates |
| Bid forms & securities | Formal offer and guarantees |
| Form of Agreement | Binds the parties on signing |
(c) Earnest money vs. performance security
| Aspect | Earnest money (Bid security) | Performance security |
|---|---|---|
| When given | With the bid, before award | After award, before signing contract |
| Purpose | Ensures bidder does not withdraw / signs if selected | Ensures the contractor completes the work to terms |
| Typical value (Nepal) | about 2–2.5% of estimated cost (often a fixed lump as per PPMO) | about 5% of contract amount (bank guarantee) |
| Refund | Returned to unsuccessful bidders after award; to winner after furnishing performance security | Released after successful completion / defect-liability period |
A related item, retention money, is typically 5% deducted from each running bill (up to a ceiling) and released after the defect-liability period — it supplements the performance security.
Section B: Short Answer Questions
Attempt all questions.
Define estimate and list any four types of estimates with one line describing the purpose of each.
Estimate: An estimate is the calculated, probable cost of a project, computed in advance from drawings and specifications using known rates of materials, labour and other charges. It tells the owner whether the scheme is financially feasible and how much money to arrange.
Four types of estimates:
- Preliminary (approximate) estimate — rough cost based on per-unit (per m², per bed, per km) rates, used to decide whether to proceed and to obtain administrative approval.
- Detailed estimate — item-wise quantities × rates worked out from full drawings; the most accurate, used for tendering and execution.
- Revised estimate — prepared when the original is exceeded by more than ~5% or scope changes, to seek fresh sanction.
- Supplementary estimate — for additional works/items found necessary after the original estimate was sanctioned, prepared and approved separately.
(Others: quantity estimate, annual repair/maintenance estimate.)
Differentiate between general specifications and detailed specifications, and state why specifications are important in a contract.
| Basis | General specification | Detailed specification |
|---|---|---|
| Scope | Brief, overall description of the nature/class of work for the whole project | Item-by-item description of materials and workmanship for each item of work |
| Detail level | Low — gives a general idea of cost class and quality | High — gives proportions, methods, tolerances, testing |
| Use | Helps the owner form a general idea and compare schemes | Guides the contractor's actual execution and the engineer's checking/payment |
| Example | "First-class building with RCC frame and brick walls in cement mortar" | "Brickwork in 1:6 cement mortar with first-class bricks, 10 mm joints, cured 7 days…" |
Importance of specifications:
- Define the quality of materials and workmanship, fixing the standard the contractor must meet.
- Form a basis of the rate analysis and hence the cost; rates have meaning only against a specification.
- Serve as a legal/contract reference for acceptance, rejection and dispute resolution.
- Ensure the finished work matches the owner's intention even though drawings alone cannot show quality.
For 1 m³ of cement concrete of ratio 1:2:4, calculate the quantities of cement (in bags), sand and coarse aggregate. Take the dry-volume factor (dry to wet) as 1.54 and 1 bag of cement = 0.035 m³ (50 kg).
Dry volume
For 1 m³ of finished (wet) concrete, dry volume of ingredients:
Total parts for 1:2:4 .
Cement
Sand (fine aggregate)
Coarse aggregate
Summary
| Material | Quantity per m³ |
|---|---|
| Cement | 6.29 bags (0.22 m³) |
| Sand | 0.44 m³ |
| Coarse aggregate | 0.88 m³ |
(Check: 0.22 + 0.44 + 0.88 = 1.54 m³ ✓)
A wall is 6.0 m long and 3.0 m high. It contains a door of and a window of . Calculate the net area of 12 mm cement plaster on one face of the wall, applying standard deductions for openings.
Gross area of wall (one face)
Deductions for openings (one face)
Door: Window: Total openings
For 12 mm plaster on one face, the full opening area is deducted on that face (no separate reveal addition is required at this level of measurement).
Net plaster area
Net area of 12 mm cement plaster on one face = 14.10 m².
(Note: as per IS/standard practice, for openings up to 0.5 m² no deduction is made and jambs are not added; both openings here exceed that, so full deduction applies and the result stands at 14.10 m².)
Define sinking fund. A structure must be replaced after 40 years at an estimated cost of Rs 20,00,000. Compute the annual sinking-fund instalment if money accumulates at 5% compound interest per annum.
Definition
A sinking fund is an amount set aside annually (and invested at compound interest) so that, by the end of an asset's useful life, the accumulated fund equals the money required to replace the asset. It spreads the future replacement cost over the life as equal yearly instalments.
Annual instalment
The sinking-fund formula:
where , , .
Compute .
So .
Annual sinking-fund instalment ≈ Rs 16,556.
Compare the long-wall short-wall method and the centre-line method of estimating quantities. State one advantage and one limitation of the centre-line method.
| Basis | Long-wall short-wall method | Centre-line method |
|---|---|---|
| Approach | Long walls measured out-to-out, short walls in-to-in (or vice-versa), each item separately | Single centre-line length × cross-section, common for all items |
| Corners | Corner lengths added/subtracted explicitly | Corners handled automatically (cancel out) for rectangular plans |
| Speed | Slower; more entries | Faster; fewer calculations |
| Suitability | Any plan shape | Best for simple symmetrical/rectangular plans |
Advantage of centre-line method: It is quick and reduces calculation, since one centre-line length serves footing, masonry, DPC, plinth etc.
Limitation: For plans with cross-walls, junctions or odd angles, a correction (deduction of half the wall thickness at each T-junction/cross-junction) is needed, and for irregular shapes it becomes error-prone — the long-wall short-wall method is then safer.
Frequently asked questions
- Where can I find the BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) question paper 2077?
- The full BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) 2077 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
- Does the Estimating and Costing (IOE, CE 703) 2077 paper come with solutions?
- Yes. Every question on this Estimating and Costing (IOE, CE 703) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
- How many marks is the BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) 2077 paper?
- The BE Civil Engineering (IOE, TU) Estimating and Costing (IOE, CE 703) 2077 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
- Is practising this Estimating and Costing (IOE, CE 703) past paper free?
- Yes — reading and attempting this Estimating and Costing (IOE, CE 703) past paper on Kekkei is completely free.