BE Civil Engineering (IOE, TU) Engineering Economics (IOE, CE 656) Question Paper 2079 Nepal
This is the official BE Civil Engineering (IOE, TU) Engineering Economics (IOE, CE 656) question paper for 2079, as set in the regular annual examination. It carries 80 full marks and a time allowance of 180 minutes, across 11 questions. On Kekkei you can attempt this Engineering Economics (IOE, CE 656) past paper online with a timer, get instant AI feedback and step-by-step solutions, and track the topics where you lose marks — completely free. Whether you are revising for your BE Civil Engineering (IOE, TU) Engineering Economics (IOE, CE 656) exam or solving previous years' question papers, this 2079 paper is a great way to practise under real exam conditions.
Section A: Long Answer Questions
Attempt all questions.
A municipality must select exactly one of two mutually exclusive water-pump designs. Both serve the same need over a 10-year study period and the MARR is 10% per year.
| Item | Pump A | Pump B |
|---|---|---|
| First cost | Rs 600,000 | Rs 900,000 |
| Annual operating cost | Rs 120,000 | Rs 70,000 |
| Salvage value (year 10) | Rs 60,000 | Rs 120,000 |
(a) Using present worth at MARR, determine which pump should be chosen. (b) Determine the incremental rate of return (IRR on B − A) and confirm the decision. (c) State the conditions under which the conclusions in (a) and (b) must agree.
Given: , yr.
Factor values at 10%, 10 yr:
(a) Present Worth of Costs
Treat costs as positive outflows; salvage reduces PW.
Pump A:
Pump B:
Since , Pump B has the lower present worth of cost and should be selected.
(b) Incremental Rate of Return (B − A)
Incremental cash flows (B minus A):
- Extra first cost: (outflow at year 0)
- Annual savings: per year (inflow, years 1–10)
- Extra salvage: (inflow at year 10)
Set incremental PW to zero:
Try i = 12%: ,
Try i = 13%: ,
Interpolating:
Since , the extra investment in B is justified — select Pump B. This confirms part (a).
(c) Agreement condition
PW analysis and (correctly performed) incremental ROR analysis always give the same decision for mutually exclusive alternatives, provided that: (i) the same study period / common service life is used, (ii) the analysis is done on the increment (defender vs. challenger), not on individual project IRRs, and (iii) reinvestment is assumed at the MARR. Ranking by individual IRRs alone can mislead because a higher IRR on a smaller investment may not maximise wealth.
A government road authority evaluates three independent-site but mutually exclusive bypass alignments for a single corridor. All have a 20-year life, no salvage, and the social discount rate is 8% per year.
| Alignment | Initial cost (Rs lakh) | Annual benefits (Rs lakh) | Annual O&M (Rs lakh) |
|---|---|---|---|
| X | 800 | 130 | 25 |
| Y | 1,100 | 175 | 30 |
| Z | 1,500 | 225 | 40 |
(a) Compute the conventional B/C ratio of each alignment. (b) Using incremental B/C analysis, recommend the alignment to build. (c) Comment on how treating O&M as a disbenefit (numerator) vs. a cost (denominator) would change the absolute B/C value but not the decision.
Given: , yr, .
Convert annual flows to present worth using . Net annual benefit = benefits − O&M (treating O&M in numerator) — but part (a) uses the conventional ratio with O&M in the denominator as a cost.
(a) Conventional B/C (O&M as annual cost in denominator)
X: ;
Y: ;
Z: ;
All three exceed 1.0, so each is individually acceptable.
(b) Incremental B/C
Order by increasing total cost (denominator): X (1045.45) < Y (1394.54) < Z (1892.72). Baseline = X (acceptable, B/C > 1).
Y − X:
Z − Y:
Recommendation: build Alignment Y.
(c) O&M placement
If O&M is netted in the numerator as a disbenefit, the ratio becomes . This lowers the numerator and the denominator differently, changing the absolute B/C number (it shifts away from 1). However, for incremental analysis the cross-over test () is mathematically equivalent to checking whether , i.e. whether incremental net PW > 0. Hence the selection (Y) is unchanged; only reported magnitudes differ.
A construction firm owns an excavator (the defender). A new model (the challenger) is available. MARR = 12% per year.
Defender: current market (trade-in) value Rs 1,500,000; if kept one more year, end-of-year salvage Rs 1,100,000 and operating cost Rs 900,000 during that year.
Challenger: first cost Rs 5,000,000; economic life 6 years; salvage at year 6 Rs 800,000; uniform annual operating cost Rs 350,000.
(a) Compute the AW (marginal cost) of keeping the defender one more year. (b) Compute the AW of the challenger over its economic life. (c) State whether to replace now, and explain the meaning of the defender's first cost in a replacement study.
Given: MARR . Factors at 12%: , .
(a) Defender — cost of one more year of service
The defender's "investment" if retained is its current market value Rs 1,500,000 (the opportunity cost — money forgone by not selling now).
Annual cost of keeping one more year:
For : and .
(b) Challenger — AW over 6-year economic life
Capital recovery:
(Equivalently .)
Add operating cost:
(c) Decision
The challenger's equivalent annual cost is lower (by about Rs 12,400/yr), so replace the defender now with the challenger.
Meaning of the defender's first cost: its original purchase price is a sunk cost and is irrelevant to the replacement decision. What matters is the defender's current market value, which represents the opportunity cost (capital tied up) of continuing to own it.
A contractor will receive maintenance income that is Rs 400,000 in today's (year-0) purchasing power and then escalates with general inflation. The income is received at the end of each year for 8 years. General inflation is 6% per year and the contractor's real (inflation-free) MARR is 9% per year.
(a) Compute the market (nominal) interest rate. (b) Find the present worth of the income stream using two methods — (i) real-rate method on constant-rupee cash flows, and (ii) nominal-rate method on actual-rupee cash flows — and show they agree. (c) Briefly explain why the two methods give the same answer.
Given: real MARR , inflation , yr. Year-0-rupee cash flow each year (constant purchasing power).
(a) Market (nominal) rate
(b)(i) Real-rate method (constant Rs)
The cash flow expressed in constant year-0 rupees is a level annuity of Rs 400,000. Discount at the real rate 9%:
(b)(ii) Nominal-rate method (actual Rs)
Actual (then-current) cash flow in year grows with inflation:
Discount each at the nominal rate 15.54%. Because the actual flow is a geometric series growing at discounted at :
The two results agree to within rounding (≈ Rs 2.21 million vs Rs 2.19 million); the small gap is purely from rounding the geometric-series factor and the table value. Using more decimals both converge to ≈ Rs 2.20 million.
(c) Why they agree
Deflating an actual-rupee cash flow by and discounting at the real rate is algebraically identical to discounting the actual cash flow at the nominal rate , because . The inflation factor cancels, so PW is invariant to the rupee basis chosen — provided the rate matches the rupee basis (real with constant Rs, nominal with actual Rs).
A precast-concrete plant buys a batching machine for Rs 2,400,000, with an estimated salvage value of Rs 240,000 and a useful life of 5 years.
(a) Prepare the depreciation schedule (annual depreciation and end-of-year book value) by the Straight-Line (SL) method. (b) Prepare the schedule by the Double-Declining-Balance (DDB) method, ensuring book value never drops below salvage. (c) For each method, state the book value at the end of year 3 and comment on which method writes value off faster.
Given: Cost , salvage , life yr.
(a) Straight-Line
| Year | Depreciation (Rs) | Book value end-of-year (Rs) |
|---|---|---|
| 0 | — | 2,400,000 |
| 1 | 432,000 | 1,968,000 |
| 2 | 432,000 | 1,536,000 |
| 3 | 432,000 | 1,104,000 |
| 4 | 432,000 | 672,000 |
| 5 | 432,000 | 240,000 |
(b) Double-Declining-Balance
DDB rate . Each year , but never below salvage Rs 240,000.
| Year | Depreciation taken (Rs) | Book value end (Rs) | |
|---|---|---|---|
| 1 | 0.40(2,400,000)=960,000 | 960,000 | 1,440,000 |
| 2 | 0.40(1,440,000)=576,000 | 576,000 | 864,000 |
| 3 | 0.40(864,000)=345,600 | 345,600 | 518,400 |
| 4 | 0.40(518,400)=207,360 | 207,360 | 311,040 |
| 5 | 0.40(311,040)=124,416 | limited to 71,040 so BV=salvage | 240,000 |
Year 5 check: unrestricted DDB would give BV = 311,040 − 124,416 = 186,624, which is below salvage (240,000). Therefore year-5 depreciation is capped at , leaving BV = Rs 240,000.
(c) End-of-year-3 book value and comparison
- SL:
- DDB:
DDB writes the asset down much faster in the early years (larger early deductions, smaller later ones), giving a far lower year-3 book value. This accelerated pattern is advantageous for early tax shielding, whereas SL spreads the deduction evenly across the life.
Section B: Short Answer Questions
Attempt all questions.
An engineer deposits Rs 50,000 now and Rs 30,000 at the end of every year for 6 years into an account paying a nominal 12% per year compounded monthly.
(a) Find the effective annual interest rate. (b) Find the total amount accumulated at the end of year 6.
Given: nominal , compoundings/yr, yr.
(a) Effective annual rate
(b) Future worth at year 6
Use the effective annual rate (12.6825%) with annual cash flows.
Single deposit (compounded 6 yr):
Annual series (6 end-of-year payments):
Total:
Maintenance costs for a steel bridge are Rs 80,000 at the end of year 1 and increase by Rs 15,000 each year through year 8. At an interest rate of 10% per year:
(a) Express the series as a base annuity plus an arithmetic gradient and find its present worth. (b) Find the equivalent uniform annual cost (EUAC).
Given: base (year 1), gradient , , .
Factors at 10%, 8 yr: , , .
(a) Present worth
(b) Equivalent uniform annual cost
Check: — agrees within rounding.
A small hydropower investment costs Rs 1,200,000 today and returns net cash inflows of Rs 320,000 per year for 6 years, with a salvage value of Rs 150,000 at the end of year 6.
Determine the project's internal rate of return (IRR) by trial and interpolation, and state whether it is acceptable at a MARR of 14%.
Given: , /yr, , .
Set PW = 0:
Try i = 16%: ,
Try i = 18%: ,
Interpolate:
Since , the project is acceptable.
(a) A flood-control embankment costs Rs 8,000,000 to build and Rs 250,000 per year to maintain forever. At 7% per year, find its capitalized cost (present worth of perpetual service). (b) A culvert costing Rs 600,000 lasts 25 years with no salvage; at 7%, find its capital recovery (annual ownership) cost.
Given: .
(a) Capitalized cost (perpetual maintenance)
For a perpetual uniform cost, .
(b) Capital recovery of the culvert
(No salvage, so there is no credit term.)
A surveying instrument costs Rs 900,000, has a salvage value of Rs 100,000, and a useful life of 4 years.
(a) Using the Sum-of-Years-Digits (SOYD) method, find the depreciation charge for each year. (b) Find the book value at the end of year 2.
Given: , , . Depreciable base .
Sum of years digits: .
(a) Annual depreciation
| Year | Fraction | (Rs) |
|---|---|---|
| 1 | 4/10 | |
| 2 | 3/10 | |
| 3 | 2/10 | |
| 4 | 1/10 |
Check: ✓ (equals depreciable base).
(b) Book value end of year 2
Answer the following short numerical/conceptual parts (each independent).
(a) What single sum invested today at 9% compounded annually will grow to Rs 1,000,000 in 12 years? (b) How many years (to one decimal) are needed for money to triple at 8% per year compounded annually? (c) Distinguish briefly between the present worth and annual worth methods, and state one situation where AW is more convenient than PW.
(a) Required deposit today (P/F)
(b) Time to triple at 8%
(Rule-of-72 check: yr to double; tripling sensibly takes longer, ≈ 14 yr.)
(c) PW vs AW
- Present Worth (PW): converts all cash flows to a single equivalent value at time 0. Best for comparing total lifetime wealth impact and for one-time / non-repeating decisions.
- Annual Worth (AW): converts all cash flows to an equivalent uniform end-of-period amount.
When AW is more convenient: when comparing mutually exclusive alternatives with unequal lives, AW automatically reflects a per-year (repeated-service) basis, so there is no need to find a least-common-multiple study period as PW would require. AW is also natural when results are wanted on a per-unit-time basis (e.g., cost per year, per tonne).
Frequently asked questions
- Where can I find the BE Civil Engineering (IOE, TU) Engineering Economics (IOE, CE 656) question paper 2079?
- The full BE Civil Engineering (IOE, TU) Engineering Economics (IOE, CE 656) 2079 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
- Does the Engineering Economics (IOE, CE 656) 2079 paper come with solutions?
- Yes. Every question on this Engineering Economics (IOE, CE 656) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
- How many marks is the BE Civil Engineering (IOE, TU) Engineering Economics (IOE, CE 656) 2079 paper?
- The BE Civil Engineering (IOE, TU) Engineering Economics (IOE, CE 656) 2079 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
- Is practising this Engineering Economics (IOE, CE 656) past paper free?
- Yes — reading and attempting this Engineering Economics (IOE, CE 656) past paper on Kekkei is completely free.