Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long10 marks

A new flexible pavement is to be designed for a National Highway in the Terai region of Nepal using the IRC:37-2012 (CBR–traffic) approach. The following data are available:

  • Initial traffic at the end of construction = 1500 commercial vehicles per day (CVPD), counted in both directions.
  • Annual traffic growth rate, r=7.5%r = 7.5\%.
  • Design life, n=15n = 15 years.
  • Vehicle Damage Factor, VDF=3.5VDF = 3.5.
  • Lane Distribution Factor, D=0.75D = 0.75 (two-lane single carriageway).
  • Subgrade CBR = 6%.

(a) Compute the cumulative number of standard axles (in millions of standard axles, msa) for the design period. [6]

(b) Explain how the design CBR of a subgrade is determined when several test pits give different CBR values, and state how the total pavement thickness and the bituminous-layer thickness are obtained from the IRC:37 design charts for the computed traffic and CBR. [4]

(a) Cumulative standard axles (msa)

The IRC:37 design traffic formula is

N=365×[(1+r)n1]r×A×D×FN = \frac{365 \times \big[(1+r)^n - 1\big]}{r} \times A \times D \times F

where AA is the initial number of commercial vehicles per day in the design lane direction at the start of the design period, DD is the lane distribution factor, FF is the vehicle damage factor.

Step 1 – Two-way to design-direction traffic. Traffic counted both directions = 1500 CVPD. Assuming a 50:50 directional split, traffic in one direction:

A=15002=750 CVPD.A = \frac{1500}{2} = 750 \text{ CVPD}.

Step 2 – Growth factor.

(1+r)n1r=(1.075)1510.075.\frac{(1+r)^n - 1}{r} = \frac{(1.075)^{15} - 1}{0.075}.

(1.075)15=2.95888(1.075)^{15} = 2.95888, so

2.9588810.075=1.958880.075=26.1184.\frac{2.95888 - 1}{0.075} = \frac{1.95888}{0.075} = 26.1184.

Step 3 – Cumulative standard axles.

N=365×26.1184×750×0.75×3.5.N = 365 \times 26.1184 \times 750 \times 0.75 \times 3.5.

Work stepwise:

  • 365×26.1184=9533.2365 \times 26.1184 = 9533.2
  • 9533.2×750=71499009533.2 \times 750 = 7\,149\,900
  • 7149900×0.75=53624257\,149\,900 \times 0.75 = 5\,362\,425
  • 5362425×3.5=187684885\,362\,425 \times 3.5 = 18\,768\,488 standard axles.
N18.77 msa\boxed{N \approx 18.77 \text{ msa}}

(b) Design CBR and reading the IRC:37 charts

Design CBR from multiple pits: The subgrade soil is tested (soaked CBR, 4-day soak) at representative locations. Because the weakest soil governs but isolated low outliers should not penalise the whole section, IRC recommends using a statistically representative value — the lowest value applicable to a homogeneous stretch, or where many tests exist, the value such that not more than a chosen percentile (commonly the value exceeded by ~90% of samples for high-volume roads) is exceeded. The 90th-percentile / representative CBR for the homogeneous section is adopted as the design subgrade CBR.

Using the charts: With (i) cumulative traffic N=18.7720N = 18.77 \approx 20 msa and (ii) subgrade CBR = 6%, the relevant IRC:37 pavement design catalogue/chart gives the total pavement thickness (sum of bituminous + granular base + granular sub-base) and a recommended pavement composition. The chart/table for CBR 6% and 20 msa specifies the thicknesses of:

  • Bituminous Concrete (BC) wearing course,
  • Dense Bituminous Macadam (DBM) binder course (the bituminous-layer thickness),
  • Granular base (WMM) and granular sub-base (GSB).

The bituminous-layer (BC + DBM) thickness is read directly from the composition table for the design traffic; higher traffic and lower CBR both increase the required thicknesses.

flexible-pavementirc-37pavement-design
2long10 marks

A cement-concrete (rigid) pavement slab of thickness h=250 mmh = 250\text{ mm} rests on a subgrade with modulus of subgrade reaction k=60 MN/m3k = 60\text{ MN/m}^3. The concrete has modulus of elasticity E=3.0×104 MPaE = 3.0 \times 10^4\text{ MPa} and Poisson's ratio μ=0.15\mu = 0.15. A wheel load P=50 kNP = 50\text{ kN} is applied through a circular contact area of radius a=150 mma = 150\text{ mm}.

(a) Compute the radius of relative stiffness, ll. [3]

(b) Using Westergaard's edge-load equation, compute the critical edge-load stress. Use

σe=0.572Ph2[4log10 ⁣(lb)+0.359],\sigma_e = \frac{0.572\,P}{h^2}\left[4\log_{10}\!\left(\frac{l}{b}\right) + 0.359\right],

with equivalent radius b=1.6a2+h20.675hb = \sqrt{1.6a^2 + h^2} - 0.675h (since a<1.724ha < 1.724h). [5]

(c) State which of interior, edge, or corner loading is most critical and one design implication. [2]

(a) Radius of relative stiffness

l=[Eh312(1μ2)k]0.25l = \left[\frac{E h^3}{12(1-\mu^2)\,k}\right]^{0.25}

Use consistent units (N, mm): E=3.0×104 MPa=3.0×104 N/mm2E = 3.0\times10^4\text{ MPa} = 3.0\times10^4\text{ N/mm}^2, h=250 mmh = 250\text{ mm}, k=60 MN/m3=0.06 N/mm3k = 60\text{ MN/m}^3 = 0.06\text{ N/mm}^3.

Numerator: Eh3=3.0×104×2503=3.0×104×1.5625×107=4.6875×1011E h^3 = 3.0\times10^4 \times 250^3 = 3.0\times10^4 \times 1.5625\times10^7 = 4.6875\times10^{11}.

Denominator: 12(10.152)k=12×(10.0225)×0.06=12×0.9775×0.06=0.703812(1-0.15^2)k = 12 \times (1-0.0225) \times 0.06 = 12 \times 0.9775 \times 0.06 = 0.7038.

l4=4.6875×10110.7038=6.6603×1011 mm4.l^4 = \frac{4.6875\times10^{11}}{0.7038} = 6.6603\times10^{11}\text{ mm}^4. l=(6.6603×1011)0.25.l = (6.6603\times10^{11})^{0.25}.

6.6603×1011=8.1610×105\sqrt{6.6603\times10^{11}} = 8.1610\times10^{5}; 8.1610×105=903.4\sqrt{8.1610\times10^{5}} = 903.4.

l903 mm\boxed{l \approx 903\text{ mm}}

(b) Edge-load stress

Equivalent radius (a=150<1.724h=431a = 150 < 1.724h = 431 mm, so use the small-area formula):

b=1.6a2+h20.675h=1.6(150)2+25020.675(250).b = \sqrt{1.6a^2 + h^2} - 0.675h = \sqrt{1.6(150)^2 + 250^2} - 0.675(250).

1.6×22500=360001.6 \times 22500 = 36000; +2502=36000+62500=98500+250^2 = 36000 + 62500 = 98500; 98500=313.85\sqrt{98500} = 313.85. 0.675×250=168.750.675 \times 250 = 168.75.

b=313.85168.75=145.10 mm.b = 313.85 - 168.75 = 145.10\text{ mm}.

Log term: l/b=903.4/145.10=6.226l/b = 903.4/145.10 = 6.226; log10(6.226)=0.7942\log_{10}(6.226) = 0.7942.

4×0.7942+0.359=3.1768+0.359=3.5358.4 \times 0.7942 + 0.359 = 3.1768 + 0.359 = 3.5358.

Stress: P=50 kN=50000 NP = 50\text{ kN} = 50000\text{ N}, h2=2502=62500 mm2h^2 = 250^2 = 62500\text{ mm}^2.

σe=0.572×5000062500×3.5358=2860062500×3.5358=0.4576×3.5358.\sigma_e = \frac{0.572 \times 50000}{62500} \times 3.5358 = \frac{28600}{62500} \times 3.5358 = 0.4576 \times 3.5358. σe1.618 MPa  (1.62 N/mm2)\boxed{\sigma_e \approx 1.618\text{ MPa} \;(\approx 1.62\text{ N/mm}^2)}

(c) Most critical loading and implication

For a typical jointed plain concrete pavement, the corner load produces the highest tensile stress, but where corners are protected by dowels/load transfer the edge load governs flexural design. Among the three, edge loading generally gives the largest mid-slab bottom tensile stress for design checks. Design implication: provide tie bars at longitudinal joints and adequate edge thickening / dowelled transverse joints, and ensure the flexural strength (modulus of rupture) exceeds the critical stress with the required factor of safety.

rigid-pavementwestergaardwheel-load-stress
3long8 marks

A Broad Gauge (BG) railway track (G=1.676 mG = 1.676\text{ m}, dynamic gauge =1.750 m= 1.750\text{ m} for cant purposes) has a circular curve of radius R=1000 mR = 1000\text{ m}. The maximum sanctioned speed on the section is 110 km/h110\text{ km/h} and the booked speed of goods (slow) trains is 50 km/h50\text{ km/h}.

(a) Determine the equilibrium cant for the maximum speed and the cant required by the equilibrium-speed (theoretical) approach. [2]

(b) Adopting the actual cant equal to the cant for the equilibrium speed (take equilibrium speed = average of the two = 80 km/h), compute the cant deficiency for the fast train and the cant excess for the goods train. State whether they are within IR permissible limits (cant deficiency 100 mm\le 100\text{ mm}, cant excess 75 mm\le 75\text{ mm}). [6]

Governing formula

For Indian Railways practice the cant (superelevation) is

e=GV2127R(e in m, G in m, V in km/h, R in m).e = \frac{G V^2}{127\,R}\quad\text{(}e\text{ in m, }G\text{ in m, }V\text{ in km/h, }R\text{ in m)}.

Using the dynamic gauge G=1.750 mG = 1.750\text{ m}, R=1000 mR = 1000\text{ m}.

(a) Cant for maximum speed and for equilibrium speed

Cant for maximum speed (110 km/h):

emax=1.750×1102127×1000=1.750×12100127000=21175127000=0.16673 m=166.7 mm.e_{max} = \frac{1.750 \times 110^2}{127 \times 1000} = \frac{1.750 \times 12100}{127000} = \frac{21175}{127000} = 0.16673\text{ m} = 166.7\text{ mm}.

Cant for equilibrium speed (80 km/h):

eeq=1.750×802127×1000=1.750×6400127000=11200127000=0.08819 m=88.2 mm.e_{eq} = \frac{1.750 \times 80^2}{127 \times 1000} = \frac{1.750 \times 6400}{127000} = \frac{11200}{127000} = 0.08819\text{ m} = 88.2\text{ mm}.

Adopt actual provided cant ea=88.2e_a = 88.2 mm (equilibrium-speed cant).

(b) Cant deficiency and cant excess

Cant deficiency (fast train, 110 km/h): Cant deficiency = (cant needed for max speed) − (cant provided)

Cd=emaxea=166.788.2=78.5 mm.C_d = e_{max} - e_a = 166.7 - 88.2 = 78.5\text{ mm}.

Since 78.5 mm100 mm78.5\text{ mm} \le 100\text{ mm}, the cant deficiency is within the permissible limit.

Cant excess (goods train, 50 km/h): Cant required for the slow speed:

eslow=1.750×502127×1000=1.750×2500127000=4375127000=0.03445 m=34.4 mm.e_{slow} = \frac{1.750 \times 50^2}{127 \times 1000} = \frac{1.750 \times 2500}{127000} = \frac{4375}{127000} = 0.03445\text{ m} = 34.4\text{ mm}.

Cant excess = (cant provided) − (cant needed for slow speed)

Ce=eaeslow=88.234.4=53.8 mm.C_e = e_a - e_{slow} = 88.2 - 34.4 = 53.8\text{ mm}.

Since 53.8 mm75 mm53.8\text{ mm} \le 75\text{ mm}, the cant excess is within the permissible limit.

Summary

QuantityValueLimitStatus
Cant for max speed166.7 mm
Provided cant (eq. speed)88.2 mm
Cant deficiency78.5 mm≤100 mmOK
Cant excess53.8 mm≤75 mmOK
Cd=78.5 mm (OK),Ce=53.8 mm (OK)\boxed{C_d = 78.5\text{ mm (OK)},\quad C_e = 53.8\text{ mm (OK)}}
railway-engineeringsuperelevationcant
4long8 marks

An airport is to be built to serve a design aircraft whose basic runway length under standard sea-level conditions is 2100 m2100\text{ m}. The site has the following characteristics:

  • Airport elevation = 1300 m above MSL.
  • Mean of the maximum daily temperatures of the hottest month =32C= 32^\circ\text{C}.
  • Mean of the average daily temperatures of the hottest month =24C= 24^\circ\text{C}.
  • Effective runway gradient =0.35%= 0.35\%.

Apply the ICAO corrections for elevation, temperature, and gradient (apply checks for the total correction limit) and determine the corrected (actual) runway length. [8]

ICAO corrections (sequential)

Step 1 – Elevation correction. Increase basic length by 7% per 300 m of elevation above MSL.

Elevation factor=7100×1300300=0.07×4.3333=0.30333.\text{Elevation factor} = \frac{7}{100} \times \frac{1300}{300} = 0.07 \times 4.3333 = 0.30333.

Corrected length after elevation:

L1=2100(1+0.30333)=2100×1.30333=2737.0 m.L_1 = 2100 \,(1 + 0.30333) = 2100 \times 1.30333 = 2737.0\text{ m}.

Step 2 – Temperature correction. First find the Airport Reference Temperature (ART):

ART=Ta+TmTa3=24+32243=24+2.667=26.667C.ART = T_a + \frac{T_m - T_a}{3} = 24 + \frac{32-24}{3} = 24 + 2.667 = 26.667^\circ\text{C}.

Standard atmospheric temperature at 1300 m elevation (lapse 0.0065C/m0.0065\,^\circ\text{C/m} from 15C15^\circ\text{C} at MSL):

Tstd=150.0065×1300=158.45=6.55C.T_{std} = 15 - 0.0065 \times 1300 = 15 - 8.45 = 6.55^\circ\text{C}.

Temperature rise above standard:

ΔT=ARTTstd=26.6676.55=20.117C.\Delta T = ART - T_{std} = 26.667 - 6.55 = 20.117^\circ\text{C}.

Increase length by 1% per 1C1^\circ\text{C} rise:

L2=L1(1+0.01ΔT)=2737.0×(1+0.20117)=2737.0×1.20117=3287.6 m.L_2 = L_1 (1 + 0.01\,\Delta T) = 2737.0 \times (1 + 0.20117) = 2737.0 \times 1.20117 = 3287.6\text{ m}.

Check on combined elevation + temperature correction: total = (3287.62100)/2100=56.6%(3287.6 - 2100)/2100 = 56.6\%. ICAO requires a specific site study if elevation+temperature correction exceeds 35%; here it is exceeded, so the result must be verified by site-specific data, but we proceed with the standard computation as required.

Step 3 – Gradient correction. Increase length after temperature correction by 20% per 1% effective gradient.

Gradient factor=0.20×0.35=0.07.\text{Gradient factor} = 0.20 \times 0.35 = 0.07. L3=L2(1+0.07)=3287.6×1.07=3517.7 m.L_3 = L_2 (1 + 0.07) = 3287.6 \times 1.07 = 3517.7\text{ m}.

Final corrected runway length

L3518 m\boxed{L \approx 3518\text{ m}}

(Elevation correction = +637.0 m; temperature = +550.6 m; gradient = +230.1 m; total = +1417.7 m over the basic 2100 m.)

airport-engineeringrunway-lengthcorrections
5long9 marks

A Benkelman Beam deflection survey was conducted on an existing flexible pavement (10 points) at a pavement temperature of 40C40^\circ\text{C}. The mean of the characteristic rebound deflection readings (already on the leg scale, multiplied by the 2:1 beam constant) is xˉ=1.10 mm\bar{x} = 1.10\text{ mm} with a standard deviation σ=0.25 mm\sigma = 0.25\text{ mm}.

(a) Compute the characteristic deflection Dc=xˉ+2σD_c = \bar{x} + 2\sigma for this National Highway. [2]

(b) Apply a temperature correction to bring the deflection to the standard 35C35^\circ\text{C} using a correction of 0.0065 mm0.0065\text{ mm} per C^\circ\text{C} per 25 mm of bituminous layer thickness; bituminous layer thickness =100 mm= 100\text{ mm}. (Higher temperature gives higher deflection, so correction is subtracted when reducing to 35C35^\circ\text{C}.) [4]

(c) If the design (allowable) deflection for the projected traffic is 1.00 mm1.00\text{ mm}, recommend the overlay decision and name two other functional/structural evaluation methods. [3]

(a) Characteristic deflection

Dc=xˉ+2σ=1.10+2(0.25)=1.10+0.50=1.60 mm.D_c = \bar{x} + 2\sigma = 1.10 + 2(0.25) = 1.10 + 0.50 = 1.60\text{ mm}. Dc=1.60 mm\boxed{D_c = 1.60\text{ mm}}

(b) Temperature correction to 35°C

Temperature difference from standard: ΔT=4035=5C\Delta T = 40 - 35 = 5^\circ\text{C}. Bituminous thickness in units of 25 mm: 100/25=4100/25 = 4.

Correction magnitude:

ΔD=0.0065×ΔT×t25=0.0065×5×4=0.130 mm.\Delta D = 0.0065 \times \Delta T \times \frac{t}{25} = 0.0065 \times 5 \times 4 = 0.130\text{ mm}.

Since measured at 40C40^\circ\text{C} (higher than standard, deflection is larger), subtract to reduce to 35C35^\circ\text{C}:

Dc,35=1.600.130=1.47 mm.D_{c,35} = 1.60 - 0.130 = 1.47\text{ mm}. Dc,351.47 mm\boxed{D_{c,35} \approx 1.47\text{ mm}}

(c) Overlay decision and other methods

The corrected characteristic deflection Dc,35=1.47 mmD_{c,35} = 1.47\text{ mm} exceeds the allowable design deflection of 1.00 mm1.00\text{ mm}. The existing pavement is structurally deficient for the projected traffic, so a strengthening (bituminous) overlay is required. The overlay thickness is read from the IRC:81 overlay design chart using the characteristic deflection (1.47 mm) and projected cumulative traffic (msa); a thicker overlay is needed because the deflection is well above the allowable value.

Two other evaluation methods:

  1. Falling Weight Deflectometer (FWD) — dynamic deflection bowl for back-calculation of layer moduli (structural).
  2. Roughness measurement by Bump Integrator / IRI, or pavement condition / distress survey (PCI) for functional evaluation; skid-resistance testing for surface friction.
pavement-evaluationbenkelman-beammaintenance
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short6 marks

In a Marshall mix-design test, one compacted specimen gave the following data: mass in air =1230 g= 1230\text{ g}, mass of saturated surface-dry specimen in air =1233 g= 1233\text{ g}, mass in water =705 g= 705\text{ g}. The theoretical maximum specific gravity of the mix (Rice value) Gmm=2.480G_{mm} = 2.480.

(a) Compute the bulk specific gravity GmbG_{mb} of the compacted specimen. [3]

(b) Compute the percentage air voids (VaV_a). [3]

(a) Bulk specific gravity

Using SSD (saturated surface-dry) method:

Gmb=WairWSSDWwater=12301233705=1230528=2.3295.G_{mb} = \frac{W_{air}}{W_{SSD} - W_{water}} = \frac{1230}{1233 - 705} = \frac{1230}{528} = 2.3295. Gmb2.330\boxed{G_{mb} \approx 2.330}

(b) Air voids

Va=(1GmbGmm)×100=(12.32952.480)×100.V_a = \left(1 - \frac{G_{mb}}{G_{mm}}\right) \times 100 = \left(1 - \frac{2.3295}{2.480}\right) \times 100. 2.32952.480=0.93932.\frac{2.3295}{2.480} = 0.93932. Va=(10.93932)×100=0.06068×100=6.07%.V_a = (1 - 0.93932) \times 100 = 0.06068 \times 100 = 6.07\%. Va6.1%\boxed{V_a \approx 6.1\%}

This is slightly above the typical desirable range of 3–5% for a wearing course, indicating the mix may need a small increase in binder content or improved compaction.

bitumenmarshall-mix-designpavement-materials
7short6 marks

A concrete pavement slab of thickness h=220 mmh = 220\text{ mm} has E=3.0×104 MPaE = 3.0 \times 10^4\text{ MPa}, thermal coefficient α=10×106/C\alpha = 10 \times 10^{-6}\,/^\circ\text{C}, and Poisson's ratio μ=0.15\mu = 0.15. The maximum temperature differential between top and bottom of the slab is t=16Ct = 16^\circ\text{C}. For the given slab dimensions the Bradbury warping stress coefficient at the edge is C=0.72C = 0.72.

Compute the edge warping (temperature) stress. [6]

Bradbury edge warping stress

The edge warping stress is

σte=CEαt2.\sigma_{te} = \frac{C\,E\,\alpha\,t}{2}.

Substitute C=0.72C = 0.72, E=3.0×104 MPaE = 3.0\times10^4\text{ MPa}, α=10×106/C\alpha = 10\times10^{-6}\,/^\circ\text{C}, t=16Ct = 16^\circ\text{C}:

Step 1: Eαt=3.0×104×10×106×16E\,\alpha\,t = 3.0\times10^4 \times 10\times10^{-6} \times 16.

  • 3.0×104×10×106=0.303.0\times10^4 \times 10\times10^{-6} = 0.30.
  • 0.30×16=4.80 MPa.0.30 \times 16 = 4.80\text{ MPa}.

Step 2: σte=0.72×4.802=3.4562=1.728 MPa.\sigma_{te} = \dfrac{0.72 \times 4.80}{2} = \dfrac{3.456}{2} = 1.728\text{ MPa}.

σte1.73 MPa\boxed{\sigma_{te} \approx 1.73\text{ MPa}}

Note: The edge formula does not contain μ\mu (Poisson's ratio appears only in the interior warping-stress expression σti=Eαt2(Cx+μCy1μ2)\sigma_{ti} = \frac{E\alpha t}{2}\left(\frac{C_x + \mu C_y}{1-\mu^2}\right)). The slab thickness hh is needed for selecting CC from the ratio L/lL/l but is not in the final edge-stress formula. This warping stress must be combined with the wheel-load stress to check the slab in the most critical season/time of day.

rigid-pavementwarping-stresstemperature-stress
8short6 marks

(a) Sketch (describe) a typical permanent-way cross-section and state the function of each of: rail, sleeper, ballast, and formation. [3]

(b) Define a turnout and explain the terms: switch, crossing (frog), and crossing number NN. For a 1 in N1\text{ in }N crossing, write the relation between the crossing angle and NN. [3]

(a) Permanent-way cross-section and functions

        Rail   Rail
         |      |        <-- rails
   ======================  <-- sleepers (cross-ties)
   \\::::::::::::::::::://   <-- ballast (crib + shoulder)
    \\__________________//
   ----- formation (subgrade) -----
  • Rail: provides a smooth, continuous, hard running surface for wheels; guides the train and transmits wheel loads to the sleepers.
  • Sleeper: holds the two rails at correct gauge, distributes the rail load over a wider area of ballast, and provides resistance against longitudinal and lateral movement.
  • Ballast: transmits and distributes load from sleepers to the formation, provides drainage, holds sleepers in position, and gives elasticity to the track.
  • Formation (subgrade): the prepared earthwork (embankment/cutting) that ultimately bears all the track loads and provides a stable base.

(b) Turnout and components

A turnout is the complete arrangement of points and crossing with lead rails by which a train is diverted from one track to another.

  • Switch (points): a pair of tongue (movable) rails and stock rails that guide the wheels from the main track toward the turnout.
  • Crossing / frog: the assembly (a V-shaped point rail with two wing rails) provided where one rail crosses another to allow wheel flanges to pass.
  • Crossing number NN: defines the flatness of the crossing; a 1 in N1\text{ in }N crossing spreads 1 unit laterally for NN units along the track. A larger NN means a flatter crossing and permits higher speed.

Relation (right-angle / RDSO method):

tanα=1Nα=tan1 ⁣(1N),\tan\alpha = \frac{1}{N} \quad\Rightarrow\quad \alpha = \tan^{-1}\!\left(\frac{1}{N}\right),

where α\alpha is the crossing angle. (By the centre-line method, 2tan(α/2)=1/N2\tan(\alpha/2) = 1/N.)

railway-engineeringtrack-componentsturnout
9short5 marks

(a) State the objectives of tunnel ventilation and name two methods of mechanical (artificial) ventilation. [2]

(b) Briefly explain the New Austrian Tunnelling Method (NATM) and state two situations where it is suitable. [3]

(a) Objectives and methods of tunnel ventilation

Objectives:

  • Supply fresh air (oxygen) to workers and, in service, to passengers.
  • Dilute and remove dust, smoke, blasting fumes and exhaust gases (CO, CO2\text{CO}_2, NOx\text{NO}_x).
  • Control temperature and humidity for comfort and safety; remove heat.
  • Provide smoke control / escape conditions in case of fire.

Two methods of mechanical ventilation:

  1. Longitudinal ventilation (air pushed along the tunnel axis, e.g. by jet fans).
  2. Transverse / semi-transverse ventilation (separate supply and exhaust ducts deliver and extract air across the cross-section). (Blowing-in and exhaust systems are the basic forced types.)

(b) New Austrian Tunnelling Method (NATM)

NATM is an observational, sequential excavation method in which the surrounding rock mass is mobilised as a primary load-bearing ring rather than merely being a load on the lining. The excavation is supported quickly with a flexible primary support — shotcrete, rock bolts, steel ribs/lattice girders and wire mesh — and the deformation/convergence of the opening is continuously monitored (instrumentation). Support is adjusted based on observed behaviour, allowing controlled stress redistribution; a secondary (final) lining is added once movements stabilise.

Two suitable situations:

  1. In weak, jointed or squeezing rock / mixed ground where the rock can still contribute to support if controlled deformation is allowed.
  2. For tunnels of varying or non-circular cross-section (e.g. road/metro tunnels, caverns, station chambers) where rigid mechanised TBM methods are uneconomic or impractical.
tunnel-engineeringventilationconstruction-methods
10short5 marks

(a) With a neat description, classify bridges on any TWO bases and explain the difference between the superstructure and the substructure of a bridge. [3]

(b) Define afflux and economical span of a bridge. Using Lacey's formula, estimate the linear waterway for a design flood discharge of Q=500 m3/sQ = 500\text{ m}^3/\text{s} (take regime perimeter P=4.8QP = 4.8\sqrt{Q}). [2]

(a) Classification and super/sub-structure

Classification (any two bases):

  1. By material: timber, masonry, RCC, prestressed concrete, steel, composite bridges.
  2. By structural form: slab, beam/girder, arch, truss, cantilever, suspension, cable-stayed bridges. (Other bases: by function — road, rail, pedestrian, aqueduct; by span length; by inter-span continuity — simply supported, continuous; by alignment — square/skew.)

Superstructure vs substructure:

  • Superstructure: the portion above the bearings — deck slab, girders/trusses, parapets — that directly carries the moving (live) and dead loads and transmits them to the supports.
  • Substructure: the portion below the bearings — abutments, piers, and their foundations — that receives the load from the superstructure and transfers it safely to the founding strata, also resisting water/earth pressure and scour.

(b) Afflux, economical span, and Lacey waterway

  • Afflux: the rise (heading-up) of the upstream water level above the normal flood level caused by the contraction of the natural waterway by the bridge piers and abutments.
  • Economical span: the span for which the total cost of the bridge is minimum — approximately the span at which the cost of one span of the superstructure equals the cost of one pier/substructure (the substructure cost equals the superstructure cost per span).

Lacey's regime (linear) waterway:

P=4.8Q=4.8×500=4.8×22.3607=107.3 m.P = 4.8\sqrt{Q} = 4.8 \times \sqrt{500} = 4.8 \times 22.3607 = 107.3\text{ m}. Linear waterway107.3 m\boxed{\text{Linear waterway} \approx 107.3\text{ m}}
bridge-engineeringbridge-componentswaterway
11short7 marks

A pavement section carries the following daily axle-load spectrum (one direction). Using the IRC/AASHTO fourth-power law, compute the Vehicle Damage Factor (VDF) — i.e., the equivalent standard axles (of 80 kN) per commercial vehicle — for this mix. Take the standard axle as 80 kN.

Axle groupAxle load (kN)Number of axles per day
Single100200
Single80300
Single60500

Assume the daily commercial-vehicle count is 500 (i.e., these 1000 axles belong to 500 vehicles, averaging 2 axles per vehicle). [7]

Fourth-power equivalency law

The load equivalency factor (LEF) for an axle of load LL relative to the standard 80 kN axle is

LEF=(L80)4.\text{LEF} = \left(\frac{L}{80}\right)^4.

Total equivalent standard axles (ESAL) per day = niLEFi\sum n_i \,\text{LEF}_i.

Step 1 – LEF for each group.

  • 100 kN: (100/80)4=(1.25)4=2.44141.(100/80)^4 = (1.25)^4 = 2.44141.
  • 80 kN: (80/80)4=1.0000.(80/80)^4 = 1.0000.
  • 60 kN: (60/80)4=(0.75)4=0.31641.(60/80)^4 = (0.75)^4 = 0.31641.

Step 2 – ESAL contribution of each group.

Axle loadLEFNumber/dayESAL/day
100 kN2.44141200488.28
80 kN1.00000300300.00
60 kN0.31641500158.20
Total1000946.48

Details:

  • 200×2.44141=488.28200 \times 2.44141 = 488.28
  • 300×1.0=300.00300 \times 1.0 = 300.00
  • 500×0.31641=158.20500 \times 0.31641 = 158.20
  • Sum =488.28+300.00+158.20=946.48= 488.28 + 300.00 + 158.20 = 946.48 standard axles/day.

Step 3 – Vehicle Damage Factor. VDF = (equivalent standard axles per day) / (number of commercial vehicles per day)

VDF=946.48500=1.893.VDF = \frac{946.48}{500} = 1.893. Total 946.5 ESAL/day,VDF1.89 standard axles per commercial vehicle\boxed{\text{Total } \approx 946.5 \text{ ESAL/day}, \quad VDF \approx 1.89 \text{ standard axles per commercial vehicle}}
flexible-pavementesalaxle-load-equivalency

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Transportation Engineering II (IOE, CE 704) question paper 2078?
The full BE Civil Engineering (IOE, TU) Transportation Engineering II (IOE, CE 704) 2078 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Transportation Engineering II (IOE, CE 704) 2078 paper come with solutions?
Yes. Every question on this Transportation Engineering II (IOE, CE 704) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Transportation Engineering II (IOE, CE 704) 2078 paper?
The BE Civil Engineering (IOE, TU) Transportation Engineering II (IOE, CE 704) 2078 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Transportation Engineering II (IOE, CE 704) past paper free?
Yes — reading and attempting this Transportation Engineering II (IOE, CE 704) past paper on Kekkei is completely free.