Browse papers
A

Section A: Long Answer Questions

Attempt all questions.

5 questions
1long10 marks

Explain the historical development of highways with reference to the contributions of Tresaguet, Telford and Macadam. Discuss the four stages of road development in chronological order. A district has the following data for highway network planning by the saturation system: number of villages with population groups and assigned utility units are given below.

Population rangeNo. of villagesUtility units per village
5001 and above44
2001 – 500093
1001 – 2000162
500 – 1000301

Two alternative road alignments are proposed:

  • Alignment X: length 22 km, serves villages giving a total utility of 64 units.
  • Alignment Y: length 30 km, serves villages giving a total utility of 80 units.

Determine the utility per unit length for each alignment and recommend which should be constructed first.

Historical development

Tresaguet (France, ~1764): First scientific road. Cross-section of about 30 cm thickness with a sub-base of large foundation stones laid on edge, an intermediate layer of smaller broken stones, and a wearing surface of gravel. Emphasised subgrade drainage and cross-slope.

Telford (England, ~1820): Provided a flat subgrade and built a stone foundation (large flat stones hand-set), increasing thickness towards the centre to give a cambered surface (about 1 in 90). Heavy, expensive but durable; drainage by side ditches.

Macadam (England, ~1827): Recognised that the subgrade itself carries the load if kept dry. Used a compacted subgrade raised above ground with cross-slope, then layers of broken angular stone of small uniform size (< 25 mm) compacted by traffic — the first economical, well-graded construction (the basis of water-bound macadam).

Four stages of road development (Highway Development Plans)

  1. Nagpur Road Plan (first 20-year plan) — classified roads as National Highways, State Highways, Major District Roads, Other District Roads and Village Roads; based on star-and-grid pattern.
  2. Bombay Road Plan (second 20-year plan) — aimed to double road density; introduced expressways.
  3. Lucknow Road Plan (third 20-year plan) — target road length tied to population and area.
  4. Road Development Plan / Vision documents — modern stage emphasising network optimisation, expressways and rural connectivity. (In the Nepalese context the analogous stages are reflected in successive National Transport / Road Master Plans.)

Saturation-system computation (utility per unit length)

The saturation (maximum-utility) system ranks roads by utility obtained per unit length:

Utility per km=Total utility units servedLength of alignment\text{Utility per km} = \frac{\text{Total utility units served}}{\text{Length of alignment}}

Alignment X:

6422=2.91 units/km\frac{64}{22} = 2.91\ \text{units/km}

Alignment Y:

8030=2.67 units/km\frac{80}{30} = 2.67\ \text{units/km}

Recommendation

Alignment X gives the higher utility per unit length (2.91 > 2.67 units/km), so under the saturation system Alignment X should be constructed first as it provides maximum service per kilometre of road built.

highway-developmenthighway-planningsaturation-system
2long8 marks

Define stopping sight distance (SSD) and state the factors affecting it. Derive the expression for SSD on a gradient. A two-lane highway is designed for a speed of 65 km/h. Using a total reaction (perception–brake) time of 2.5 s, a longitudinal coefficient of friction of 0.36, and an upgrade of 3%, compute the stopping sight distance. Comment on how the result would change on a 3% downgrade.

Definition

Stopping sight distance is the minimum sight distance available to a driver travelling at design speed to safely stop the vehicle without colliding with a stationary object on the road. It equals the lag (reaction) distance plus the braking distance.

Factors affecting SSD: design speed, reaction time of driver, friction (tyre–pavement) condition, gradient of the road, condition of brakes/vehicle, and presence of rain/wet surface.

Derivation on a gradient

Let vv = speed in m/s, tt = total reaction time, ff = longitudinal friction coefficient, gg = grade as a fraction (+ for up, − for down).

Lag distance =vt= v\,t.

During braking, energy dissipated by friction plus work against gravity:

12mv2=mg0(f±n)dbdb=v22g0(f±n)\tfrac{1}{2}m v^2 = m g_0 (f \pm n) d_b \quad\Rightarrow\quad d_b = \frac{v^2}{2\,g_0\,(f \pm n)}

where g0=9.81 m/s2g_0 = 9.81\ \text{m/s}^2 and nn = grade fraction (+ up, − down).

SSD=vt+v22g0(f±n)\boxed{SSD = v\,t + \frac{v^2}{2\,g_0\,(f \pm n)}}

Numerical (V = 65 km/h, t = 2.5 s, f = 0.36, +3%)

v=653.6=18.06 m/sv = \frac{65}{3.6} = 18.06\ \text{m/s}

Lag distance:

vt=18.06×2.5=45.14 mv t = 18.06 \times 2.5 = 45.14\ \text{m}

Braking distance (upgrade, use f+n=0.36+0.03=0.39f+n = 0.36 + 0.03 = 0.39):

db=18.0622×9.81×0.39=326.27.652=42.63 md_b = \frac{18.06^2}{2 \times 9.81 \times 0.39} = \frac{326.2}{7.652} = 42.63\ \text{m}

SSD:

SSD=45.14+42.63=87.77 mSSD = 45.14 + 42.63 = 87.77\ \text{m}

SSD ≈ 87.8 m (upgrade).

Comment on a 3% downgrade

On a downgrade, gravity assists motion so fn=0.360.03=0.33f - n = 0.36 - 0.03 = 0.33, giving a larger braking distance:

db=326.22×9.81×0.33=50.38 m,SSD=45.14+50.38=95.5 m.d_b = \frac{326.2}{2\times9.81\times0.33} = 50.38\ \text{m},\quad SSD = 45.14 + 50.38 = 95.5\ \text{m}.

Thus the downgrade requires a longer SSD (≈ 95.5 m); for design of two-way roads the worst (downgrade) value governs.

sight-distancestopping-sight-distancegeometric-design
3long8 marks

Explain why summit (crest) vertical curves are designed for sight distance rather than comfort, and why valley (sag) curves are governed by headlight distance and comfort. An ascending grade of +3% meets a descending grade of −2% at a summit. Design the length of the summit curve for a stopping sight distance of 120 m, taking driver eye height = 1.2 m and object height = 0.15 m. Check both cases (L>SL>S and L<SL<S) and adopt the correct length.

Why summit curves are designed for sight distance

On a summit curve the road surface itself obstructs the driver's line of sight; centrifugal force acts upward, relieving pressure on springs, so passenger discomfort is not critical. The governing criterion is therefore adequate sight distance (SSD, and OSD where overtaking is allowed).

On a valley (sag) curve, in daylight there is no sight obstruction, but at night the headlight beam limits the visible distance; also centrifugal force acts downward, adding to gravity and causing discomfort/impact. Hence valley curves are designed for headlight sight distance and rider comfort.

Data

Deviation (algebraic difference) of grades:

N=+0.03(0.02)=0.05N = +0.03 - (-0.02) = 0.05

SSD, S=120 mS = 120\ \text{m}, H=1.2 mH = 1.2\ \text{m} (eye), h=0.15 mh = 0.15\ \text{m} (object).

Denominator constant:

(2H+2h)2=(2.4+0.30)2=(1.549+0.548)2=4.40\left(\sqrt{2H}+\sqrt{2h}\right)^2 = \left(\sqrt{2.4}+\sqrt{0.30}\right)^2 = (1.549+0.548)^2 = 4.40

Case 1: L>SL > S

L=NS2(2H+2h)2=0.05×12024.40=7204.40=163.6 mL = \frac{N S^2}{\left(\sqrt{2H}+\sqrt{2h}\right)^2} = \frac{0.05 \times 120^2}{4.40} = \frac{720}{4.40} = 163.6\ \text{m}

Check: L=163.6 m>S=120 mL = 163.6\ \text{m} > S = 120\ \text{m}valid.

Case 2: L<SL < S

L=2S(2H+2h)2N=2(120)4.400.05=24088=152.0 mL = 2S - \frac{\left(\sqrt{2H}+\sqrt{2h}\right)^2}{N} = 2(120) - \frac{4.40}{0.05} = 240 - 88 = 152.0\ \text{m}

Check: L=152.0 m>S=120 mL = 152.0\ \text{m} > S = 120\ \text{m}invalid (contradicts assumption L<SL<S).

Adopted length

Only Case 1 is consistent, so the design length of the summit curve = 163.6 m (≈ 164 m).

vertical-alignmentsummit-curvesight-distance
4long8 marks

A horizontal curve on a state highway is to be designed for a speed of 80 km/h. Take maximum superelevation = 0.07 and design coefficient of lateral friction = 0.15.

(a) Determine the minimum radius of the horizontal curve.

(b) For the radius found in (a), compute the length of transition curve by the rate-of-change-of-centrifugal-acceleration method, taking the allowable rate C=8075+VC = \dfrac{80}{75+V}.

(c) Also find the transition length required to introduce the superelevation at a rate of 1 in 150 (rotation about the centre line), given carriageway width = 7.0 m and extra widening = 0.9 m. Adopt the governing transition length.

(a) Minimum radius

Rmin=V2127(e+f)=802127(0.07+0.15)=6400127×0.22=640027.94=229.1 mR_{min} = \frac{V^2}{127\,(e+f)} = \frac{80^2}{127\,(0.07+0.15)} = \frac{6400}{127 \times 0.22} = \frac{6400}{27.94} = 229.1\ \text{m}

Rmin229 mR_{min} \approx 229\ \text{m} (adopt R=229 mR = 229\ \text{m}).

(b) Transition length by rate of change of radial acceleration

Allowable rate:

C=8075+V=8075+80=80155=0.516 m/s3(0.5C0.8 OK)C = \frac{80}{75+V} = \frac{80}{75+80} = \frac{80}{155} = 0.516\ \text{m/s}^3 \quad (0.5 \le C \le 0.8\ \text{OK}) Ls=0.0215V3CR=0.0215×8030.516×229=0.0215×512000118.2=11008118.2=93.1 mL_s = \frac{0.0215\,V^3}{C\,R} = \frac{0.0215 \times 80^3}{0.516 \times 229} = \frac{0.0215 \times 512000}{118.2} = \frac{11008}{118.2} = 93.1\ \text{m}

Ls93.1 mL_s \approx 93.1\ \text{m}.

(c) Transition length for rate of introduction of superelevation

For rotation about the centre line, the outer edge is raised by e(W+We)/2e\,(W+W_e)/2 relative to the centre. Total width =W+We=7.0+0.9=7.9 m= W + W_e = 7.0 + 0.9 = 7.9\ \text{m}. Rise of outer edge above centre line:

Δ=e(W+We)2=0.07×7.92=0.2765 m\Delta = \frac{e\,(W+W_e)}{2} = \frac{0.07 \times 7.9}{2} = 0.2765\ \text{m}

At a longitudinal slope of 1 in 150:

Ls=150×Δ=150×0.2765=41.5 mL_s = 150 \times \Delta = 150 \times 0.2765 = 41.5\ \text{m}

Ls41.5 mL_s \approx 41.5\ \text{m}.

Governing transition length

The largest of the computed values governs:

Ls=max(93.1, 41.5)=93.1 mL_s = \max(93.1,\ 41.5) = 93.1\ \text{m}

Adopt transition length Ls95 mL_s \approx 95\ \text{m} (rounded up for design).

horizontal-alignmentsuperelevationtransition-curve
5long8 marks

Define traffic volume, traffic density and space-mean speed, and state the fundamental relation between them. The Greenshields linear speed–density model for a single lane is given as

v=70(1k200)v = 70\left(1 - \frac{k}{200}\right)

where vv is in km/h and kk in veh/km. Determine (a) the free-flow speed and jam density, (b) the expression for flow qq in terms of kk, (c) the maximum flow (capacity) and the speed and density at which it occurs.

Definitions

  • Traffic volume (flow), qq: the number of vehicles passing a section of road per unit time (veh/h).
  • Traffic density (concentration), kk: the number of vehicles present per unit length of road at an instant (veh/km).
  • Space-mean speed, vv: the average speed of vehicles obtained by averaging over the vehicles occupying a length of road (harmonic mean of spot speeds).

Fundamental relation:   q=k×v.\;q = k \times v.

(a) Free-flow speed and jam density

Given v=70(1k200)v = 70\left(1 - \dfrac{k}{200}\right).

  • Free-flow speed vfv_f occurs at k=0k = 0:   vf=70 km/h.\;v_f = 70\ \text{km/h}.
  • Jam density kjk_j occurs at v=0v = 0:   0=70(1kj/200)kj=200 veh/km.\;0 = 70(1 - k_j/200) \Rightarrow k_j = 200\ \text{veh/km}.

(b) Flow in terms of density

q=kv=70k(1k200)=70k70k2200=70k0.35k2q = k\,v = 70k\left(1 - \frac{k}{200}\right) = 70k - \frac{70k^2}{200} = 70k - 0.35k^2

(c) Maximum flow (capacity)

Maximum flow occurs where dqdk=0\dfrac{dq}{dk}=0:

dqdk=700.70k=0ko=100 veh/km\frac{dq}{dk} = 70 - 0.70k = 0 \Rightarrow k_o = 100\ \text{veh/km}

This is kj/2k_j/2, as expected for the Greenshields model. The corresponding speed:

vo=70(1100200)=35 km/h(=vf/2)v_o = 70\left(1 - \frac{100}{200}\right) = 35\ \text{km/h}\quad(= v_f/2)

Maximum (capacity) flow:

qmax=kovo=100×35=3500 veh/hq_{max} = k_o\,v_o = 100 \times 35 = 3500\ \text{veh/h}

Capacity qmax=3500 veh/hq_{max} = 3500\ \text{veh/h}, occurring at k=100 veh/kmk = 100\ \text{veh/km} and v=35 km/hv = 35\ \text{km/h}.

traffic-engineeringtraffic-studiesspeed-flow-density
B

Section B: Short Answer Questions

Attempt all questions.

6 questions
6short6 marks

Why is extra widening of pavement provided on horizontal curves? A two-lane road (n=2n = 2) has a curve of radius 80 m designed for 70 km/h. Taking the longest wheelbase l=6 ml = 6\ \text{m}, compute the mechanical widening, psychological widening and total extra widening.

Need for extra widening

Extra widening is provided on horizontal curves because:

  1. A vehicle's rear wheels track inside the front wheels on a curve (off-tracking), so the vehicle occupies a wider path — mechanical widening.
  2. Drivers tend to keep a greater clearance from the edge and from other vehicles at curves and steer erratically — psychological widening.

Mechanical widening

Wm=nl22R=2×622×80=72160=0.45 mW_m = \frac{n\,l^2}{2R} = \frac{2 \times 6^2}{2 \times 80} = \frac{72}{160} = 0.45\ \text{m}

Psychological widening

Wps=V2.64R=702.6480=702.64×8.944=7023.61=2.96 mW_{ps} = \frac{V}{2.64\sqrt{R}} = \frac{70}{2.64\sqrt{80}} = \frac{70}{2.64 \times 8.944} = \frac{70}{23.61} = 2.96\ \text{m}

Total extra widening

We=Wm+Wps=0.45+2.96=3.41 mW_e = W_m + W_{ps} = 0.45 + 2.96 = 3.41\ \text{m}

Total extra widening We3.41 mW_e \approx 3.41\ \text{m} (mechanical 0.45 m + psychological 2.96 m).

horizontal-alignmentextra-wideninggeometric-design
7short6 marks

Sketch and label the components of overtaking sight distance (OSD) on a two-lane two-way road. Compute the OSD for a design speed of 70 km/h, taking the speed of the overtaken (slow) vehicle as 16 km/h less than design speed, reaction time of the overtaking driver t=2 st = 2\ \text{s}, and average acceleration of the overtaking vehicle a=0.92 m/s2a = 0.92\ \text{m/s}^2. Include the distance for the opposing vehicle.

Components of OSD

For a two-way road the OSD has three parts:

  d1            d2                       d3
|----|---------------------------|---------------------|
 A1   <- overtaking manoeuvre ->        opposing vehicle
  • d1d_1 — distance travelled by the overtaking vehicle during the reaction time at the speed of the slow vehicle.
  • d2d_2 — distance travelled during the actual overtaking manoeuvre (slow-vehicle speed × manoeuvre time + 2× spacing).
  • d3d_3 — distance travelled by an opposing vehicle (at design speed) during the manoeuvre time.
OSD=d1+d2+d3OSD = d_1 + d_2 + d_3

Data

V=70 km/hv=19.44 m/sV = 70\ \text{km/h} \Rightarrow v = 19.44\ \text{m/s}. Speed of overtaken vehicle Vb=7016=54 km/hvb=15.0 m/sV_b = 70 - 16 = 54\ \text{km/h} \Rightarrow v_b = 15.0\ \text{m/s}. t=2 st = 2\ \text{s}, a=0.92 m/s2a = 0.92\ \text{m/s}^2.

d1d_1 (reaction)

d1=vbt=15.0×2=30.0 md_1 = v_b\,t = 15.0 \times 2 = 30.0\ \text{m}

Spacing and manoeuvre time

Minimum spacing: s=0.2vb+6=0.2(15.0)+6=9.0 ms = 0.2 v_b + 6 = 0.2(15.0) + 6 = 9.0\ \text{m}. Manoeuvre time:

T=4sa=4×9.00.92=39.13=6.26 sT = \sqrt{\frac{4s}{a}} = \sqrt{\frac{4 \times 9.0}{0.92}} = \sqrt{39.13} = 6.26\ \text{s}

d2d_2 (overtaking manoeuvre)

d2=vbT+2s=15.0×6.26+2(9.0)=93.9+18.0=111.9 md_2 = v_b\,T + 2s = 15.0 \times 6.26 + 2(9.0) = 93.9 + 18.0 = 111.9\ \text{m}

d3d_3 (opposing vehicle)

d3=vT=19.44×6.26=121.7 md_3 = v\,T = 19.44 \times 6.26 = 121.7\ \text{m}

Overtaking sight distance

OSD=30.0+111.9+121.7=263.6 mOSD = 30.0 + 111.9 + 121.7 = 263.6\ \text{m}

OSD ≈ 263.6 m (≈ 264 m).

overtaking-sight-distancesight-distancetwo-lane-road
8short6 marks

List the desirable properties of road aggregates and name the laboratory test used to assess each property. Explain the Los Angeles abrasion test and state its significance. If a sample of 5000 g of aggregate after the abrasion test retains 3850 g on the 1.7 mm sieve, compute the abrasion value and comment on its suitability for surface course (maximum permitted = 30%).

Desirable properties of aggregates and corresponding tests

Property requiredReasonTest
Strength (crushing resistance)resist wheel loadsAggregate Crushing Value test
Hardness (abrasion resistance)resist rubbing by trafficLos Angeles Abrasion test
Toughness (impact resistance)resist impact loadsAggregate Impact Value test
Durability (weather resistance)resist alternate wetting/drying, frostSoundness test
Shape (good interlock)stability of mixFlakiness & Elongation Index
Adhesion with bitumenresist strippingStripping value test
Water absorption / specific gravityquality & mix designSpecific gravity & absorption test

Los Angeles abrasion test

A specified mass of graded aggregate is placed in a hollow steel drum together with a charge of standard steel balls (abrasive charge). The drum is rotated for a specified number of revolutions (typically 500–1000). The combined action of impact and grinding between the aggregate and the steel balls causes wear. After the test the sample is sieved on the 1.7 mm sieve; the material passing the sieve represents the wear.

Significance: It measures the resistance of aggregate to abrasion/wear under traffic. A low LA abrasion value indicates a hard, durable aggregate suitable for wearing courses.

Calculation

Abrasion value=Mass passing 1.7 mmOriginal mass×100\text{Abrasion value} = \frac{\text{Mass passing 1.7 mm}}{\text{Original mass}} \times 100

Mass passing =50003850=1150 g= 5000 - 3850 = 1150\ \text{g}.

Abrasion value=11505000×100=23%\text{Abrasion value} = \frac{1150}{5000} \times 100 = 23\%

Comment

The abrasion value 23% < 30% (permitted maximum for surface/wearing course), so the aggregate is satisfactory for use in the surface course.

highway-materialsaggregate-testspavement-materials
9short5 marks

What is the role of bitumen as a binder in flexible pavements? Briefly describe any three standard tests on bitumen and state what each indicates. Differentiate between penetration grade and viscosity grade of bitumen.

Role of bitumen

Bitumen is a black, viscous, thermoplastic hydrocarbon used as a binder in flexible pavements. It coats the aggregate, binds the mineral particles together, provides waterproofing, and imparts flexibility so that the surfacing can withstand traffic loads and temperature variations without cracking.

Three standard tests on bitumen

  1. Penetration test — measures the depth (in 1/10 mm) to which a standard needle penetrates the bitumen in 5 s at 25 °C under a 100 g load. Indicates the consistency/hardness of bitumen; lower penetration = harder grade.
  2. Softening point (Ring and Ball) test — the temperature at which the bitumen attains a specified softness (ball falls 25 mm). Indicates temperature susceptibility; a higher softening point is better for hot climates.
  3. Ductility test — the distance (in cm) a standard briquette of bitumen stretches before breaking at 27 °C. Indicates the ability to deform without cracking (flexibility/adhesion). Minimum is usually 50 cm. (Other tests: viscosity, flash & fire point, specific gravity, loss on heating.)

Penetration grade vs viscosity grade

AspectPenetration gradeViscosity grade
Basis of gradingPenetration value at 25 °C (e.g. 60/70, 80/100)Absolute/kinematic viscosity (e.g. VG-10, VG-30, VG-40)
Property controlledConsistency at one temperatureConsistency over a temperature range
Temperature sensitivityNot directly accountedBetter characterises behaviour at high & low temperatures
ReliabilityOlder, simpler methodMore rational, performance-related
highway-materialsbitumenbinder-tests
10short5 marks

Define Passenger Car Unit (PCU) and explain its purpose. A 15-minute traffic count on a single carriageway recorded the following: cars 240, two-wheelers 180, buses 30, trucks 24. Using PCU factors car = 1.0, two-wheeler = 0.5, bus = 3.0, truck = 3.0, compute the flow in PCU/h.

Passenger Car Unit (PCU)

A PCU is a factor that expresses the relative interference/space requirement of different vehicle types in terms of an equivalent number of passenger cars. It converts a mixed (heterogeneous) traffic stream into an equivalent homogeneous flow so that capacity, level of service and design volumes can be assessed on a common basis. The PCU value of a vehicle depends on its size, speed, manoeuvrability and the traffic/roadway conditions.

Computation

Convert the 15-minute counts to PCU:

VehicleCountPCU factorPCU (15 min)
Car2401.0240.0
Two-wheeler1800.590.0
Bus303.090.0
Truck243.072.0
Total492.0

Flow in 15 minutes =492 PCU= 492\ \text{PCU}.

Convert to hourly flow (multiply by 4):

q=492×4=1968 PCU/hq = 492 \times 4 = 1968\ \text{PCU/h}

Flow = 1968 PCU/h.

traffic-engineeringpcutraffic-volume-study
11short10 marks

Write short notes on any TWO of the following:

(a) Requirements of an ideal highway alignment and the factors controlling it.

(b) Elements of a typical highway cross-section (with a labelled sketch) — carriageway, shoulder, camber, right of way, kerb and side drains.

(c) The engineering surveys carried out before finalising a highway alignment (map study, reconnaissance, preliminary survey, final location & detailed survey).

(Attempt any two; each note carries 5 marks.)

(a) Requirements of an ideal highway alignment

An ideal alignment should be:

  • Short — a straight alignment between terminals gives the least length and cost (subject to other constraints).
  • Easy — easy to construct, maintain and for vehicles to operate; gentle gradients and curves.
  • Safe — safe geometric elements (adequate sight distance, safe curves and gradients) and a stable alignment from the embankment/cut-slope point of view.
  • Economical — least overall cost considering construction, maintenance and vehicle operation.

Factors controlling alignment: obligatory points (through which the road must/must not pass), traffic demand, geometric design requirements, economics, nature of terrain/gradient, drainage and water-table, geology and soil, political/administrative considerations, and environmental factors.

(b) Elements of a highway cross-section

 |<----------- Right of Way ----------->|
 |   side    shoulder  carriageway  shoulder   side  |
 |   drain  |        |____________|        |  drain  |
 |   \__/   |_______/   camber     \_______|   \__/  |
              (slopes from crown to edges)
  • Carriageway: the paved width used by vehicles; width depends on number and width of lanes.
  • Shoulder: the strips on either side of the carriageway for emergency stopping and lateral support; usually surfaced more roughly than the carriageway.
  • Camber (cross-slope): the transverse slope (e.g. 2–2.5%) given to the surface to drain rain water to the sides.
  • Right of way: the total land width acquired for the road including future widening, utilities and drains.
  • Kerb: the boundary between the carriageway and the shoulder/footpath (low, mountable or barrier type).
  • Side drains: longitudinal drains/ditches alongside the road to collect and carry away surface and subsurface water.

(c) Engineering surveys for highway location

  1. Map study: topographic maps are studied to identify possible alignment corridors, obligatory points, ridge/valley lines and approximate gradients.
  2. Reconnaissance survey: a field inspection of the corridors identified from the map study; rough data on terrain, soil, drainage, obstacles and existing roads are collected to drop unfeasible alternatives.
  3. Preliminary survey: detailed instrument survey of the selected alternatives — topographic, soil, drainage and traffic data are collected, alternative alignments are compared technically and economically, and the best is selected.
  4. Final location and detailed survey: the chosen centre line is pegged on the ground (centre-line/location survey) and detailed levelling, cross-sections, drainage and soil data are collected for preparation of working drawings and estimates.
highway-alignmenthighway-cross-sectionengineering-surveys

Frequently asked questions

Where can I find the BE Civil Engineering (IOE, TU) Transportation Engineering I (IOE, CE 652) question paper 2076?
The full BE Civil Engineering (IOE, TU) Transportation Engineering I (IOE, CE 652) 2076 (regular) question paper is available free on Kekkei. You can read every question online and attempt the paper under timed exam conditions.
Does the Transportation Engineering I (IOE, CE 652) 2076 paper come with solutions?
Yes. Every question on this Transportation Engineering I (IOE, CE 652) past paper includes a step-by-step solution, plus instant AI feedback when you attempt it on Kekkei.
How many marks is the BE Civil Engineering (IOE, TU) Transportation Engineering I (IOE, CE 652) 2076 paper?
The BE Civil Engineering (IOE, TU) Transportation Engineering I (IOE, CE 652) 2076 paper carries 80 full marks and is meant to be completed in 180 minutes, across 11 questions.
Is practising this Transportation Engineering I (IOE, CE 652) past paper free?
Yes — reading and attempting this Transportation Engineering I (IOE, CE 652) past paper on Kekkei is completely free.